Number on map
|
X
|
Y
|
Comments
|
1
|
226,614
|
729,594
|
|
2
|
246,249
|
718,970
|
|
3
|
246,000
|
711,000
|
|
4
|
244,869
|
711,000
|
|
5
|
246,002
|
707,000
|
|
6
|
251,595
|
707,000
|
|
7
|
251,566
|
699,431
|
To point 8 along the Green line
|
8
|
243,191
|
702,137
|
|
9
|
240,189
|
704,361
|
|
10
|
239,490
|
714,378
|
|
11
|
236,101
|
715,506
|
|
12
|
232,185
|
714,068
|
|
13
|
231,441
|
713,501
|
To point 14 along the Green line
|
14
|
221,049
|
717,386
|
|
15
|
217,681
|
721,404
|
|
16
|
219,463
|
726,571
|
●
|
The area of the license is defined solely by the above stated coordinates (see the term above, we use a coordinate system rather than waypoints). It is hereby specified that in the event of a discrepancy between maps submitted by the Licensee and the above description, then the coordinates prevail.
|
●
|
Granting of this license shall not make redundant receiving any permit, confirmation or license from any public body or other as required by law. In addition this license shall not be deemed to make redundant arranging all aspects necessary by law through any public or private body.
|
No.
|
ACTIVITY DESCRIPION
|
PROJECTED TO
BE CARRIED
OUT BY:
|
1
|
Sign agreement with seismic contractor for reprocessing of 2-4 existing seismic lines and following the results, reprocess further 6 seismic lines, and provide the commissioner with the contractor agreement
|
1 March 2014
|
2
|
Field viability investigation of conducting seismic in Jezreel Valley and provide the report to the commissioner
|
1 March 2014
|
3
|
Sign agreement with geophysical contractor to conduct 2D seismic reflection survey, based on the viability investigation results, with minimum of 30 km, and provide the commissioner with the contractor agreement
|
1 April 2014
|
4
|
RockEval of organic rich rocks of En Zetim Formation samples for identifying the potential for oil generation, and submit report on results
|
1 April 2014
|
5
|
Geological basin analysis based on existing available data, including burial history, maturity and oil generation conditions modeling, and submit report on results
|
1 June 2014
|
6
|
Finalize reprocessing of 2-8 seismic lines (according to stage 1 of the program) and submit the reprocessed results and a report, based on the instructions on the Ministry of National Infrastructures, Energy and Water Resources website, under "Delivery of seismic data guidelines"
|
1 September 2014
|
7
|
2D reflection seismic survey acquisition in Jezreel Valley (according to stage 3 of the work plan)
|
1 December 2014
|
8
|
Submit the 2D reflection seismic survey results, including QA/QC of seismic acquisition, report of field data and all accompanying reports, as defined by the "Delivery of seismic data guidelines” that appear on the Ministry of National Infrastructures, Energy and Water Resources website.
|
6 weeks after
seismic
acquisition
is completed
|
9
|
Seismic data processing of the new acquired data, and submit the processing results and reports, based on the instructions on the "Delivery of seismic data guidelines"
|
1 March 2015
|
10
|
Seismic interpretation of reprocessed seismic lines and new acquired seismic lines, including mapping of at least 4 significant seismic horizons, and preparing time and depth structural maps along the license area,
and submit geophysical summary report
|
1 June 2015
|
11
|
Submit a drilling prospect, to include the proposed well location, geological and geophysical description of the well targets, with geological forecast and an initial engineering plan
|
1 July 2015
|
12
|
Submit a resource assessment report prepared by an authorized independent firm (Competent Person Report), in accordance with the Petroleum Resources Management System (PRMS), and submit to the commissioner
|
1 September 2015
|
13
|
Submit an environmental document, based on the Petroleum Regulations (deviation permission from the planning and building law), 2012
|
1 October 2015
|
14
|
Sign a contract with a drilling contractor, and provide the commissioner with the contractor agreement
|
1 October 2015
|
15
|
Submit a detained engineering plan for performing the drilling
|
1 October 2015
|
16
|
Spud a well within the license area
to proposed total depth of 4,000 meters (13,124 ft.)
|
1 December 2015
|
17
|
Submit a final report of the drilling results
|
1 September 2016
|
18
|
Submit a continued work plan within the license area
(future license development)
|
1 October 2016
|