Table of Contents                                                                                 

 


UNITED STATES
SECURITIES AND EXCHANGE COMMISSION
Washington, D.C. 20549

FORM 10-Q

(MARK ONE)
x QUARTERLY REPORT PURSUANT TO SECTION 13, 15(d), OR 37 OF THE
SECURITIES EXCHANGE ACT OF 1934
For the quarterly period ended December 31, 2016
OR
  o TRANSITION REPORT PURSUANT TO SECTION 13 OR 15(d) OF
THE SECURITIES EXCHANGE ACT OF 1934
For the transition period from _____ to _____

Commission file number 000-52313
TVA-LOGOA10.JPG
TENNESSEE VALLEY AUTHORITY
(Exact name of registrant as specified in its charter)
A corporate agency of the United States created by an act of Congress
 (State or other jurisdiction of incorporation or organization)
 
62-0474417
 (IRS Employer Identification No.)
 
400 W. Summit Hill Drive
Knoxville, Tennessee
 (Address of principal executive offices)
 
37902
 (Zip Code)
(865) 632-2101
(Registrant’s telephone number, including area code)

None
(Former name, former address and former fiscal year, if changed since last report)

Indicate by check mark whether the registrant (1) has filed all reports required to be filed by Section 13, 15(d), or 37 of the Securities Exchange Act of 1934 during the preceding 12 months (or for such shorter period that the registrant was required to file such reports), and (2) has been subject to such filing requirements for the past 90 days.
Yes x No o

Indicate by check mark whether the registrant has submitted electronically and posted on its corporate Web site, if any, every Interactive Data File required to be submitted and posted pursuant to Rule 405 of Regulation S-T (§232.405 of this chapter) during the preceding 12 months (or for such shorter period that the registrant was required to submit and post such files).
Yes x No o

Indicate by check mark whether the registrant is a large accelerated filer, an accelerated filer, a non-accelerated filer, or a smaller reporting company.  See the definitions of “large accelerated filer,” “accelerated filer,” and “smaller reporting company” in Rule 12b-2 of the Exchange Act.  (Check one):
Large accelerated filer   o                                                                                     Accelerated filer o
Non-accelerated filer     x                                                                                   Smaller reporting company   o
(Do not check if a smaller reporting company)

Indicate by check mark whether the registrant is a shell company (as defined in Rule 12b-2 of the Exchange Act).
Yes o    No x
 

1

Table of Contents                                                                                 

Table of Contents
 
 
 
 
GLOSSARY OF COMMON ACRONYMS ......................................................................................................................................
FORWARD-LOOKING INFORMATION .........................................................................................................................................
GENERAL INFORMATION ............................................................................................................................................................
 
 
 
 
 
ITEM 1. FINANCIAL STATEMENTS .............................................................................................................................................
Consolidated Statements of Operations (unaudited) ............................................................................................................
Consolidated Statements of Comprehensive Income (Loss) (unaudited).............................................................................
Consolidated Balance Sheets (unaudited) ............................................................................................................................
Consolidated Statements of Cash Flows (unaudited) ...........................................................................................................
Consolidated Statements of Changes in Proprietary Capital (unaudited) .............................................................................
Notes to Consolidated Financial Statements (unaudited) .....................................................................................................
 
 
Executive Overview ...............................................................................................................................................................
Results of Operations ............................................................................................................................................................
Liquidity and Capital Resources ............................................................................................................................................
Key Initiatives and Challenges..............................................................................................................................................
Environmental Matters..........................................................................................................................................................
Legal Proceedings................................................................................................................................................................
Off-Balance Sheet Arrangements.........................................................................................................................................
Critical Accounting Policies and Estimates ...........................................................................................................................
New Accounting Standards and Interpretations ....................................................................................................................
Corporate Governance..........................................................................................................................................................
Legislative and Regulatory Matters.......................................................................................................................................
 
 
ITEM 3. QUANTITATIVE AND QUALITATIVE DISCLOSURES ABOUT MARKET RISK ..............................................................
 
 
ITEM 4. CONTROLS AND PROCEDURES ..................................................................................................................................
      Disclosure Controls and Procedures ......................................................................................................................................
      Changes in Internal Control over Financial Reporting ............................................................................................................
 
 
              PART II - OTHER INFORMATION
 
 
 
ITEM 1. LEGAL PROCEEDINGS ..................................................................................................................................................
 
 
ITEM  1A. RISK FACTORS ...........................................................................................................................................................
 
 
ITEM  6. EXHIBITS .......................................................................................................................................................................
 
 
SIGNATURES ...............................................................................................................................................................................
 
 
EXHIBIT INDEX ............................................................................................................................................................................

2

Table of Contents                                                                                 

GLOSSARY OF COMMON ACRONYMS
Following are definitions of terms or acronyms that may be used in this Quarterly Report on Form 10-Q for the quarter ended December 31, 2016 (the “Quarterly Report”):
 
Term or Acronym
 
Definition
AFUDC
 
Allowance for funds used during construction
AOCI
 
Accumulated other comprehensive income (loss)
ARO
 
Asset retirement obligation
ART
 
Asset Retirement Trust
ASLB
 
Atomic Safety and Licensing Board
BEST
 
Bellefonte Efficiency and Sustainability Team
BREDL
 
Blue Ridge Environmental Defense League
CAA
 
Clean Air Act
CAIR
 
Clean Air Interstate Rule
CCP
 
Coal combustion products
CCR
 
Coal combustion residuals
CME
 
Chicago Mercantile Exchange
CO 2
 
Carbon dioxide
COL
 
Combined construction and operating license
COLA
 
Cost-of-living adjustment
CSAPR
 
Cross-State Air Pollution Rule
CT
 
Combustion turbine unit
CVA
 
Credit valuation adjustment
CY
 
Calendar year
DCP
 
Deferred Compensation Plan
DOE
 
Department of Energy
EPA
 
Environmental Protection Agency
ESPA
 
Early Site Permit Application
FASB
 
Financial Accounting Standards Board
FCM
 
Futures Commission Merchant
FERC
 
Federal Energy Regulatory Commission
FTP
 
Financial Trading Program
GAAP
 
Accounting principles generally accepted in the United States of America
GAO
 
Government Accountability Office
GHG
 
Greenhouse gas
GWh
 
Gigawatt hour(s)
IRP
 
Integrated Resource Plan
JSCCG
 
John Sevier Combined Cycle Generation LLC
kWh
 
Kilowatt hour(s)
LIBOR
 
London Interbank Offered Rate
LPC
 
Local power company customer of TVA
LTDCP
 
Long-Term Deferred Compensation Plan
MATS
 
Mercury and Air Toxics Standards
MD&A
 
Management’s Discussion and Analysis of Financial Condition and Results of Operations
MISO
 
Midcontinent Independent System Operator, Inc.
mmBtu
 
Million British thermal unit(s)
MtM
 
Mark-to-market
MW
 
Megawatt
NAAQS
 
National Ambient Air Quality Standards
NAV
 
Net asset value

3

Table of Contents                                                                                 

NDT
 
Nuclear Decommissioning Trust
NEPA
 
National Environmental Policy Act
NERC
 
North American Electric Reliability Corporation
NO x
 
Nitrogen oxide
NPDES
 
National Pollutant Discharge Elimination System
NRC
 
Nuclear Regulatory Commission
OCI
 
Other comprehensive income (loss)
PM
 
Particulate matter
QER
 
Quadrennial Energy Review
QTE
 
Qualified technological equipment and software
REIT
 
Real Estate Investment Trust
SACE
 
Southern Alliance for Clean Energy
SCCG
 
Southaven Combined Cycle Generation LLC
SCRs
 
Selective catalytic reduction systems
SEC
 
Securities and Exchange Commission
SERP
 
Supplemental Executive Retirement Plan
Seven States
 
Seven States Power Corporation
SHLLC
 
Southaven Holdco LLC
SMR
 
Small modular reactor(s)
SO 2
 
Sulfur dioxide
SSSL
 
Seven States Southaven, LLC
TCWN
 
Tennessee Clean Water Network
TDEC
 
Tennessee Department of Environment & Conservation
TOU
 
Time-of-use
TVARS
 
Tennessee Valley Authority Retirement System
U.S. Treasury
 
United States Department of the Treasury
VIE
 
Variable interest entity
XBRL
 
eXtensible Business Reporting Language


4

Table of Contents                                                                                 

FORWARD-LOOKING INFORMATION

This Quarterly Report contains forward-looking statements relating to future events and future performance.  All statements other than those that are purely historical may be forward-looking statements.  In certain cases, forward-looking statements can be identified by the use of words such as “may,” “will,” “should,” “expect,” “anticipate,” “believe,” “intend,” “project,” “plan,” “predict,” “assume,” “forecast,” “estimate,” “objective,” “possible,” “probably,” “likely,” “potential,” "speculate," or other similar expressions.

Although the Tennessee Valley Authority ("TVA") believes that the assumptions underlying the forward-looking statements are reasonable, TVA does not guarantee the accuracy of these statements.  Numerous factors could cause actual results to differ materially from those in the forward-looking statements.  These factors include, among other things:

New, amended, or existing laws, regulations, or administrative orders, including those related to environmental matters, and the costs of complying with these laws, regulations, and administrative orders;
The cost of complying with known, anticipated, and new emissions reduction requirements, some of which could render continued operation of many of TVA's aging coal-fired generation units not cost-effective and result in their removal from service, perhaps permanently;
Actions taken, or inaction, by the U.S. government relating to the national debt ceiling or automatic spending cuts in government programs;
Costs and liabilities that are not anticipated in TVA’s financial statements for third-party claims, natural resource damages, or fines or penalties associated with unexpected events such as failures of a facility or infrastructure as well as for environmental clean-up activities;
Addition or loss of customers by TVA or the local power company customers of TVA ("LPCs") ;
Significant reductions in demand for electricity produced through non-renewable or centrally located generation sources which may result from, among other things, economic downturns, increased energy efficiency and conservation, increased utilization of distributed generation, and improvements in alternative generation and energy storage technologies;
Changes in customer preferences for energy produced from cleaner generation sources;
Significant delays, cost increases, or cost overruns associated with the construction and maintenance of generation or transmission assets;
Changes in the timing or amount of pension and health care obligations and related funding;
Increases in TVA's financial liabilities for decommissioning its nuclear facilities or retiring other assets;
Physical or cyber attacks on TVA's assets;
The outcome of legal or administrative proceedings;
The failure of TVA's generation, transmission, flood control, and related assets, including coal combustion residuals ("CCR") facilities, to operate as anticipated, resulting in lost revenues, damages, and other costs that are not reflected in TVA’s financial statements or projections;
Differences between estimates of revenues and expenses and actual revenues earned and expenses incurred;
Weather conditions;
Catastrophic events such as fires, earthquakes, explosions, solar events, electromagnetic pulses, geomagnetic disturbances, droughts, floods, hurricanes, tornadoes, pandemics, wars, national emergencies, terrorist activities, and other similar events, especially if these events occur in or near TVA's service area;
Events at a TVA facility, which, among other things, could result in loss of life, damage to the environment, damage to or loss of the facility, and damage to the property of others;
Events or changes involving transmission lines, dams, and other facilities not operated by TVA, including those that affect the reliability of the interstate transmission grid of which TVA's transmission system is a part and those that increase flows across TVA's transmission grid;
Disruption of fuel supplies, which may result from, among other things, economic conditions, weather conditions, production or transportation difficulties, labor challenges, or environmental laws or regulations affecting TVA's fuel suppliers or transporters;
Purchased power price volatility and disruption of purchased power supplies;
Events which affect the supply of water for TVA's generation facilities;
Changes in TVA's determinations of the appropriate mix of generation assets;
Ineffectiveness of TVA's efforts at adapting its organization to an evolving marketplace and remaining cost competitive;
Inability to obtain, or loss of, regulatory approval for the construction or operation of assets;
The requirement or decision to make additional contributions to TVA's pension or other post-retirement benefit plans or to TVA's Nuclear Decommissioning Trust ("NDT") or Asset Retirement Trust ("ART") ;
Limitations on TVA's ability to borrow money which may result from, among other things, TVA's approaching or substantially reaching the limit on bonds, notes, and other evidences of indebtedness specified in the Tennessee Valley Authority Act of 1933, as amended, 16 U.S.C. §§ 831-831ee (the “TVA Act”);
An increase in TVA's cost of capital which may result from, among other things, changes in the market for TVA's debt securities, changes in the credit rating of TVA or the U.S. government, or, potentially, an increased reliance by TVA on alternative financing should TVA approach its debt limit;
Changes in the economy and volatility in financial markets;
Changes in technology;

5

Table of Contents                                                                                 

Reliability and creditworthiness of counterparties;
Changes in the market price of commodities such as coal, uranium, natural gas, fuel oil, crude oil, construction materials, reagents, electricity, and emission allowances;
Changes in the market price of equity securities, debt securities, and other investments;
Changes in interest rates, currency exchange rates, and inflation rates;
Ineffectiveness of TVA's disclosure controls and procedures or its internal control over financial reporting;
Inability to eliminate identified deficiencies in TVA's systems, standards, controls, or corporate culture;
Inability to attract or retain a skilled workforce;
Events at a nuclear facility, whether or not operated by or licensed to TVA, which, among other things, could lead to increased regulation or restriction on the construction, ownership, operation, and decommissioning of nuclear facilities or on the storage of spent fuel, obligate TVA to pay retrospective insurance premiums, reduce the availability and affordability of insurance, increase the costs of operating TVA's existing nuclear units, and cause TVA to forego future construction at these or other facilities;
Loss of quorum of the TVA Board of Directors; and
Other unforeseeable events.

See also Item 1A, Risk Factors, and Item 7, Management’s Discussion and Analysis of Financial Condition and Results of Operations in TVA’s Annual Report on Form 10-K for the year ended September 30, 2016 (the “Annual Report”), and
Part I, Item 2, Management’s Discussion and Analysis of Financial Condition and Results of Operations in this Quarterly Report for a discussion of factors that could cause actual results to differ materially from those in a forward-looking statement.  New factors emerge from time to time, and it is not possible for TVA to predict all such factors or to assess the extent to which any factor or combination of factors may impact TVA’s business or cause results to differ materially from those contained in any forward-looking statement.  TVA undertakes no obligation to update any forward-looking statement to reflect developments that occur after the statement is made.

GENERAL INFORMATION

Fiscal Year

References to years ( 2017 , 2016 , etc.) in this Quarterly Report are to TVA’s fiscal years ending September 30.  Years that are preceded by “CY” are references to calendar years.

Notes

References to “Notes” are to the Notes to Consolidated Financial Statements contained in Part I, Item 1, Financial Statements in this Quarterly Report.

Available Information

TVA's Annual Reports on Form 10-K, Quarterly Reports on Form 10-Q, and Current Reports on Form 8-K, as well as all amendments to those reports, are available on TVA's web site, free of charge, as soon as reasonably practicable after such reports are electronically filed with or furnished to the Securities and Exchange Commission ("SEC") .  TVA's web site is www.tva.gov.  Information contained on TVA’s web site shall not be deemed to be incorporated into, or to be a part of, this Quarterly Report.  All TVA SEC reports are available to the public without charge from the web site maintained by the SEC at www.sec.gov.  


6

Table of Contents                                                                                 

PART I - FINANCIAL INFORMATION

ITEM 1.  FINANCIAL STATEMENTS

  TENNESSEE VALLEY AUTHORITY
 CONSOLIDATED STATEMENTS OF OPERATIONS (Unaudited)
Three Months Ended December 31
(in millions)
 
2016
 
2015
Operating revenues
 
 
 
Revenue from sales of electricity
$
2,508

 
$
2,246

Other revenue
38

 
34

Total operating revenues
2,546

 
2,280

Operating expenses
 

 
 

Fuel
568

 
480

Purchased power
242

 
247

Operating and maintenance
741

 
740

Depreciation and amortization
437

 
461

Tax equivalents
129

 
124

Total operating expenses
2,117

 
2,052

Operating income
429

 
228

Other income (expense), net
12

 
12

Interest expense
 

 
 

Interest expense
339

 
335

Allowance for funds used during construction

 
(58
)
Net interest expense
339

 
277

Net income (loss)
$
102

 
$
(37
)
The accompanying notes are an integral part of these consolidated financial statements.


  TENNESSEE VALLEY AUTHORITY
 CONSOLIDATED STATEMENTS OF COMPREHENSIVE INCOME (LOSS) (Unaudited)
Three Months Ended December 31
(in millions)
 
2016
 
2015
 
 
 
 
Net income (loss)
$
102

 
$
(37
)
Other comprehensive income (loss)
 
 
 
Net unrealized gain (loss) on cash flow hedges
(8
)
 
(27
)
Reclassification to earnings from cash flow hedges
38

 
24

Total other comprehensive income (loss)
$
30

 
$
(3
)
Total comprehensive income (loss)
$
132

 
$
(40
)
The accompanying notes are an integral part of these consolidated financial statements.


7

Table of Contents                                                                                 

TENNESSEE VALLEY AUTHORITY
 CONSOLIDATED BALANCE SHEETS
 (in millions)
ASSETS
 
December 31, 2016

September 30, 2016
Current assets
(Unaudited)

 
Cash and cash equivalents
$
300

 
$
300

Accounts receivable, net
1,451

 
1,747

Inventories, net
1,120

 
993

Regulatory assets
454

 
536

Other current assets
101

 
68

Total current assets
3,426

 
3,644

 
 
 
 
Property, plant, and equipment
 

 
 

Completed plant
56,815

 
51,564

Less accumulated depreciation
(27,634
)
 
(27,592
)
Net completed plant
29,181

 
23,972

Construction in progress
3,278

 
8,458

Nuclear fuel
1,409

 
1,450

Capital leases
160

 
163

Total property, plant, and equipment, net
34,028

 
34,043

 
 
 
 
Investment funds
2,293

 
2,257

 
 
 
 
Regulatory and other long-term assets
 

 
 

Regulatory assets
9,728

 
10,164

Other long-term assets
389

 
386

Total regulatory and other long-term assets
10,117

 
10,550

 
 
 
 
Total assets
$
49,864

 
$
50,494

The accompanying notes are an integral part of these consolidated financial statements.



8

Table of Contents                                                                                 

TENNESSEE VALLEY AUTHORITY
 CONSOLIDATED BALANCE SHEETS
 (in millions)
LIABILITIES AND PROPRIETARY CAPITAL
 
December 31, 2016
 
September 30, 2016
Current liabilities
(Unaudited)
 
 
Accounts payable and accrued liabilities
$
1,785

 
$
2,163

Accrued interest
339

 
363

Current portion of leaseback obligations
58

 
58

Current portion of energy prepayment obligations
100

 
100

Regulatory liabilities
173

 
154

Short-term debt, net
2,027

 
1,407

Current maturities of power bonds
1,681

 
1,555

Current maturities of long-term debt of variable interest entities
35

 
35

Current maturities of notes payable
27

 
27

Total current liabilities
6,225

 
5,862

 
 
 
 
Other liabilities
 
 
 
Post-retirement and post-employment benefit obligations
6,827

 
6,929

Asset retirement obligations
3,881

 
3,840

Other long-term liabilities
2,424

 
2,776

Leaseback obligations
408

 
409

Energy prepayment obligations
85

 
110

Total other liabilities
13,625

 
14,064

 
 
 
 
Long-term debt, net
 
 
 
Long-term power bonds, net
20,215

 
20,901

Long-term debt of variable interest entities, net
1,200

 
1,199

Long-term notes payable
48

 
48

Total long-term debt, net
21,463

 
22,148

Total liabilities
41,313

 
42,074

 
 
 
 
Commitments and contingencies
 
 
 
 
 
 
 
Proprietary capital
 
 
 
Power program appropriation investment
258

 
258

Power program retained earnings
7,697

 
7,594

Total power program proprietary capital
7,955

 
7,852

Nonpower programs appropriation investment, net
578

 
580

Accumulated other comprehensive income (loss)
18

 
(12
)
Total proprietary capital
8,551

 
8,420

 
 
 
 
Total liabilities and proprietary capital
$
49,864

 
$
50,494

The accompanying notes are an integral part of these consolidated financial statements.


9

Table of Contents                                                                                 

TENNESSEE VALLEY AUTHORITY
 CONSOLIDATED STATEMENTS OF CASH FLOWS (Unaudited)
  For the Three Months Ended December 31
 (in millions)
 
2016
 
2015
Cash flows from operating activities
 
 
 
Net income (loss)
$
102

 
$
(37
)
Adjustments to reconcile net income (loss) to net cash provided by operating activities
 

 
 

Depreciation and amortization (including amortization of debt issuance costs and premiums/discounts)
449

 
472

Amortization of nuclear fuel cost
85

 
63

Non-cash retirement benefit expense
84

 
82

Prepayment credits applied to revenue
(25
)
 
(25
)
Fuel cost adjustment deferral
57

 
37

Fuel cost tax equivalents
2

 
(7
)
Changes in current assets and liabilities
 

 
 

Accounts receivable, net
299

 
375

Inventories and other current assets, net
(61
)
 
(104
)
Accounts payable and accrued liabilities
(209
)
 
(246
)
Accrued interest
(24
)
 
(22
)
Regulatory assets costs
(16
)
 
(11
)
Pension contributions
(75
)
 

Other, net
(51
)
 
(61
)
Net cash provided by operating activities
617

 
516

Cash flows from investing activities
 

 
 

Construction expenditures
(625
)
 
(866
)
Nuclear fuel expenditures
(100
)
 
(101
)
Loans and other receivables
 

 
 

Advances
(3
)
 
(2
)
Repayments
1

 
1

Other, net
20

 

Net cash used in investing activities
(707
)
 
(968
)
Cash flows from financing activities
 

 
 

Long-term debt
 

 
 

Redemptions and repurchases of power bonds
(527
)
 
(4
)
Short-term debt issues (redemptions), net
619

 
470

Payments on leases and leasebacks
(1
)
 
(2
)
Payments to U.S. Treasury
(1
)
 
(2
)
Other, net

 
1

Net cash provided by (used in) financing activities
90

 
463

Net change in cash and cash equivalents

 
11

Cash and cash equivalents at beginning of period
300

 
300

Cash and cash equivalents at end of period
$
300

 
$
311

 
 
 
 
Supplemental disclosures
 
 
 
Significant non-cash transactions
 
 
 
Accrued capital and nuclear fuel expenditures
$
336

 
$
372

Capital lease obligations incurred

 
9

The accompanying notes are an integral part of these consolidated financial statements.

10

Table of Contents                                                                                 

TENNESSEE VALLEY AUTHORITY
CONSOLIDATED STATEMENTS OF CHANGES IN PROPRIETARY CAPITAL (Unaudited)
For the Three Months Ended December 31, 2016 and 2015
(in millions)
 
Power Program Appropriation Investment
 
 
Power Program Retained Earnings
 
Nonpower Programs Appropriation Investment, Net
 
Accumulated
Other
Comprehensive
Income (Loss)
from
Net Gains (Losses) on Cash Flow Hedges
 
 
 
Total
Balance at September 30, 2015
$
258

 
$
6,357

 
$
590

 
$
(2
)
 
$
7,203

Net income (loss)

 
(34
)
 
(3
)
 

 
(37
)
Total other comprehensive income (loss)

 

 

 
(3
)
 
(3
)
Return on power program appropriation investment

 
(2
)
 

 

 
(2
)
Balance at December 31, 2015 (unaudited)
$
258

 
$
6,321

 
$
587

 
$
(5
)
 
$
7,161

 
 
 
 
 
 
 
 
 
 
Balance at September 30, 2016
$
258

 
$
7,594

 
$
580

 
$
(12
)
 
$
8,420

Net income (loss)

 
104

 
(2
)
 

 
102

Total other comprehensive income (loss)

 

 

 
30

 
30

Return on power program appropriation investment

 
(1
)
 

 

 
(1
)
Balance at December 31, 2016 (unaudited)
$
258

 
$
7,697

 
$
578

 
$
18

 
$
8,551

The accompanying notes are an integral part of these consolidated financial statements.





11

Table of Contents                                                                                 

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS (Unaudited)
(Dollars in millions except where noted)


1.  Nature of Operations and Summary of Significant Accounting Policies

General

The Tennessee Valley Authority ("TVA") is a corporate agency and instrumentality of the United States that was created in 1933 by legislation enacted by the United States ("U.S.") Congress in response to a request by President Franklin D. Roosevelt.  TVA was created to, among other things, improve navigation on the Tennessee River, reduce the damage from destructive flood waters within the Tennessee River system and downstream on the lower Ohio and Mississippi Rivers, further the economic development of TVA's service area in the southeastern United States, and sell the electricity generated at the facilities TVA operates.

Today, TVA operates the nation's largest public power system and supplies power in most of Tennessee, northern Alabama, northeastern Mississippi, and southwestern Kentucky and in portions of northern Georgia, western North Carolina, and southwestern Virginia to a population of over nine million people.

TVA also manages the Tennessee River, its tributaries, and certain shorelines to provide, among other things, year-round navigation, flood damage reduction, and affordable and reliable electricity. Consistent with these primary purposes, TVA also manages the river system and public lands to provide recreational opportunities, adequate water supply, improved water quality, cultural and natural resource protection, and economic development.

The power program has historically been separate and distinct from the stewardship programs.  It is required to be self-supporting from power revenues and proceeds from power financings, such as proceeds from the issuance of bonds, notes, or other evidences of indebtedness ("Bonds") .  Although TVA does not currently receive congressional appropriations, it is required to make annual payments to the United States Department of the Treasury ("U.S. Treasury") as a return on the government's appropriation investment in TVA's power facilities (the "Power Program Appropriation Investment").  In the 1998 Energy and Water Development Appropriations Act, Congress directed TVA to fund essential stewardship activities related to its management of the Tennessee River system and nonpower or stewardship properties with power revenues in the event that there were insufficient appropriations or other available funds to pay for such activities in any fiscal year.  Congress has not provided any appropriations to TVA to fund such activities since 1999.  Consequently, during 2000, TVA began paying for essential stewardship activities primarily with power revenues, with the remainder funded with user fees and other forms of revenues derived in connection with those activities.  The activities related to stewardship properties do not meet the criteria of an operating segment under accounting principles generally accepted in the United States of America ("GAAP") .  Accordingly, these assets and properties are included as part of the power program, TVA's only operating segment.

Power rates are established by the TVA Board of Directors (the "TVA Board") as authorized by the Tennessee Valley Authority Act of 1933, as amended, 16 U.S.C. §§ 831-831ee (the “TVA Act”).  The TVA Act requires TVA to charge rates for power that will produce gross revenues sufficient to provide funds for operation, maintenance, and administration of its power system; payments to states and counties in lieu of taxes ("tax equivalents") ; debt service on outstanding indebtedness;

12

Table of Contents                                                                                 

payments to the U.S. Treasury in repayment of and as a return on the Power Program Appropriation Investment; and such additional margin as the TVA Board may consider desirable for investment in power system assets, retirement of outstanding Bonds in advance of maturity, additional reduction of the Power Program Appropriation Investment, and other purposes connected with TVA's power business.  In setting TVA's rates, the TVA Board is charged by the TVA Act to have due regard for the primary objectives of the TVA Act, including the objective that power shall be sold at rates as low as are feasible.  Rates set by the TVA Board are not subject to review or approval by any state or other federal regulatory body.

Fiscal Year

TVA's fiscal year ends September 30.  Years ( 2017 , 2016 , etc.) refer to TVA's fiscal years unless they are preceded by “CY,” in which case the references are to calendar years.

Cost-Based Regulation

Since the TVA Board is authorized by the TVA Act to set rates for power sold to its customers, TVA is self-regulated. Additionally, TVA's regulated rates are designed to recover its costs.  Based on current projections, TVA believes that rates, set at levels that will recover TVA's costs, can be charged and collected.  As a result of these factors, TVA records certain assets and liabilities that result from the regulated ratemaking process that would not be recorded under GAAP for non-regulated entities.  Regulatory assets generally represent incurred costs that have been deferred because such costs are probable of future recovery in customer rates.  Regulatory liabilities generally represent obligations to make refunds to customers for previous collections for costs that are not likely to be incurred or deferral of gains that will be credited to customers in future periods.  TVA assesses whether the regulatory assets are probable of future recovery by considering factors such as applicable regulatory changes, potential legislation, and changes in technology.  Based on these assessments, TVA believes the existing regulatory assets are probable of future recovery.  This determination reflects the current regulatory and political environment and is subject to change in the future.  If future recovery of regulatory assets ceases to be probable, or any of the other factors described above cease to be applicable, TVA would no longer be considered to be a regulated entity and would be required to write off these costs.  All regulatory asset write offs would be required to be recognized in earnings in the period in which future recovery ceases to be probable.

Basis of Presentation

TVA prepares its consolidated interim financial statements in conformity with GAAP for consolidated interim financial information. Accordingly, TVA's consolidated interim financial statements do not include all of the information and notes required by GAAP for annual financial statements. As such, they should be read in conjunction with the audited financial statements for the year ended September 30, 2016 , and the notes thereto, which are contained in TVA's Annual Report on Form 10-K for the year ended September 30, 2016 (the “Annual Report”). In the opinion of management, all adjustments (consisting of items of a normal recurring nature) considered necessary for fair presentation are included in the consolidated interim financial statements.

The accompanying consolidated interim financial statements, which have been prepared in accordance with GAAP, include the accounts of TVA, two wholly-owned direct subsidiaries, and three variable interest entities ("VIE") of which TVA is the primary beneficiary. See Note 7 . Intercompany balances and transactions have been eliminated in consolidation.

Use of Estimates

The preparation of financial statements requires TVA to estimate the effects of various matters that are inherently uncertain as of the date of the consolidated financial statements.  Although the consolidated financial statements are prepared in conformity with GAAP, TVA is required to make estimates and assumptions that affect the reported amounts of assets and liabilities, the disclosure of contingent assets and liabilities, and the amounts of revenues and expenses reported during the reporting period.  Each of these estimates varies in regard to the level of judgment involved and its potential impact on TVA's financial results.  Estimates are considered critical either when a different estimate could have reasonably been used, or where changes in the estimate are reasonably likely to occur from period to period, and such use or change would materially impact TVA's financial condition, results of operations, or cash flows.

Allowance for Uncollectible Accounts

The allowance for uncollectible accounts reflects TVA's estimate of probable losses inherent in its accounts and loans receivable balances.  TVA determines the allowance based on known accounts, historical experience, and other currently available information including events such as customer bankruptcy and/or a customer failing to fulfill payment arrangements.  It also reflects TVA's corporate credit department's assessment of the financial condition of customers and the credit quality of the receivables.

The allowance for uncollectible accounts was $ 1 million at both December 31, 2016 , and September 30, 2016 , for accounts receivable. Additionally, loans receivable of $ 152 million and $ 141 million at December 31, 2016 , and September 30, 2016 , respectively, are included in Accounts receivable, net and Other long-term assets, for the current and long-term portions,

13

Table of Contents                                                                                 

respectively, and reported net of allowances for uncollectible accounts of $ 8 million at both December 31, 2016 , and September 30, 2016 .

Pre-Commercial Plant Operations

As part of the process of completing the construction of a generating unit, the electricity produced is used to serve the demands of the electric system.  TVA estimates revenue from such pre-commercial generation based on the guidance provided by Federal Energy Regulatory Commission ("FERC") regulations. Watts Bar Nuclear Plant ("Watts Bar") Unit 2 commenced pre-commercial plant operations on June 3, 2016, and commercial operations of Watts Bar Unit 2 began on October 19, 2016.  TVA is constructing a natural gas-fired generation facility at its Paradise Fossil Plant site and commenced pre-commercial plant operations on October 10, 2016.  As of December 31, 2016 , the Paradise natural gas-fired facility was still in pre-commercial operations. Estimated revenue of $14 million , primarily related to Watts Bar Unit 2, was capitalized to offset project costs and is included in Revenue from sales of electricity as a contra-revenue amount on the consolidated statement of operations for the three months ended December 31, 2016 . During this same period, TVA capitalized related fuel costs for these two construction projects of approximately $ 5 million .

Depreciation     

Depreciation expense was $336 million and $364 million for the three months ended December 31, 2016 and 2015, respectively. Depreciation rates are determined based on an external depreciation study. TVA concluded and implemented the results of a new study during the three months ended December 31, 2016. Implementation of the new depreciation rates resulted in an estimated decrease of approximately $ 56 million in depreciation and amortization expense during the three months ended December 31, 2016, as compared to the same period of the prior year. This estimate represents the impact of implementing the new depreciation rates only and does not include any potential impact of other possible changes, including additions to or retirements of net completed plant that occurred during the same period. The decrease in depreciation expense as a result of the new depreciation rates is primarily attributable to the use of TVA's current generation plans, which resulted in changes in retirement date assumptions for coal-fired plants, and changes in the estimated service lives for transmission assets.

Allowance for Funds Used During Construction

TVA may capitalize interest on eligible projects as allowance for funds used during construction ("AFUDC") , based on the average interest rate of TVA’s outstanding debt.  The allowance is applicable to construction in progress related to eligible projects with (1) an expected total project cost of $ 1.0 billion or more, and (2) an estimated construction period of at least three years in duration.  There was no AFUDC capitalized during the three months ended December 31, 2016, as compared to $ 58 million capitalized during the three months ended December 31, 2015. The capitalized AFUDC was related to the Watts Bar Unit 2 project, which was completed in October 2016.

Blended Low-Enriched Uranium Program

Under the blended low-enriched uranium ("BLEU") program, TVA, the U.S. Department of Energy ("DOE") , and certain nuclear fuel contractors have entered into agreements providing for the DOE's surplus of enriched uranium to be blended with other uranium down to a level that allows the blended uranium to be fabricated into fuel that can be used in nuclear power plants. Under the terms of an interagency agreement between TVA and the DOE, in exchange for supplying highly enriched uranium materials to the appropriate third-party fuel processors for processing into usable BLEU fuel for TVA, the DOE participates to a degree in the savings generated by TVA’s use of this blended nuclear fuel. Over the life of the program, TVA projects that the DOE’s share of savings generated by TVA’s use of this blended nuclear fuel could result in payments to the DOE of as much as $ 165 million . TVA accrues an obligation with each BLEU reload batch related to the portion of the ultimate future payments estimated to be attributable to the BLEU fuel currently in use. At December 31, 2016 , TVA had paid out approximately $ 151 million for this program, and the obligation recorded was $ 14 million .


14

Table of Contents                                                                                 

2.  Impact of New Accounting Standards and Interpretations
    
The following are accounting standard updates issued by the Financial Accounting Standards Board ("FASB") that TVA adopted during the first quarter of 2017.
Standard
 
Description
 
Effective Date for TVA
 
Effect on the Financial Statements or Other Significant Matters

Consolidation
 
This guidance amends the consolidation analysis for VIEs as well as voting interest entities. The standard reduces the number of consolidation models through the elimination of the indefinite deferral for certain entities that was previously allowed and places more emphasis on risk of loss when determining a controlling financial interest. This guidance allows for either a full retrospective or a modified retrospective application.
 
October 1, 2016
 
The adoption of the standard did not materially impact TVA's financial condition, results of operations, or cash flows.

The following accounting standards have been issued, but as of December 31, 2016 , were not effective and had not been adopted by TVA.
Standard
 
Description
 
Effective Date for TVA
 
Effect on the Financial Statements or Other Significant Matters

Revenue Recognition
 
This guidance applies to revenue from contracts with customers.  The standard requires that an entity recognize revenue to depict the transfer of goods or services to customers in an amount that reflects the consideration to which the entity expects to be entitled in exchange for those goods or services. In August 2015, the FASB issued a one-year deferral of the effective date. The new effective date allows for either a full retrospective or a modified retrospective application. Early adoption is permitted.
 
October 1, 2018


 
TVA is currently evaluating the potential impact of these changes on its consolidated financial statements and related disclosures and the application method to be used.
Inventory Valuation
 
This guidance changes the model used for the subsequent measurement of inventory from the previous lower of cost or market model to the lower of cost or net realizable value. The guidance applies only to inventory valued using methods other than last-in, first out or the retail inventory method (for example, first-in, first-out or average cost). This amendment is intended to simplify the subsequent measurement of inventory. When the standard becomes effective, it includes interim periods within the fiscal year that begins on that date, and is required to be applied prospectively. Early adoption is permitted.
 
October 1, 2017
 
TVA is currently evaluating the potential impact of these changes on its consolidated financial statements.
Lease Accounting
 
This guidance changes the provisions of recognition in both the lessee and lessor accounting models. The standard requires entities that lease assets — referred to as “lessees” — to recognize on the balance sheet the assets and liabilities for the rights and obligations created by leases with terms of more than 12 months. The recognition, measurement, and presentation of expenses and cash flows arising from a lease by a lessee primarily will depend on its classification as a finance (similar to current capital leases) or operating lease. However, unlike current lease accounting rules — which require only capital leases to be recognized on the balance sheet — the new standard will require both types of leases to be recognized on the balance sheet. Operating leases will result in straight-line expense, while finance leases will result in recognition of interest on the lease liability separate from amortization expense. The accounting for the owner of the assets leased by the lessee — also known as lessor accounting — will remain largely unchanged from current lease accounting rules. When the standard becomes effective, it will include interim periods within that fiscal year, and will be required to be applied using a modified retrospective transition. Early adoption is permitted.
 
October 1, 2019
 
TVA is currently evaluating the potential impact of these changes on its consolidated financial statements and related disclosures.

15

Table of Contents                                                                                 

Financial Instruments
 
This guidance applies to the recognition and measurement of financial assets and liabilities. The standard requires all equity investments to be measured at fair value with changes in the fair value recognized through net income (other than those accounted for under the equity method of accounting or those that result in consolidation of the investee). The standard also amends presentation requirements related to certain changes in the fair value of a liability and eliminates certain disclosure requirements of significant assumptions for financial instruments measured at amortized cost on the balance sheet. Public entities must apply the amendments by means of a cumulative-effect adjustment to the balance sheet as of the beginning of the fiscal year of adoption. Early adoption is not permitted unless specific early adoption guidance is applied.
 
October 1, 2018
 
TVA is currently evaluating the potential
impact of these changes on its
consolidated financial statements.
Derivatives and Hedging
 
This guidance clarifies the requirements for assessing whether contingent call or put options that can accelerate the payment of principal on debt instruments are clearly and closely related to their debt hosts. An entity performing the assessment under the amendments in this update is required to assess the embedded call or put options solely in accordance with a four-step decision sequence. When the standard becomes effective, it will include interim periods within that fiscal year, and will be required to be applied using a modified retrospective transition. Early adoption is permitted.
 
October 1, 2017
 
TVA is currently evaluating the potential
impact of these changes on its
consolidated financial statements.

3.  Accounts Receivable, Net

Accounts receivable primarily consist of amounts due from customers for power sales.  The table below summarizes the types and amounts of TVA’s accounts receivable:
Accounts Receivable, Net  
 
At December 31, 2016
 
At September 30, 2016
Power receivables
$
1,377

 
$
1,637

Other receivables
75

 
111

Allowance for uncollectible accounts
(1
)
 
(1
)
Accounts receivable, net
$
1,451

 
$
1,747


4.  Inventories, Net

The table below summarizes the types and amounts of TVA’s inventories:
Inventories, Net  
 
At December 31, 2016
 
At September 30, 2016
Materials and supplies inventory
$
728

 
$
673

Fuel inventory
410

 
345

Emission allowance inventory, net
15

 
14

Allowance for inventory obsolescence
(33
)
 
(39
)
Inventories, net
$
1,120

 
$
993



16

Table of Contents                                                                                 

5.  Other Long-Term Assets

The table below summarizes the types and amounts of TVA’s other long-term assets:
Other Long-Term Assets  
 
At December 31, 2016
 
At September 30, 2016
EnergyRight ® receivables
$
111

 
$
112

Loans and other long-term receivables, net
148

 
136

Prepaid capacity payments
40

 
42

Commodity contract derivative assets
6

 
3

Other
84

 
93

Other long-term assets
$
389

 
$
386


In association with the EnergyRight ® Solutions program, local power company customers of TVA ("LPCs") offer financing to end-use customers for the purchase of energy-efficient equipment. Depending on the nature of the energy-efficiency project, loans may have a maximum term of five years or ten years . TVA purchases the resulting loans receivable from its LPCs. The loans receivable are then transferred to a third-party bank with which TVA has agreed to repay in full any loan receivable that has been in default for 180 days or more or that TVA has determined is uncollectible. Given this continuing involvement, TVA accounts for the transfer of the loans receivable as secured borrowings. The current and long-term portions of the loans receivable are reported in Accounts receivable, net and Other long-term assets, respectively, on TVA’s consolidated balance sheets. As of December 31, 2016 , and September 30, 2016 , the carrying amount of the loans receivable, net of discount, reported in Accounts receivable, net was approximately $ 28 million and $ 29 million , respectively. See Note 8 for information regarding the associated financing obligation.     


17

Table of Contents                                                                                 

6.  Regulatory Assets and Liabilities

Regulatory assets generally represent incurred costs that have been deferred because such costs are probable of future recovery in customer rates.  Regulatory liabilities generally represent obligations to make refunds to customers for previous collections for costs that are not likely to be incurred or deferrals of gains that will be credited to customers in future periods.  Components of regulatory assets and regulatory liabilities are summarized in the table below:
Regulatory Assets and Liabilities  
 
At December 31, 2016
 
At September 30, 2016
Current regulatory assets
 
 
 
Deferred nuclear generating units
$
237

 
$
237

Unrealized losses on commodity derivatives
104

 
122

Fuel cost adjustment receivable
41

 
98

Environmental agreements
27

 
34

Environmental cleanup costs - Kingston ash spill
42

 
42

Other current regulatory assets
3

 
3

Total current regulatory assets
454

 
536

 
 
 
 
Non-current regulatory assets
 

 
 

Deferred pension costs and other post-retirement benefits costs
5,330

 
5,385

Unrealized losses on interest rate derivatives
1,106

 
1,547

Nuclear decommissioning costs
935

 
938

Deferred nuclear generating units
915

 
850

Non-nuclear decommissioning costs
863

 
819

Environmental cleanup costs - Kingston ash spill
288

 
299

Unrealized losses on commodity derivatives
32

 
56

Environmental agreements
15

 
18

Other non-current regulatory assets
244

 
252

Total non-current regulatory assets
9,728

 
10,164

Total regulatory assets
$
10,182

 
$
10,700

 
 
 
 
Current regulatory liabilities
 

 
 

Fuel cost adjustment tax equivalents
$
151

 
$
148

Unrealized gains on commodity derivatives
22

 
6

Total current regulatory liabilities
173

 
154

 
 
 
 
Non-current regulatory liabilities
 

 
 

Unrealized gains on commodity derivatives
6

 
3

Total non-current regulatory liabilities
6

 
3

Total regulatory liabilities
$
179

 
$
157


Deferred Nuclear Generation Units . On November 14, 2016, following a public auction, TVA entered into a contract to sell substantially all of the Bellefonte Nuclear Plant ("Bellefonte") site for $ 111 million.  The net book value of the Bellefonte assets to be sold and the related asset retirement costs are collectively $ 121 million and are included in Regulatory asset-Deferred nuclear generating units on TVA’s Consolidated Balance Sheet at December 31, 2016, as approved by the TVA Board.  TVA received $ 22 million on November 14, 2016, which is recorded as a long-term liability on TVA’s Consolidated Balance Sheet at December 31, 2016, with the remaining $ 89 million due at closing.  The buyer has up to two years to close on the property.  Proceeds received from the sale will be recorded as a reduction to the regulatory asset upon closing and will reduce amounts collected in future rates.  Any subsequent losses resulting from the disposition or impairment of Bellefonte will be recovered in future rates until fully recovered based upon the TVA Board-approved recovery of the Regulatory asset-Deferred nuclear generating units in future rates at an amount of $ 237 million per year until fully recovered. 

7.  Variable Interest Entities

A VIE is an entity that either (i) has insufficient equity to permit the entity to finance its activities without additional subordinated financial support or (ii) has equity investors who lack the characteristics of owning a controlling financial interest. When TVA determines that it has a variable interest in a variable interest entity, a qualitative evaluation is performed to assess which interest holders have the power to direct the activities that most significantly impact the economic performance of the

18

Table of Contents                                                                                 

entity and have the obligation to absorb losses or receive benefits that could be significant to the entity. The evaluation considers the purpose and design of the business, the risks that the business was designed to create and pass along to other entities, the activities of the business that can be directed and which party can direct them, and the expected relative impact of those activities on the economic performance of the business through its life. TVA has the power to direct the activities of an entity when it has the ability to make key operating and financing decisions, including, but not limited to, capital investment and the issuance of debt. Based on the evaluation of these criteria, TVA has determined it is the primary beneficiary of three entities and as such is required to account for the VIEs on a consolidated basis.

John Sevier VIE

In 2012, TVA entered into a $ 1.0 billion construction management agreement and lease financing arrangement with John Sevier Combined Cycle Generation LLC ("JSCCG") for the completion and lease by TVA of the John Sevier Combined Cycle Facility ("John Sevier CCF") . JSCCG is a special single-purpose limited liability company formed in January 2012 to finance the John Sevier CCF through a $ 900 million secured note issuance (the “JSCCG notes”) and the issuance of $ 100 million of membership interests subject to mandatory redemption.  The membership interests were purchased by John Sevier Holdco LLC ("Holdco") .  Holdco is a special single-purpose entity, also formed in January 2012, established to acquire and hold the membership interests in JSCCG.  A non-controlling interest in Holdco is held by a third party through nominal membership interests, to which none of the income, expenses, and cash flows is allocated. 
 
The membership interests held by Holdco in JSCCG were purchased with proceeds from the issuance of $ 100 million of secured notes (the “Holdco notes") and are subject to mandatory redemption pursuant to scheduled amortizing, semi-annual payments due each January 15 and July 15, with a final payment due in January 2042. The payment dates for the mandatorily redeemable membership interests are the same as those of the Holdco notes. The sale of the JSCCG notes, the membership interests in JSCCG, and the Holdco notes closed in January 2012. The JSCCG notes are secured by TVA’s lease payments, and the Holdco notes are secured by Holdco's investment in, and amounts receivable from, JSCCG. TVA’s lease payments to JSCCG are equal to and payable on the same dates as JSCCG’s and Holdco’s semi-annual debt service payments. In addition to the lease payments, TVA pays administrative and miscellaneous expenses incurred by JSCCG and Holdco. Certain agreements related to this transaction contain default and acceleration provisions.

Southaven VIE

In 2013, TVA entered into a lease financing arrangement with Southaven Combined Cycle Generation LLC ("SCCG") for the lease by TVA of the Southaven Combined Cycle Facility ("Southaven CCF") . SCCG is a special single-purpose limited liability company formed in June 2013 to finance the Southaven CCF through a $ 360 million secured notes issuance (the “SCCG notes”) and the issuance of $ 40 million of membership interests subject to mandatory redemption. The membership interests were purchased by Southaven Holdco LLC ("SHLLC") . SHLLC is a special single-purpose entity, also formed in June 2013, established to acquire and hold the membership interests of SCCG. A non-controlling interest in SHLLC is held by a third party through nominal membership interests, to which none of the income, expenses, and cash flows of SHLLC are allocated.

The membership interests held by SHLLC were purchased with proceeds from the issuance of $ 40 million of secured notes (the "SHLLC notes"), and are subject to mandatory redemption pursuant to a schedule of amortizing, semi-annual payments due each February 15 and August 15, with a final payment due on August 15, 2033. The payment dates for the mandatorily redeemable membership interests are the same as those of the SHLLC notes and the payment amounts are sufficient to provide returns on, as well as returns of, capital until the investment has been repaid to SHLLC in full. The rate of return on investment to SHLLC is 7.0 percent , which is reflected as interest expense in the consolidated statements of operations. SHLLC is required to pay a pre-determined portion of the return on investment to Seven States Southaven, LLC ("SSSL") on each lease payment date as agreed in SHLLC's formation documents (the "Seven States Return"). The current and long-term portions of the Membership interests of VIE subject to mandatory redemption are included in Accounts payable and accrued liabilities and Other long-term liabilities, respectively.

The payment dates for the mandatorily redeemable membership interests are the same as those of the SHLLC notes. The SCCG notes are secured by TVA’s lease payments, and the SHLLC notes are secured by SHLLC’s investment in, and amounts receivable from, SCCG. TVA’s lease payments to SCCG are payable on the same dates as SCCG’s and SHLLC’s semi-annual debt service payments and are equal to the sum of (i) the amount of SCCG’s semi-annual debt service payments, (ii) the amount of SHLLC’s semi-annual debt service payments, and (iii) the amount of the Seven States Return. In addition to the lease payments, TVA pays administrative and miscellaneous expenses incurred by SCCG and SHLLC. Certain agreements related to this transaction contain default and acceleration provisions.

In the event that TVA were to choose to exercise an early buy out feature of the Southaven Facility Lease, in part or in whole, TVA must pay to SCCG amounts sufficient for SCCG to repay or partially repay on a pro rata basis the membership interests held by SHLLC, including any outstanding investment amount plus accrued but unpaid return. TVA also has the right, at any time and without any early redemption of the other portions of the Southaven Facility Lease payments due to SCCG, to fully repay SHLLC's investment, upon which repayment SHLLC will transfer the membership interests to a designee of TVA.


19

Table of Contents                                                                                 

Impact on Consolidated Financial Statements

The financial statement items attributable to carrying amounts and classifications of JSCCG, Holdco, and SCCG as of December 31, 2016 , and September 30, 2016 , as reflected in the consolidated balance sheets are as follows:

Summary of Impact of VIEs on Consolidated Balance Sheets
 
At December 31, 2016
 
At September 30, 2016
Current liabilities
 
 
 

Accrued interest
$
26

 
$
11

Accounts payable and accrued liabilities
2

 
2

Current maturities of long-term debt of variable interest entities
35

 
35

Total current liabilities
63

 
48

Other liabilities
 
 
 
Other long-term liabilities
33

 
33

Long-term debt, net
 
 
 
Long-term debt of variable interest entities, net
1,200

 
1,199

Total liabilities
$
1,296

 
$
1,280


Interest expense of $ 15 million related to debt of variable interest entities and membership interests of variable interest entity subject to mandatory redemption is included in the Consolidated Statements of Operations for the three months ended December 31, 2016 and 2015 .

Creditors of the VIEs do not have any recourse to the general credit of TVA. TVA does not have any obligations to provide financial support to the VIEs other than as prescribed in the terms of the agreements related to these transactions.

8.  Other Long-Term Liabilities

Other long-term liabilities consist primarily of liabilities related to certain derivative instruments as well as liabilities under agreements related to compliance with certain environmental regulations (see Note 16 Legal Proceedings Environmental Agreements ). The table below summarizes the types and amounts of Other long-term liabilities:
Other Long-Term Liabilities
 
At December 31, 2016
 
At September 30, 2016
Interest rate swap liabilities
$
1,497

 
$
1,938

Capital lease obligations
176

 
177

EnergyRight ®  financing obligation
129

 
130

Environmental agreements liability
15

 
18

Currency swap liabilities
170

 
162

Membership interests of VIE subject to mandatory redemption
33

 
33

Commodity contract derivative liabilities
32

 
49

Regulatory liabilities
6

 
3

Commodity swap derivative liabilities

 
2

Other
366

 
264

Total other long-term liabilities
$
2,424

 
$
2,776


EnergyRight ® Financing Obligation . TVA purchases certain loans receivable from its LPCs in association with the EnergyRight ® Solutions program. The current and long-term portions of the resulting financing obligation are reported in Accounts payable and accrued liabilities and Other long-term liabilities, respectively, on TVA’s consolidated balance sheets. As of December 31, 2016 , and September 30, 2016 , the carrying amount of the financing obligation reported in Accounts payable and accrued liabilities was approximately $32 million and $ 33 million , respectively. See Note 5 for information regarding the associated loans receivable and for details regarding the EnergyRight ® Solutions program.


20

Table of Contents                                                                                 

9.  Asset Retirement Obligations

During the three months ended December 31, 2016 , TVA's total ARO liability increased $ 29 million . During the three months ended December 31, 2016 , the ARO liability increased as a result of changes in estimates and periodic accretion, partially offset by settlement projects that were conducted during these periods.  The nuclear and non-nuclear accretion expense was deferred as regulatory assets.  During the three months ended December 31, 2016 , $ 36 million of the related regulatory assets were amortized into expense as these amounts were collected in rates. See Note 6 . TVA maintains investment trusts to help fund its decommissioning obligations. See Note 13 and Note 16 Contingencies Decommissioning Costs for a discussion of the trusts' objectives and the current balances of the trusts.
Asset Retirement Obligation Activity
 
Nuclear
 
Non-Nuclear
 
Total
 
Balance at September 30, 2016
$
2,492

 
$
1,560

 
$
4,052

 
Settlements

 
(28
)
 
(28
)
 
Change in estimate

 
20

 
20

 
Accretion (recorded as regulatory asset)
29

 
8

 
37

 
Balance at December 31, 2016
$
2,521

 
$
1,560

 
$
4,081

(1  
)  
Note
(1) The current portion of ARO in the amount of $ 200 million and $ 212 million is included in Accounts payable and accrued liabilities at December 31, 2016 , and September 30, 2016 , respectively.

10.  Debt and Other Obligations

Debt Outstanding

Total debt outstanding at December 31, 2016 , and September 30, 2016 , consisted of the following:
Debt Outstanding  
 
At December 31, 2016
 
At September 30, 2016
Short-term debt
 
 
 
Short-term debt, net
$
2,027

 
$
1,407

Current maturities of power bonds
1,681

 
1,555

Current maturities of long-term debt of variable interest entities
35

 
35

Current maturities of notes payable
27

 
27

Total current debt outstanding, net
3,770

 
3,024

Long-term debt
 

 
 

Long-term power bonds (1)
20,373

 
21,063

Long-term debt of variable interest entities
1,211

 
1,211

Long-term notes payable
48

 
48

Unamortized discounts, premiums, issue costs, and other
(169
)
 
(174
)
Total long-term debt, net
21,463

 
22,148

Total outstanding debt
$
25,233

 
$
25,172

Note
(1) Includes net exchange gain from currency transactions of $ 188 million at December 31, 2016 , and $ 150 million at September 30, 2016 .


21

Table of Contents                                                                                 

Debt Securities Activity

The table below summarizes the long-term debt securities activity for the period from October 1, 2016, to December 31, 2016 :
Debt Securities Activity
 
 
Date
 
Amount (1)
 
Interest Rate
 
 
 
 
 
 
 
Redemptions/Maturities

 
 
 
 
 
 
electronotes ®
 
First Quarter 2017
 
$
1

 
2.65
%
2009 Series B
 
December 2016
 
1

 
3.77
%
2001 Series D
 
December 2016
 
525

 
4.88
%
Total redemptions/maturities of debt
 
 
 
$
527

 


Note
(1) All redemptions were at 100 percent of par.

Credit Facility Agreements

TVA and the U.S. Treasury, pursuant to the TVA Act, have entered into a memorandum of understanding under which the U.S. Treasury provides TVA with a $ 150 million credit facility. This credit facility was renewed for 2017 with a maturity date of September 30, 2017. Access to this credit facility or other similar financing arrangements with the U.S. Treasury has been available to TVA since the 1960s. TVA can borrow under the U.S. Treasury credit facility only if it cannot issue Bonds in the market on reasonable terms, and TVA considers the U.S. Treasury credit facility a secondary source of liquidity. The interest rate on any borrowing under this facility is based on the average rate on outstanding marketable obligations of the United States with maturities from date of issue of one year or less. There were no outstanding borrowings under the facility at December 31, 2016 . The availability of this credit facility may be impacted by how the U.S. government addresses the situation of approaching its debt limit.

TVA also has funding available in the form of four long-term revolving credit facilities totaling $ 2.7 billion . One $150 million credit facility matures on December 12, 2019, one $ 500 million credit facility matures on February 1, 2020, one $ 1.0 billion credit facility matures on June 2, 2020, and another $ 1.0 billion credit facility matures on September 30, 2020. The interest rate on any borrowing under these facilities varies based on market factors and the rating of TVA's senior unsecured, long-term, non-credit-enhanced debt. TVA is required to pay an unused facility fee on the portion of the total $ 2.7 billion that TVA has not borrowed or committed under letters of credit. This fee, along with letter of credit fees, may fluctuate depending on the rating of TVA's senior unsecured, long-term, non-credit-enhanced debt. At December 31, 2016 , and September 30, 2016 , there were approximately $1.1 billion and $ 1.4 billion , respectively, of letters of credit outstanding under the facilities. See Note 12 Other Derivative Instruments Collateral .

The following table provides additional information regarding TVA's funding available under the four long-term credit facilities:
Summary of Long-Term Credit Facilities
At December 31, 2016
Maturity Date
Facility Limit
 
Letters of Credit Outstanding
 
Cash Borrowings
 
Availability
December 2019
$
150

 
$

 
$

 
$
150

February 2020
500

 
500

 

 

June 2020
1,000

 
262

 

 
738

September 2020
1,000

 
373

 

 
627

Total
$
2,650

 
$
1,135

 
$

 
$
1,515



22

Table of Contents                                                                                 

Lease/Leaseback Obligations
    
TVA previously entered into leasing transactions to obtain third-party financing for 24 peaking combustion turbine units (“CTs”) as well as certain qualified technological equipment and software (collectively, “QTE”). Due to TVA’s continuing involvement with the combustion turbine facilities and the QTE during the leaseback term, TVA accounted for the lease proceeds as financing obligations. In 2016, TVA acquired 100 percent of the equity interests in two special purpose entities ("SPEs") created for the purpose of facilitating a portion of the leaseback arrangements. As a result of the acquisition, TVA effectively settled its leaseback obligations related to eight CTs. At December 31, 2016 , and September 30, 2016 , the outstanding leaseback obligations related to CTs and QTE were $466 million and $467 million , respectively.

11.  Accumulated Other Comprehensive Income (Loss)

Accumulated other comprehensive income (loss) ("AOCI") represents market valuation adjustments related to TVA’s currency swaps. The currency swaps are cash flow hedges and are the only derivatives in TVA’s portfolio that have been designated and qualify for hedge accounting treatment. TVA records exchange rate gains and losses on its foreign currency-denominated debt in net income and marks its currency swap assets and liabilities to market through other comprehensive income (loss) ("OCI") . TVA then reclassifies an amount out of AOCI into net income, offsetting the exchange gain/loss recorded on the debt. During the three months ended December 31, 2016 and 2015 , TVA reclassified $ 38 million and $ 24 million of losses, respectively, related to its cash flow hedges from AOCI to Interest expense.

TVA records certain assets and liabilities that result from the regulated ratemaking process that would not be recorded under GAAP for non-regulated entities. As such, certain items that would generally be reported in AOCI or that would impact the statements of operations are recorded as regulatory assets or regulatory liabilities.

See Note 6 for a schedule of regulatory assets and liabilities.  See Note 12 for a discussion of the recognition in AOCI of gains and losses associated with certain derivative contracts. See Note 13 for a discussion of the recognition of certain investment fund gains and losses as regulatory assets and liabilities.  See Note 15 for a discussion of the regulatory accounting related to components of TVA’s benefit plans.
    
12.  Risk Management Activities and Derivative Transactions

TVA is exposed to various risks.  These include risks related to commodity prices, investment prices, interest rates, currency exchange rates, and inflation as well as counterparty credit and performance risks.  To help manage certain of these risks, TVA has entered into various derivative transactions, principally commodity option contracts, forward contracts, swaps, swaptions, futures, and options on futures.  Other than certain derivative instruments in its trust investment funds, it is TVA’s policy to enter into these derivative transactions solely for hedging purposes and not for speculative purposes. TVA has suspended its Financial Trading Program ("FTP") and no longer uses financial instruments to hedge risks related to commodity prices; however, TVA plans to continue to manage fuel price volatility through other methods and to periodically reevaluate its suspended FTP program for future use of financial instruments.

Overview of Accounting Treatment

TVA recognizes certain of its derivative instruments as either assets or liabilities on its consolidated balance sheets at fair value.  The accounting for changes in the fair value of these instruments depends on (1) whether TVA uses regulatory accounting to defer the derivative gains and losses, (2) whether the derivative instrument has been designated and qualifies for hedge accounting treatment, and (3) if so, the type of hedge relationship (for example, cash flow hedge).

23

Table of Contents                                                                                 

The following tables summarize the accounting treatment that certain of TVA's financial derivative transactions receive:
Summary of Derivative Instruments That Receive Hedge Accounting Treatment (part 1)  
Amount of Mark-to-Market Gain (Loss) Recognized in OCI
 
 
 
 
 
 
Three Months Ended
December 31
 
Derivatives in Cash Flow Hedging Relationship
 
Objective of Hedge Transaction
 
Accounting for Derivative
Hedging Instrument
 
2016
 
2015
 
Currency swaps
 
To protect against changes in cash flows caused by changes in foreign currency exchange rates (exchange rate risk)
 
Unrealized gains and losses are recorded in AOCI and reclassified to interest expense to the extent they are offset by gains and losses on the hedged transaction
 
$
(8
)
 
$
(27
)
 

Summary of Derivative Instruments That Receive Hedge Accounting Treatment (part 2) (1)
Amount of Gain (Loss) Reclassified from OCI to Interest Expense
 
 
Three Months Ended
December 31
 
Derivatives in Cash Flow Hedging Relationship
 
2016
 
2015
 
Currency swaps
 
$
(38
)
 
$
(24
)
 

Note
(1) There were no ineffective portions or amounts excluded from effectiveness testing for any of the periods presented. Based on forecasted foreign currency exchange rates, TVA expects to reclassify approximately $ 15 million of gains from AOCI to interest expense within the next twelve months to offset amounts anticipated to be recorded in interest expense related to net exchange gain on the debt.
Summary of Derivative Instruments That Do Not Receive Hedge Accounting Treatment
Amount of Gain (Loss) Recognized in Income on Derivatives





 
Three Months Ended
December 31 ( 1)
 
Derivative Type
 
Objective of Derivative
 
Accounting for Derivative Instrument
 
2016
 
2015
 
Interest rate swaps
 
To fix short-term debt variable rate to a fixed rate (interest rate risk)
 
Mark-to-market gains and losses are recorded as regulatory assets or liabilities. Realized gains and losses are recognized in interest expense when payments are made or received on the swap settlement dates.
 
$
(26
)
 
$
(28
)
 
 
 
 
 
 
 
 
 
 
 
Commodity contract derivatives
 
To protect against fluctuations in market prices of purchased coal or natural gas (price risk)
 
Mark-to-market gains and losses are recorded as regulatory assets or liabilities. Realized gains and losses due to contract settlements are recognized in fuel expense as incurred.
 
(2
)
 

 
 
 
 
 
 
 
 
 
 
 
Commodity derivatives
under FTP
 
To protect against fluctuations in market prices of purchased commodities (price risk)
 
Mark-to-market gains and losses are recorded as regulatory assets or liabilities. Realized gains and losses are recognized in fuel expense or purchased power expense when the related commodity is used in production.
 
(14
)
 
(36
)
 
Note
(1) All of TVA's derivative instruments that do not receive hedge accounting treatment have unrealized gains (losses) that would otherwise be recognized in income
but instead are deferred as regulatory assets and liabilities. As such, there was no related gain (loss) recognized in income for these unrealized gains (losses) for the three months ended December 31, 2016 and 2015 .


24

Table of Contents                                                                                 

Fair Values of TVA Derivatives
 
 
At December 31, 2016
 
At September 30, 2016
Derivatives That Receive Hedge Accounting Treatment
 
Balance
 
Balance Sheet Presentation
 
Balance
 
Balance Sheet Presentation
Currency swaps
 
 
 
 
 
 
 
 
£200 million Sterling
 
$
(88
)
 
Other long-term liabilities
 
$
(82
)
 
Other long-term liabilities
£250 million Sterling
 
(47
)
 
Other long-term liabilities
 
(41
)
 
Other long-term liabilities
£150 million Sterling
 
(35
)
 
Other long-term liabilities
 
(39
)
 
Other long-term liabilities
 
 
 
 
 
 
 
 
 
 
 
At December 31, 2016
 
At September 30, 2016
Derivatives That Do Not Receive Hedge Accounting Treatment
 
Balance
 
Balance Sheet Presentation
 
Balance
 
Balance Sheet Presentation
Interest rate swaps
 
 
 
 
 
 
 
 
$1.0 billion notional
 
(1,084
)
 
Other long-term liabilities
 
(1,387
)
 
Other long-term liabilities
$476 million notional
 
(404
)
 
Other long-term liabilities
 
(539
)
 
Other long-term liabilities
$42 million notional
 
(9
)
 
Other long-term liabilities
 
(12
)
 
Other long-term liabilities
Commodity contract derivatives
 
(87
)
 
Other current assets $22; Other long-term assets $6; Other long-term liabilities $(32); Accounts payable and accrued liabilities $(83)
 
(125
)
 
Other current assets $6; Other long-term assets $3; Other long-term liabilities $(49); Accounts payable and accrued liabilities $(85)
FTP
 
 
 
 
 
 
 
 
Derivatives under FTP (1)
 
(20
)
 
Other current assets $(15); Accounts payable and accrued liabilities $(5)
 
(39
)
 
Other current assets $(30); Other long-term liabilities $(2); Accounts payable and accrued liabilities $(7)
Note
(1)  Fair values of certain derivatives under the FTP that were in net liability positions totaling $15 million and $30 million at December 31, 2016 , and September 30, 2016 , respectively, are recorded in TVA's margin cash accounts in Other current assets. These derivatives are transacted with futures commission merchants, and cash deposits have been posted to the margin cash accounts held with each futures commission merchant to offset the net liability positions in full.

Cash Flow Hedging Strategy for Currency Swaps

To protect against exchange rate risk related to three British pound sterling denominated Bond transactions, TVA entered into foreign currency hedges at the time the Bond transactions occurred.  TVA had three currency swaps outstanding as of December 31, 2016 , with total currency exposure of £600 million and expiration dates ranging from 2021 to 2043 .

When the dollar strengthens against the British pound sterling, the exchange gain on the Bond liability is offset by an exchange loss on the swap contract.  Conversely, when the dollar weakens against the British pound sterling, the exchange loss on the Bond liability is offset by an exchange gain on the swap contract.  All such exchange gains or losses on the Bond liability are included in Long-term debt, net.  The offsetting exchange losses or gains on the swap contracts are recognized in AOCI.  If any gain (loss) were to be incurred as a result of the early termination of the foreign currency swap contract, the resulting income (expense) would be amortized over the remaining life of the associated bond as a component of Interest expense.
    
Derivatives Not Receiving Hedge Accounting Treatment

Interest Rate Derivatives .  Generally TVA uses interest rate swaps to fix variable short-term debt to a fixed rate, and TVA uses regulatory accounting treatment to defer the mark-to-market ("MtM") gains and losses on its interest rate swaps. The net deferred unrealized gains and losses are classified as regulatory assets or liabilities on TVA's consolidated balance sheets and are included in the ratemaking formula when the transactions settle. The values of these derivatives are included in Other long-term assets or Other long-term liabilities on the consolidated balance sheets, and realized gains and losses, if any, are included in TVA's consolidated statements of operations. For the three months ended December 31, 2016 and 2015 , the changes in fair market value of the interest rate swaps resulted in deferred unrealized gains of $ 441 million and $ 89 million , respectively.

Commodity Derivatives . TVA enters into certain derivative contracts for coal and natural gas that require physical delivery of the contracted quantity of the commodity. TVA marks to market all such contracts and defers the fair market values as regulatory assets or liabilities on a gross basis. At December 31, 2016 , TVA's coal contract derivatives had terms of up to two years and natural gas contract derivatives had terms of up to four years.

25

Table of Contents                                                                                 

Commodity Contract Derivatives  
 
At December 31, 2016
 
At September 30, 2016
 
Number of   Contracts
 
Notional Amount
 
Fair Value (MtM)
 
Number of Contracts
 
Notional Amount
 
Fair Value  ( MtM )
Coal contract derivatives
20
 
25 million tons
 
$
(104
)
 
20
 
20 million tons
 
$
(127
)
Natural gas contract derivatives
34
 
198 million mmBtu
 
$
17

 
39
 
148 million mmBtu
 
$
2


Derivatives Under FTP. While TVA has suspended its FTP and no longer uses financial instruments to hedge risks related to commodity prices, certain natural gas swaps with a maturity of one year or less remain as part of the suspended FTP.
Derivatives Under Financial Trading Program (1)
 
At December 31, 2016
 
At September 30, 2016
 
Notional Amount
 
Fair Value (MtM)
(in millions)
 
Notional Amount
 
Fair Value (MtM)
(in millions)
Natural gas (in mmBtu)
 
 
 
 
 
 
 
Swap contracts
15,400,000

 
$
(20
)
 
21,052,500

 
$
(39
)
Note
(1) Fair value amounts presented are based on the net commodity position with the counterparty. Notional amounts disclosed represent the net value of contractual amounts.

TVA defers all FTP unrealized gains (losses) as regulatory liabilities (assets) and records only realized gains or losses to match the delivery period of the underlying commodity. In addition to the open commodity derivatives disclosed above, TVA had closed derivative contracts with market values of $ (1) million at December 31, 2016 , and $ (5) million at September 30, 2016 . TVA experienced the following unrealized and realized gains and losses related to the FTP at the dates and during the periods, as applicable, set forth in the tables below:
Financial Trading Program Unrealized Gains (Losses)
 
 
At December 31 2016
 
At September 30 2016
FTP unrealized gains (losses) deferred as regulatory liabilities (assets)
 
 
 
 
Natural gas
 
$
(20
)
 
$
(39
)
    
Financial Trading Program Realized Gains (Losses)
 
 
Three Months Ended
December 31
 
 
 
2016
 
2015
 
Decrease (increase) in fuel expense
 
 
 
 
 
Natural gas
 
$
(11
)
 
$
(29
)
 

Financial Trading Program Realized Gains (Losses)
 
 
Three Months Ended
December 31
 
 
 
2016
 
2015
 
Decrease (increase) in purchased power expense
 
 
 
 
 
Natural gas
 
$
(3
)
 
$
(7
)
 

26

Table of Contents                                                                                 


Offsetting of Derivative Assets and Liabilities

The amounts of TVA's derivative instruments as reported in the consolidated balance sheets as of December 31, 2016 , and September 30, 2016 , are shown in the table below:
Derivative Assets and Liabilities
 
As of December 31, 2016
 
Gross Amounts of Recognized Assets/Liabilities
 
Gross Amounts Offset in the Balance Sheet (1)
 
Net Amounts of Assets/Liabilities Presented in the Balance Sheet (2)
Assets
 
 
 
 
 
Commodity derivatives not subject to master netting or similar arrangement
$
28

 
$

 
$
28

 
 
 
 
 
 
Liabilities
 
 
 
 
 
Currency swap(s) (3)
$
170

 
$

 
$
170

Interest rate swaps (3)
1,497

 

 
1,497

Commodity derivatives under FTP
20

 
(15
)
 
5

Total derivatives subject to master netting or similar arrangement
1,687

 
(15
)
 
1,672

Commodity derivatives not subject to master netting or similar arrangement
115

 

 
115

 
 
 
 
 
 
Total
$
1,802

 
$
(15
)
 
$
1,787

 
 
 
 
 
 
 
As of September 30, 2016
 
Gross Amounts of Recognized Assets/Liabilities
 
Gross Amounts Offset in the Balance Sheet (1)
 
Net Amounts of Assets/Liabilities Presented in the Balance Sheet (2)
Assets
 
 
 
 
 
Commodity derivatives under FTP subject to master netting or similar arrangement
$
6

 
$
(6
)
 
$

Commodity derivatives not subject to master netting or similar arrangement
9

 

 
9

 
 
 
 
 
 
Total
$
15

 
$
(6
)
 
$
9

 
 
 
 
 
 
Liabilities
 
 
 
 
 
Currency swap(s) (3)
$
162

 
$

 
$
162

Interest rate swaps (3)
1,938

 

 
1,938

Commodity derivatives under FTP
45

 
(36
)
 
9

Total derivatives subject to master netting or similar arrangement
2,145

 
(36
)
 
2,109

Commodity derivatives not subject to master netting or similar arrangement
134

 

 
134

 
 
 
 
 
 
Total
$
2,279

 
$
(36
)
 
$
2,243

Notes
(1) Amounts primarily include counterparty netting of derivative contracts, margin account deposits for futures commission merchants transactions, and cash collateral received or paid in accordance with the accounting guidance for derivatives and hedging transactions.
(2) There are no derivative contracts subject to a master netting arrangement or similar agreement that are not offset in the consolidated balance sheets.
(3) Letters of credit of approximately $ 1.1 billion and $ 1.4 billion were posted as collateral at December 31, 2016 , and September 30, 2016 , respectively, to partially secure the liability positions of one of the currency swaps and one of the interest rate swaps in accordance with the collateral requirements for these derivatives.

Other Derivative Instruments

Investment Fund Derivatives .  Investment funds consist primarily of funds held in the Nuclear Decommissioning Trust ("NDT") , the Asset Retirement Trust ("ART") , the Supplemental Executive Retirement Plan ("SERP") , and the Long-Term Deferred Compensation Plan ("LTDCP") . All securities in the trusts are classified as trading.  See Note 13 Investment Funds for a discussion of the trusts' objectives and the types of investments included in the various trusts.  These trusts may invest in derivative instruments which may include swaps, futures, options, forwards, and other instruments. The fair values of these derivatives were in asset positions totaling $14 million and $ 15 million at December 31, 2016 and September 30, 2016 , respectively. At December 31, 2016 , and September 30, 2016 , the fair value of other derivative instruments in these trusts was not material to TVA's consolidated financial statements.


27

Table of Contents                                                                                 

Collateral .  TVA's interest rate swaps and currency swaps contain contract provisions that require a party to post collateral (in a form such as cash or a letter of credit) when the party's liability balance under the agreement exceeds a certain threshold.  At December 31, 2016 , the aggregate fair value of all derivative instruments with credit-risk related contingent features that were in a liability position was $ 1.7 billion .  TVA's collateral obligations at December 31, 2016 , under these arrangements were approximately $ 1.1 billion , for which TVA had posted approximately $ 1.1 billion in letters of credit. These letters of credit reduce the available balance under the related credit facilities.  TVA's assessment of the risk of its nonperformance includes a reduction in its exposure under the contract as a result of this posted collateral.

For all of its derivative instruments with credit-risk related contingent features:
    
If TVA remains a majority-owned U.S. government entity but Standard & Poor's Financial Services, LLC ("S&P") or Moody's Investors Service, Inc. ("Moody's") downgrades TVA's credit rating to AA or Aa2, respectively, TVA's collateral obligations would likely increase by $ 22 million , and

If TVA ceases to be majority-owned by the U.S. government, TVA's credit rating would likely be downgraded and TVA would be required to post additional collateral.

Counterparty Risk

TVA may be exposed to certain risks when a counterparty has the potential to fail to meet its obligations in accordance with agreed terms. These risks may be related to credit, operational, or nonperformance matters. To mitigate certain counterparty risk, TVA analyzes the counterparty’s financial condition prior to entering into an agreement, establishes credit limits, monitors the appropriateness of those limits, as well as any changes in the creditworthiness of the counterparty, on an ongoing basis, and when required, employs credit mitigation measures, such as collateral or prepayment arrangements and master purchase and sale agreements, to mitigate credit risk. TVA believes its policies and procedures for counterparty performance risk reviews have generally protected TVA against significant exposure related to market and economic conditions.

Customers .  TVA is exposed to counterparty credit risk associated with trade accounts receivable from delivered power sales to LPCs, and from industries and federal agencies directly served, all located in the Tennessee Valley region. TVA is also exposed to risk from exchange power arrangements with a small number of investor-owned regional utilities related to either delivered power or the replacement of open positions of longer-term purchased power or fuel agreements. See Note 1 Allowance for Uncollectible Accounts and Note 3 .

Suppliers .   If one of TVA's fuel or purchased power suppliers fails to perform under the terms of its contract with TVA, TVA might lose the money that it paid to the supplier under the contract and have to purchase replacement fuel or power on the spot market, perhaps at a significantly higher price than TVA was entitled to pay under the contract. In addition, TVA might not be able to acquire replacement fuel or power in a timely manner and thus might be unable to satisfy its own obligations to deliver power. Nuclear fuel requirements, including uranium mining and milling, conversion services, enrichment services, and fabrication services, are met from various suppliers, depending on the type of service. TVA purchases the majority of its natural gas requirements from a variety of suppliers under short-term contracts.

To help ensure a reliable supply of coal, TVA had coal contracts with multiple suppliers at December 31, 2016 . The contracted supply of coal is sourced from multiple geographic regions of the United States and is to be delivered via various transportation methods (i.e., barge, rail, and truck). Emerging technologies, environmental regulations, and low natural gas prices have contributed to weak demand for coal. As a result, coal suppliers are facing increased financial pressure, which has led to relatively poor credit ratings and bankruptcies. Continued difficulties by coal suppliers could result in consolidations, additional bankruptcies, restructurings, contract renegotiations, or other scenarios. Under these scenarios and TVA’s potential available responses, TVA does not anticipate a significant financial impact in obtaining continued fuel supply for its coal-fired generation.

TVA has a power purchase agreement that expires on March 31, 2032, with a supplier of electricity for 440 megawatts ("MW") of summer net capability from a lignite-fired generating plant. TVA has determined that the supplier has the equivalent of a non-investment grade credit rating; therefore, the supplier has provided credit assurance to TVA under the terms of the agreement.

Derivative Counterparties .   TVA has entered into physical and financial contracts that qualify as derivatives for hedging purposes, and TVA's NDT fund and qualified defined benefit pension plan have entered into derivative contracts for investment purposes. If a counterparty to one of TVA's hedging transactions defaults, TVA might incur substantial costs in connection with entering into a replacement hedging transaction. If a counterparty to the derivative contracts into which the NDT fund and the qualified pension plan have entered for investment purposes defaults, the value of the investment could decline significantly or perhaps become worthless. TVA has concentrations of credit risk from the banking and coal industries because multiple companies in these industries serve as counterparties to TVA in various derivative transactions. At December 31, 2016 , all of TVA's commodity derivatives under the FTP, currency swaps, and interest rate swaps were with banking counterparties whose Moody's credit ratings were A3 or higher.


28

Table of Contents                                                                                 

TVA classifies qualified forward coal and natural gas contracts as derivatives. See Derivatives Not Receiving Hedge Accounting Treatment above. At December 31, 2016 , the coal contracts were with counterparties whose Moody's credit rating, or TVA’s internal analysis when such information was unavailable, ranged from Ca or D , respectively, to Ba3 . At December 31, 2016 , the natural gas contracts were with counterparties whose ratings ranged from B1 to A3 . See Suppliers above for discussion of challenges facing the coal industry. TVA's total value for derivative contracts with coal counterparties in an asset position as of December 31, 2016 , was approximately $9 million . TVA currently utilizes two futures commission merchants ("FCMs") to clear commodity contracts, including futures, options, and similar financial derivatives. These transactions are executed under the FTP by the FCMs on exchanges on behalf of TVA. TVA maintains margin cash accounts with the FCMs. TVA makes deposits to the margin cash accounts to adequately cover any net liability positions on its derivatives transacted with the FCMs. See the note to the Fair Values of TVA Derivatives table above.

13.  Fair Value Measurements

Fair value is determined based on the exchange price that would be received for an asset or paid to transfer a liability (an exit price) in the asset or liability's principal market, or in the absence of a principal market, the most advantageous market for the asset or liability in an orderly transaction between market participants. TVA uses market or observable inputs as the preferred source of values, followed by assumptions based on hypothetical transactions in the absence of market inputs.

Valuation Techniques

The measurement of fair value results in classification into a hierarchy by the inputs used to determine the fair value as follows:
Level 1
 
 
Unadjusted quoted prices in active markets accessible by the reporting entity for identical assets or liabilities.  Active markets are those in which transactions for the asset or liability occur with sufficient frequency and volume to provide pricing.
Level 2
 
 
 
Pricing inputs other than quoted market prices included in Level 1 that are based on observable market data and that are directly or indirectly observable for substantially the full term of the asset or liability.  These include quoted market prices for similar assets or liabilities, quoted market prices for identical or similar assets in markets that are not active, adjusted quoted market prices, inputs from observable data such as interest rate and yield curves, volatilities and default rates observable at commonly quoted intervals, and inputs derived from observable market data by correlation or other means.
Level 3
 
 
Pricing inputs that are unobservable, or less observable, from objective sources.  Unobservable inputs are only to be used to the extent observable inputs are not available.  These inputs maintain the concept of an exit price from the perspective of a market participant and should reflect assumptions of other market participants.  An entity should consider all market participant assumptions that are available without unreasonable cost and effort.  These are given the lowest priority and are generally used in internally developed methodologies to generate management's best estimate of the fair value when no observable market data is available.

A financial instrument's level within the fair value hierarchy (where Level 1 is the highest and Level 3 is the lowest) is based on the lowest level of input significant to the fair value measurement.

The following sections describe the valuation methodologies TVA uses to measure different financial instruments at fair value. Except for gains and losses on SERP and LTDCP assets, all changes in fair value of these assets and liabilities have been recorded as changes in regulatory assets, regulatory liabilities, or AOCI on TVA's consolidated balance sheets and consolidated statements of comprehensive income (loss). Except for gains and losses on SERP and LTDCP assets, there has been no impact to the consolidated statements of operations or the consolidated statements of cash flows related to these fair value measurements.

Investment Funds

At December 31, 2016 , Investment funds were composed of $ 2.3 billion of securities classified as trading and measured at fair value. Trading securities are held in the NDT, ART, SERP, and LTDCP.  The NDT holds funds for the ultimate decommissioning of TVA's nuclear power plants. The ART holds funds primarily for the costs related to the future closure and retirement of TVA's other long-lived assets. The balances in the NDT and ART were $ 1.7 billion and $ 525 million , respectively, at December 31, 2016 .

TVA established a SERP for certain executives in critical positions to provide supplemental pension benefits tied to compensation that exceeds limits set by Internal Revenue Service rules applicable to the qualified defined benefit pension plan. The LTDCP is designed to provide long-term incentives to executives to encourage them to stay with TVA and to provide competitive levels of total compensation to such executives. NDT and SERP funds are invested in portfolios of securities generally designed to achieve a return in line with overall equity market performance, and ART and LTDCP funds are invested in portfolios of securities generally designed to achieve a return in line with overall debt and equity market performance.


29

Table of Contents                                                                                 

The NDT, ART, SERP, and LTDCP are composed of multiple types of investments and are managed by external institutional managers. Most U.S. and international equities, Treasury inflation-protected securities, real estate investment trust securities, and cash securities and certain derivative instruments are measured based on quoted exchange prices in active markets and are classified as Level 1 valuations. Fixed-income investments, high-yield fixed-income investments, currencies, and most derivative instruments are non-exchange traded and are classified as Level 2 valuations. These measurements are based on market and income approaches with observable market inputs.

Private equity limited partnerships and private real estate investments may include holdings of investments in private real estate, venture capital, buyout, mezzanine or subordinated debt, restructuring or distressed debt, and special situations through funds managed by third-party investment managers. These investments generally involve a three -to- four -year period where the investor contributes capital, followed by a period of distribution, typically over several years. The investment period is generally, at a minimum, ten years or longer. The NDT had unfunded commitments related to private equity limited partnerships of $ 60 million and unfunded commitments related to private real estate of $ 5 million at December 31, 2016 . These investments have no redemption or limited redemption options and may also impose restrictions on the NDT’s ability to liquidate its investments. There are no readily available quoted exchange prices for these investments. The fair value of the investments is based on TVA’s ownership percentage of the fair value of the underlying investments as provided by the investment managers. These investments are typically valued on a quarterly basis. TVA’s private equity limited partnerships and private real estate investments are valued at net asset values ("NAV") as a practical expedient for fair value. TVA classifies its interest in these types of investments as investments measured at net asset value in the fair value hierarchy.

Commingled funds represent investment funds comprising multiple individual financial instruments. The commingled funds held by the NDT, ART, SERP, and LTDCP consist of either a single class of securities, such as equity, debt, or foreign currency securities, or multiple classes of securities. All underlying positions in these commingled funds are either exchange traded or measured using observable inputs for similar instruments. The fair value of commingled funds is based on NAV per fund share (the unit of account), derived from the prices of the underlying securities in the funds. These commingled funds can be redeemed at the measurement date NAV and are classified as Commingled funds measured at net asset value in the fair value hierarchy.

Realized and unrealized gains and losses on trading securities are recognized in current earnings and are based on average cost. The gains and losses of the NDT and ART are subsequently reclassified to a regulatory asset or liability account in accordance with TVA's regulatory accounting policy. See Note 1 Cost-Based Regulation . TVA recorded unrealized gains and losses related to its trading securities held as of the end of each period as follows:
Unrealized Investment Gains (Losses)
 
 
 
 
Three Months Ended
December 31
 
Fund
 
Financial Statement Presentation
 
2016
 
2015
 
NDT
 
Regulatory asset
 
$
(7
)
 
$
39

 
ART
 
Regulatory asset
 
3

 
12

 

Currency and Interest Rate Derivatives

See Note 12 Cash Flow Hedging Strategy for Currency Swaps and Derivatives Not Receiving Hedge Accounting Treatment for a discussion of the nature, purpose, and contingent features of TVA's currency swaps and interest rate swaps. These swaps are classified as Level 2 valuations and are valued based on income approaches using observable market inputs for similar instruments.

Commodity Contract Derivatives and Commodity Derivatives Under FTP

Commodity Contract Derivatives. Most of these contracts are valued based on market approaches which utilize short- and mid-term market-quoted prices from an external industry brokerage service. A small number of these contracts are valued based on a pricing model using long-term price estimates from TVA's coal price forecast. To value the volume option component of applicable coal contracts, TVA uses a Black-Scholes pricing model which includes inputs from the forecast, contract-specific terms, and other market inputs. These contracts are classified as Level 3 valuations.

Commodity Derivatives Under FTP. These contracts are valued based on market approaches which utilize Chicago Mercantile Exchange ("CME") quoted prices and other observable inputs. Swap contracts are valued using a pricing model based on CME inputs and are subject to nonperformance risk outside of the exit price. These contracts are classified as Level 2 valuations.

See Note 12 Derivatives Not Receiving Hedge Accounting Treatment Commodity Derivatives and Derivatives Under FTP for a discussion of the nature and purpose of coal contracts and derivatives under TVA's FTP.


30

Table of Contents                                                                                 

Nonperformance Risk

The assessment of nonperformance risk, which includes credit risk, considers changes in current market conditions, readily available information on nonperformance risk, letters of credit, collateral, other arrangements available, and the nature of master netting arrangements. TVA is a counterparty to currency swaps, interest rate swaps, commodity contracts, and other derivatives which subject TVA to nonperformance risk. Nonperformance risk on the majority of investments and certain exchange-traded instruments held by TVA is incorporated into the exit price that is derived from quoted market data that is used to mark the investment to market.

Nonperformance risk for most of TVA's derivative instruments is an adjustment to the initial asset/liability fair value. TVA adjusts for nonperformance risk, both of TVA (for liabilities) and the counterparty (for assets), by applying credit valuation adjustments ("CVAs") . TVA determines an appropriate CVA for each applicable financial instrument based on the term of the instrument and TVA's or the counterparty's credit rating as obtained from Moody's. For companies that do not have an observable credit rating, TVA uses internal analysis to assign a comparable rating to the counterparty. TVA discounts each financial instrument using the historical default rate (as reported by Moody's for CY 1983 to CY 2016) for companies with a similar credit rating over a time period consistent with the remaining term of the contract. The application of CVAs resulted in a $ 3 million decrease in the fair value of assets and a $ 1 million decrease in the fair value of liabilities at December 31, 2016 .


31

Table of Contents                                                                                 

Fair Value Measurements

The following tables set forth by level, within the fair value hierarchy, TVA's financial assets and liabilities that were measured at fair value on a recurring basis as of December 31, 2016 , and September 30, 2016 . Financial assets and liabilities have been classified in their entirety based on the lowest level of input that is significant to the fair value measurement. TVA's assessment of the significance of a particular input to the fair value measurement requires judgment and may affect the determination of the fair value of the assets and liabilities and their classification in the fair value hierarchy levels.
Fair Value Measurements
At December 31, 2016

 
Quoted Prices in Active
 Markets for
Identical Assets
(Level 1)
 
Significant Other
Observable Inputs
(Level 2)
 
Significant
Unobservable
Inputs
(Level 3)
 
Total
Assets
 
 
 
 
 
 
 
Investments
 
 
 
 
 
 
 
Equity securities
$
196

 
$

 
$

 
$
196

Government debt securities
74

 
52

 

 
126

Corporate debt securities

 
382

 

 
382

Mortgage and asset-backed securities

 
44

 

 
44

Institutional mutual funds
91

 

 

 
91

Forward debt securities contracts

 
14

 

 
14

Private equity funds measured at net asset value (1)

 

 

 
136

Private real estate funds measured at net asset value (1)

 

 

 
111

Commingled funds measured at net asset value (1)

 

 

 
1,193

Total investments
361

 
492

 

 
2,293

Commodity contract derivatives

 
19

 
9

 
28

 
 
 
 
 
 
 
 
Total
$
361

 
$
511

 
$
9

 
$
2,321

 
 
 
 
 
 
 
 
 
Quoted Prices in Active Markets for Identical Liabilities
(Level 1)
 
Significant Other
Observable Inputs
(Level 2)
 
Significant
Unobservable
Inputs
(Level 3)
 
Total
Liabilities
 
 
 
 
 
 
 
Currency swap(s) (2)
$

 
$
170

 
$

 
$
170

Interest rate swaps

 
1,497

 

 
1,497

Commodity contract derivatives

 
2

 
113

 
115

Commodity derivatives under FTP (2)
 

 
 

 
 

 
 
Swap contracts

 
5

 

 
5

 
 
 
 
 
 
 
 
Total
$

 
$
1,674

 
$
113

 
$
1,787

Notes
(1) Certain investments that are measured at fair value using the net asset value per share (or its equivalent) practical expedient have not been categorized in the fair value hierarchy. The fair value amounts presented in this table are intended to permit reconciliation of the fair value hierarchy to the amounts presented in the consolidated balance sheets.
(2)  Due to the right of setoff and method of settlement, TVA elects to record commodity derivatives under the FTP based on its net commodity position with the counterparty or FCM. Deposits are made to TVA's margin cash accounts held with each FCM to offset any net liability positions in full for derivatives that are transacted with FCMs. TVA records currency swaps net of cash collateral received from or paid to the counterparty, to the extent such amount is not recorded in Accounts payable and accrued liabilities. See Note 12 Offsetting of Derivative Assets and Liabilities .

32

Table of Contents                                                                                 

Fair Value Measurements
At September 30, 2016

 
Quoted Prices in Active
 Markets for
Identical Assets
(Level 1)
 
Significant Other
Observable Inputs
(Level 2)
 
Significant
Unobservable
Inputs
(Level 3)
 
Total
Assets
 
 
 
 
 
 
 
Investments
 
 
 
 
 
 
 
Equity securities
$
196

 
$

 
$

 
$
196

Government debt securities
88

 
36

 

 
124

Corporate debt securities

 
393

 

 
393

Mortgage and asset-backed securities

 
50

 

 
50

Institutional mutual funds
92

 

 

 
92

Forward debt securities contracts

 
15

 

 
15

Private equity funds measured at net asset value (1)

 

 

 
132

Private real estate funds measured at net asset value (1)

 

 

 
113

Commingled funds measured at net asset value (1)

 

 

 
1,142

Total investments
376

 
494

 

 
2,257

Commodity contract derivatives

 
5

 
4

 
9

 
 
 
 
 
 
 
 
Total
$
376

 
$
499

 
$
4

 
$
2,266

 
 
 
 
 
 
 
 
 
Quoted Prices in Active Markets for Identical Liabilities
(Level 1)
 
Significant Other
Observable Inputs
(Level 2)
 
Significant
Unobservable
Inputs
(Level 3)
 
Total
Liabilities
 
 
 
 
 
 
 
Currency swap(s) (2)
$

 
$
162

 
$

 
$
162

Interest rate swaps

 
1,938

 

 
1,938

Commodity contract derivatives

 
3

 
131

 
134

Commodity derivatives under FTP (2)
 
 
 

 
 

 
 
Swap contracts

 
9

 

 
9

 
 
 
 
 
 
 
 
Total
$

 
$
2,112

 
$
131

 
$
2,243


Notes
(1) Certain investments that are measured at fair value using the net asset value per share (or its equivalent) practical expedient have not been categorized in the fair value hierarchy. The fair value amounts presented in this table are intended to permit reconciliation of the fair value hierarchy to the amounts presented in the consolidated balance sheets.
(2)  Due to the right of setoff and method of settlement, TVA elects to record commodity derivatives under the FTP based on its net commodity position with the counterparty or FCM. Deposits are made to TVA's margin cash accounts held with each FCM to offset any net liability positions in full for derivatives that are transacted with FCMs. TVA records currency swaps net of cash collateral received from or paid to the counterparty, to the extent such amount is not recorded in Accounts payable and accrued liabilities. See Note 12 Offsetting of Derivative Assets and Liabilities .


33

Table of Contents                                                                                 

TVA uses internal valuation specialists for the calculation of its commodity contract derivatives fair value measurements classified as Level 3. Analytical testing is performed on the change in fair value measurements each period to ensure the valuation is reasonable based on changes in general market assumptions. Significant changes to the estimated data used for unobservable inputs, in isolation or combination, may result in significant variations to the fair value measurement reported.

The following table presents a reconciliation of all commodity contract derivatives measured at fair value on a recurring basis using significant unobservable inputs (Level 3):
Fair Value Measurements Using Significant Unobservable Inputs
 
 
 
Commodity Contract Derivatives
Balance at September 30, 2015
$
(98
)
 
Net unrealized gains (losses) deferred as regulatory assets and liabilities
(25
)
 
Balance at December 31, 2015
$
(123
)
 
 
 
 
Balance at September 30, 2016
$
(127
)
 
Net unrealized gains (losses) deferred as regulatory assets and liabilities
23

 
Balance at December 31, 2016
$
(104
)
 

The following table presents quantitative information related to the significant unobservable inputs used in the measurement of fair value of TVA's assets and liabilities classified as Level 3 in the fair value hierarchy:
Quantitative Information about Level 3 Fair Value Measurements  
 
Fair Value at December 31
 2016
 
Valuation Technique(s)
 
Unobservable Inputs
 
Range
 
 
 
 
 
 
 
 
 
 
Assets
 
 
 
 
 
 
 
 
Commodity contract derivatives
$
9

   
Pricing model
 
Coal supply and demand
 
0.7 - 0.8 billion tons/year
 
 
 
 
 
 
Long-term market prices
 
$11.65 - $85.02/ton
 
Liabilities
 
 
 
 
 
 
 
 
Commodity contract derivatives
$
113

 
Pricing model
 
Coal supply and demand
 
0.7 - 0.8 billion tons/year
 
 
 
 
 
 
Long-term market prices
 
$11.65 - $85.02/ton
 


Quantitative Information about Level 3 Fair Value Measurements  
 
Fair Value at September 30 2016
 
Valuation Technique(s)
 
Unobservable Inputs
 
Range
 
 
 
 
 
 
 
 
 
 
Assets
 
 
 
 
 
 
 
 
Commodity contract derivatives
$
4

 
Pricing model
 
Coal supply and demand
 
0.7 - 0.8 billion tons/year
 
 
 
 
 
 
Long-term market prices
 
$11.80 - $85.02/ton
 
Liabilities
 
 
 
 
 
 
 
 
Commodity contract derivatives
$
131

 
Pricing model
 
Coal supply and demand
 
0.7 - 0.8 billion tons/year
 
 
 
 
 
 
Long-term market prices
 
$11.80 - $85.02/ton
 


34

Table of Contents                                                                                 

Other Financial Instruments Not Recorded at Fair Value
          
TVA uses the methods and assumptions described below to estimate the fair value of each significant class of financial instrument. The fair values of the financial instruments held at December 31, 2016 , and September 30, 2016 , may not be representative of the actual gains or losses that will be recorded when these instruments mature or are called or presented for early redemption. The estimated values of TVA's financial instruments not recorded at fair value at December 31, 2016 , and September 30, 2016 , were as follows:
Estimated Values of Financial Instruments Not Recorded at Fair Value
 
 
 
At December 31, 2016
 
At September 30, 2016
 
Valuation Classification
 
Carrying
Amount
 
Fair
Value
 
Carrying
Amount
 
Fair
Value
EnergyRight ® receivables (including current portion)
Level 2
 
$
139

 
$
142

 
$
141

 
$
144

 
 
 
 
 
 
 
 
 
 
Loans and other long-term receivables, net (including current portion)
Level 2
 
$
152

 
$
142

 
$
141

 
$
130

 
 
 
 
 
 
 
 
 
 
EnergyRight ® financing obligation (including current portion)
Level 2
 
$
161

 
$
180

 
$
163

 
$
183

 
 
 
 
 
 
 
 
 
 
Unfunded loan commitments
Level 2
 
$

 
$
8

 
$

 
$
17

 
 
 
 
 
 
 
 
 
 
Membership interest of variable interest entity subject to mandatory redemption (including current portion)
Level 2
 
$
35

 
$
43

 
$
35

 
$
46

 
 
 
 
 
 
 
 
 
 
Long-term outstanding power bonds (including current maturities), net
Level 2
 
$
21,896

 
$
25,673

 
$
22,456

 
$
28,620

 
 
 
 
 
 
 
 
 
 
Long-term debt of variable interest entities (including current maturities), net
Level 2
 
$
1,235

 
$
1,362

 
$
1,234

 
$
1,468

 
 
 
 
 
 
 
 
 
 
Long-term notes payable (including current maturities)
Level 2
 
$
75

 
$
74

 
$
75

 
$
75


Due to the short-term maturity of Cash and cash equivalents, Restricted cash and investments, and Short-term debt, net (each considered a Level 1 valuation classification), the carrying amounts of these instruments approximate their fair values.

The fair value for loans and other long-term receivables is estimated by determining the present value of future cash flows using a discount rate equal to lending rates for similar loans made to borrowers with similar credit ratings and for similar remaining maturities, where applicable.

The fair value of long-term debt traded in the public market is determined by multiplying the par value of the debt by the indicative market price at the balance sheet date. The fair value of other long-term debt and membership interests of variable interest entity subject to mandatory redemption is estimated by determining the present value of future cash flows using current market rates for similar obligations, giving effect to credit ratings and remaining maturities.


35

Table of Contents                                                                                 

14.  Other Income (Expense), Net

Income and expenses not related to TVA’s operating activities are summarized in the following table:
Other Income (Expense), Net  
 
Three Months Ended
December 31
 
 
2016
 
2015
 
External services
$
3

 
$
4

 
Interest income
6

 
6

 
Gains (losses) on investments

 
3

 
Miscellaneous
3

 
(1
)
 
Total other income (expense), net
$
12

 
$
12

 

15.  Benefit Plans

TVA sponsors a qualified defined benefit pension plan ("pension plan") that covers most of its full-time employees hired before July 1, 2014, a qualified defined contribution plan ("401(k) plan") that covers most of its full-time employees, two unfunded post-retirement health care plans that provide for non-vested contributions toward the cost of eligible retirees' medical coverage, other postemployment benefits, such as workers' compensation, and the SERP. The pension plan and the 401(k) plan are administered by a separate legal entity, the TVA Retirement System ("TVARS"), which is governed by its own board of directors (the "TVARS Board").

The components of net periodic benefit cost and other amounts recognized as changes in regulatory assets for the three months ended December 31, 2016 and 2015 , were as follows:
Components of TVA’s Benefit Plans  
 
For the Three Months Ended December 31
 
 
Pension Benefits
 
Other Post-Retirement Benefits
 
 
2016
 
2015
 
2016
 
2015
 
Service cost
$
17

 
$
32

 
$
5

 
$
4

 
Interest cost
116

 
140

 
5

 
7

 
Expected return on plan assets
(114
)
 
(111
)
 

 

 
Amortization of prior service credit
(25
)
 
(6
)
 
(6
)
 
(1
)
 
Recognized net actuarial loss
116

 
73

 
3

 
2

 
Total net periodic benefit cost as actuarially determined
110

 
128

 
7

 
12

 
Amount capitalized due to actions of regulator
(34
)
 
(58
)
 

 

 
Total net periodic benefit cost
$
76

 
$
70

 
$
7

 
$
12

 

TVA contributes to the pension plan such amounts as are necessary on an actuarial basis to provide the pension plan with assets sufficient to meet TVA-funded benefit obligations to be paid to members. TVA contributed $275 million to TVARS in 2016 and expects to contribute $ 300 million in 2017. As of December 31, 2016 , TVA had contributed $75 million to TVARS and expects to contribute the remaining $225 million by September 30, 2017. TVA also contributed $20 million and $9 million to the 401(k) plan during the three months ended December 31, 2016 and 2015 , respectively. TVA does not separately set aside assets to fund its other post-retirement benefit plans, but rather funds such benefits on an as-paid basis. TVA provided approximately $ 20 million and $ 17 million , net of rebates and subsidies, to other post-retirement benefit plans for the three months ended December 31, 2016 and 2015 , respectively. TVA includes its cash contributions to the pension plan in the rate-making formula; accordingly, TVA recognizes pension costs as regulatory assets to the extent that the amount calculated under GAAP as pension expense differs from the amount TVA contributes to the pension plan.

16.  Contingencies and Legal Proceedings

Contingencies

Nuclear Insurance .  The Price-Anderson Act provides a layered framework of protection to compensate for losses arising from a nuclear event in the United States.  For the first layer, all of the NRC nuclear plant licensees, including TVA,

36

Table of Contents                                                                                 

purchase $ 375 million of nuclear liability insurance from American Nuclear Insurers for each plant with an operating license.  Funds for the second layer, the Secondary Financial Program, would come from an assessment of up to $ 127 million from the licensees of each of the 102 NRC licensed reactors in the United States.  The assessment for any nuclear accident would be limited to $ 19 million per year per unit.  American Nuclear Insurers, under a contract with the NRC, administers the Secondary Financial Program.  With its seven licensed units, TVA could be required to pay a maximum of $ 891 million per nuclear incident, but it would have to pay no more than $ 133 million per incident in any one year.  When the contributions of the nuclear plant licensees are added to the insurance proceeds of $ 375 million , over $ 13.0 billion , including a five percent surcharge for legal expenses, would be available.  Under the Price-Anderson Act, if the first two layers are exhausted, the U.S. Congress is required to take action to provide additional funds to cover the additional losses.

TVA carries property, decommissioning, and decontamination insurance of $ 5.1 billion for its licensed nuclear plants, with up to $ 2.1 billion available for a loss at any one site, to cover the cost of stabilizing or shutting down a reactor after an accident.  Some of this insurance, which is purchased from Nuclear Electric Insurance Limited ("NEIL") , may require the payment of retrospective premiums up to a maximum of approximately $ 132 million .

TVA purchases accidental outage (business interruption) insurance for TVA’s nuclear sites from NEIL.  In the event that an accident covered by this policy takes a nuclear unit offline or keeps a nuclear unit offline, NEIL will pay TVA, after a waiting period, an indemnity (a set dollar amount per week) up to a maximum indemnity of $ 490 million per unit.  This insurance policy may require the payment of retrospective premiums up to a maximum of approximately $ 37 million .

Decommissioning Costs.   TVA recognizes legal obligations associated with the future retirement of certain tangible long-lived assets related primarily to coal-fired generating plants and nuclear generating plants, hydroelectric generating plants/dams, transmission structures, and other property-related assets. See Note 9 .

Nuclear Decommissioning .  Provision for decommissioning costs of nuclear generating units is based on options prescribed by the NRC procedures to dismantle and decontaminate the facilities to meet the NRC criteria for license termination. At December 31, 2016 , the estimated future decommissioning cost of $ 2.5 billion was included in AROs.  The actual decommissioning costs may vary from the derived estimates because of, among other things, changes in current assumptions, such as the assumed dates of decommissioning, changes in regulatory requirements, changes in technology, and changes in the cost of labor, materials, and equipment.  Utilities that own and operate nuclear plants are required to use different procedures in calculating nuclear decommissioning costs under GAAP than those that are used in calculating nuclear decommissioning costs when reporting to the NRC.  The two sets of procedures produce different estimates for the costs of decommissioning primarily because of differences in the underlying assumptions.

TVA maintains a NDT to provide funding for the ultimate decommissioning of its nuclear power plants.  See Note 13 . TVA monitors the value of its NDT and believes that, over the long term and before cessation of nuclear plant operations and commencement of decommissioning activities, adequate funds from investments and additional contributions, if necessary, will be available to support decommissioning.  TVA’s operating nuclear power units are licensed through 2033 - 2055, depending on the unit.  It may be possible to extend the operating life of some of the units with approval from the NRC. 

Non-Nuclear Decommissioning .  The estimated future non-nuclear decommissioning ARO was $ 1.6 billion at December 31, 2016 .  This decommissioning cost estimate involves estimating the amount and timing of future expenditures and making judgments concerning whether or not such costs are considered a legal obligation.  Estimating the amount and timing of future expenditures includes, among other things, making projections of the timing and duration of the asset retirement process and how costs will escalate with inflation.  The actual decommissioning costs may vary from the derived estimates because of changes in current assumptions, such as the assumed dates of decommissioning, changes in regulatory requirements, changes in technology, and changes in the cost of labor, materials, and equipment.

TVA maintains an ART to help fund the ultimate decommissioning of its power assets.  See Note 13 . Estimates involved in determining if additional funding will be made to the ART include inflation rate, rate of return projections on the fund investments, and the planned use of other sources to fund decommissioning costs.  

Environmental Matters. TVA’s power generation activities, like those across the utility industry and in other industrial sectors, are subject to most federal, state, and local environmental laws and regulations.  Major areas of regulation affecting TVA’s activities include air quality control, water quality control, and management and disposal of solid and hazardous wastes.  In the future, regulations in all of these areas are expected to become more stringent.  Regulations are also expected to apply to new emissions and sources, with a particular emphasis on climate change, renewable generation, and energy efficiency.

TVA has incurred, and expects to continue to incur, substantial capital and operating and maintenance costs to comply with evolving environmental requirements primarily associated with, but not limited to, the operation of TVA’s coal-fired generating units.  Environmental requirements placed on the operation of TVA’s coal-fired and other generating units will likely continue to become more restrictive over time. Litigation over emissions or discharges from coal-fired generating units is also occurring, including litigation against TVA.  Failure to comply with environmental and safety laws can result in TVA being subject

37

Table of Contents                                                                                 

to enforcement actions, which can lead to the imposition of significant civil liability, including fines and penalties, criminal sanctions, and/or the shutting down of non-compliant facilities .

TVA estimates that compliance with existing and future Clean Air Act ("CAA") requirements (excluding greenhouse gas ("GHG") requirements) could lead to costs of approximately $335 million from 2017 to 2021, which include future clean air controls, existing controls capital projects, and air operations and maintenance projects. The majority of the $335 million is expected to be spent by 2018 on new controls at Gallatin and Shawnee.   TVA also estimates additional expenditures of $1.2 billion from 2017 to 2022 relating to TVA’s coal combustion residuals ("CCR") conversion program as well as expenditures of approximately $400 million from 2017 to 2023 relating to compliance with Clean Water Act requirements. There could be additional material costs if new environmental laws or regulations become applicable to TVA or the facilities it operates, or if existing environmental laws or regulations are revised or reinterpreted.  There could also be costs that cannot reasonably be predicted at this time, due to uncertainty of actions, that could increase these estimates.

Liability for releases and cleanup of hazardous substances is primarily regulated by the federal Comprehensive Environmental Response, Compensation, and Liability Act, and other federal and parallel state statutes.  In a manner similar to many other industries and power systems, TVA has generated or used hazardous substances over the years.

On November 22, 2016, the United States District Court for the Eastern District of North Carolina entered a consent decree that resolved all issues associated with the Ward Transformer site.  TVA settled all its remaining potential liability for $10 thousand .

TVA operations at some facilities have resulted in contamination that TVA is addressing.  At December 31, 2016 , and September 30, 2016 , respectively, TVA’s estimated liability for cleanup and similar environmental work for those sites for which sufficient information is available to develop a cost estimate was approximately $22 million and $23 million on a non-discounted basis, and was included in Accounts payable and accrued liabilities and Other long-term liabilities on the Consolidated Balance Sheets.
    
Legal Proceedings

From time to time, TVA is party to or otherwise involved in lawsuits, claims, proceedings, investigations, and other legal matters ("Legal Proceedings") that have arisen in the ordinary course of conducting TVA's activities, as a result of a catastrophic event or otherwise.  
 
General. At December 31, 2016 , TVA had accrued $ 51 million of probable losses with respect to Legal Proceedings. Of the accrued amount, $ 15 million is included in Other long-term liabilities and $ 36 million is included in Accounts payable and accrued liabilities.  TVA is currently unable to estimate any amount or any range of amounts of reasonably possible losses, and no assurance can be given that TVA will not be subject to significant additional claims and liabilities.  If actual liabilities significantly exceed the estimates made, TVA's results of operations, liquidity, and financial condition could be materially adversely affected.
 
Environmental Agreements . In April 2011, TVA entered into two substantively similar agreements, one with the EPA and the other with Alabama, Kentucky, North Carolina, Tennessee, and three environmental advocacy groups: the Sierra Club, the National Parks Conservation Association, and Our Children's Earth Foundation (collectively, the "Environmental Agreements”). They became effective in June 2011. Under the Environmental Agreements, TVA committed to (1) retire on a phased schedule 18 coal-fired units with a combined summer net dependable capability of 2,200 MW, (2) control, convert, or retire additional coal-fired units with a combined summer net dependable capability of 3,500 MW, (3) comply with annual, declining emission caps for SO 2 and NO x , (4) invest $ 290 million in certain TVA environmental projects, (5) provide $ 60 million to Alabama, Kentucky, North Carolina, and Tennessee to fund environmental projects, and (6) pay civil penalties of $ 10 million . In exchange for these commitments, most past claims against TVA based on alleged New Source Review and associated violations were waived and cannot be brought against TVA. Future claims, including those for sulfuric acid mist and GHG emissions, can still be brought against TVA, and claims for increases in particulates can also be pursued at many of TVA’s coal-fired units. Additionally, the Environmental Agreements do not address compliance with new laws and regulations or the cost associated with such compliance.

Case Involving Tennessee Valley Authority Retirement System .  In March 2010, eight current and former participants in and beneficiaries of TVARS filed suit in the United States District Court for the Middle District of Tennessee challenging the TVARS Board's 2009 decision to amend the TVARS Rules and Regulations (“Rules”) in exchange for a $1 billion contribution from TVA. The changes approved by the TVARS Board (1) suspended the TVA contribution requirements for 2010 through 2013, (2) reduced the calculation for cost-of-living adjustments ("COLAs") for CY 2010 through CY 2013, (3) reduced the interest crediting rate for the fixed fund accounts, and (4) increased the eligibility age to receive COLAs from age 55 to 60 . The plaintiffs alleged that these changes violated their constitutional rights (due process, equal protection, and property rights), violated the Administrative Procedure Act, and violated the substantive and procedural components of an anti-cutback provision in the Rules. TVA and the plaintiffs filed cross motions for summary judgment. In August 2015, the court granted TVA’s motion for summary judgment and dismissed the case with prejudice. In September 2015, the plaintiffs appealed this decision to the United States Court of Appeals for the Sixth Circuit (the "Sixth Circuit"). On August 12, 2016, the Sixth Circuit held that the plaintiffs’ rights

38

Table of Contents                                                                                 

were not violated because COLAs are not vested benefits. A few other issues were remanded to the district court for further proceedings.

Cases Involving Gallatin Fossil Plant CCR Facilities. In January 2015, the State of Tennessee filed a lawsuit against TVA in the Chancery Court for Davidson County, Tennessee. The lawsuit alleges that waste materials have been released into waters of the state from CCR facilities at Gallatin Fossil Plant ("Gallatin") in violation of the Tennessee Water Quality Control Act and the Tennessee Solid Waste Disposal Act. TDEC is seeking injunctive relief, which could include an order requiring TVA to relocate the CCR facilities. TDEC is also requesting civil penalties of up to $17,000 per day for each day TVA is found to have violated the statutes. In February 2015, the court issued an order allowing the Tennessee Scenic Rivers Association ("TSRA") and the Tennessee Clean Water Network ("TCWN") to intervene in the case. In January 2016, the court issued an agreed temporary injunction proposed by the State of Tennessee and TVA requiring TVA to conduct further environmental studies at Gallatin to determine the extent of soil, surface water, and groundwater contamination by CCR material at the site and to support the development of any necessary corrective action plan in cooperation with the other parties. Pursuant to the injunction, TVA submitted an Environmental Investigation Plan ("EIP") to the State of Tennessee on March 18, 2016. Following State comments on the draft EIP, TVA submitted a revised EIP to the State on June 20, 2016. On June 30, 2016, the State provided conditional approval to proceed with a portion of the investigation. In late September through early December 2016, the State provided additional approvals to proceed with other portions of the investigation. Trial in this action is scheduled to begin in October 2017.

In April 2015, TSRA and TCWN filed a separate lawsuit against TVA in the United States District Court for the Middle District of Tennessee alleging that waste materials have been released into the Cumberland River from CCR facilities at Gallatin in violation of the Clean Water Act. The plaintiffs are seeking injunctive relief, which could include an order requiring TVA to relocate the CCR facilities. The plaintiffs are also requesting civil penalties of up to $37,500 per violation per day. In June 2015, TVA filed a motion to dismiss the majority of the claims in the federal case based on the State of Tennessee’s diligent prosecution of substantially overlapping claims in its state court action. Since then, TVA has filed several other motions seeking to dismiss all claims in the case on other bases as well. In September 2016, the court ruled on all pending motions. The court held, among other things, that (1) TVA could be liable for civil penalties under the Clean Water Act and (2) the lawsuit could proceed to trial but the court could consider issues only to the extent that they are not being considered in the state court action.  In December 2016, the court denied TVA's motion to reconsider the court's decision that TVA could be liable for civil penalties. Trial is currently scheduled for January 30, 2017.

The costs associated with relocating the CCR facilities if required to do so by a court could be substantial, as could be any civil penalties TVA is ordered to pay.

Administrative Proceeding Regarding Browns Ferry Nuclear Plant Extended Power Uprate. In September 2016, the BEST and Mothers Against Tennessee River Radiation requested a hearing and sought to intervene in TVA’s license amendment request for extended power uprates at Browns Ferry Nuclear Plant. The petitioners contend that TVA's application did not correctly report the potential risk from operating at increased power levels. TVA and the NRC staff filed answers opposing the petition to intervene in October 2016. The ASLB rejected the petition to intervene in November 2016. The petitioners appealed the ASLB's decision to the NRC in November 2016. TVA and the NRC staff filed answers opposing the appeal in December 2016, and the petitioners have filed their response.

Bull Run Fossil Plant Clean Air Act Permit . In September 2015, the Sierra Club and Environmental Integrity Project filed a petition with the EPA requesting that the EPA object to the CAA renewal permit issued by TDEC to TVA for operations at Bull Run. The petitioners alleged that the permit contained impermissibly lax monitoring requirements for opacity. In February 2016, the petitioners sued the EPA for not responding to the petition in a timely manner. In August 2016, the United States District Court for the District of Columbia entered a consent decree requiring the EPA to respond to the petition by November 10, 2016.  On November 10, 2016, the EPA granted the petition and ordered TDEC to revise the permit to assure compliance with the opacity limits.  The permit remains in effect during this process.

Gallatin Fossil Plant Clean Air Act Permit . In August 2016, the Sierra Club filed a petition with the EPA requesting that the EPA object to the CAA renewal permit issued by TDEC to TVA for operations at Gallatin. The petition alleges that the permit (1) contains compliance evaluation requirements for opacity, particulate matter, and fugitive dust that are impermissibly lax, (2) includes allowances for startup, shutdown, and malfunctions that are inconsistent with the CAA, (3) fails to include reporting requirements to ensure compliance with the Environmental Agreements, and (4) contains impermissibly high SO 2 emission limits. The EPA has not yet acted on the petition.


39

Table of Contents                                                                                 

ITEM 2.  MANAGEMENT’S DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND RESULTS OF OPERATIONS
(Dollars in millions except where noted)

Management’s Discussion and Analysis of Financial Condition and Results of Operations ("MD&A") explains the results of operations and general financial condition of the Tennessee Valley Authority ("TVA") . The MD&A should be read in conjunction with the accompanying unaudited consolidated financial statements and TVA's Annual Report on Form 10-K for the fiscal year ended September 30, 2016 (the “Annual Report”).

Executive Overview

TVA had net income of $102 million for the three months ended December 31, 2016, compared with a net loss of $37 million for the three months ended December 31, 2015. As is typical for electric utilities, weather is a primary driver of TVA’s sales. TVA’s service territory experienced more normal weather during the three months ended December 31, 2016, compared to the significantly milder weather during the three months ended December 31, 2015, resulting in higher energy sales. Sales to directly served customers were also higher due to increased production at certain facilities. Total operating revenue was 12 percent greater during the first quarter of 2017 as compared to the same period of the prior year due to higher sales volume, increased fuel cost recovery, and the base rate increase effective October 1, 2016.

Total operating expenses were relatively flat during the first quarter of 2017 as compared to the same period of the prior year. Total fuel and purchased power costs increased due to increased sales volume, higher natural gas prices, and a change in generation mix utilized to meet demand. Generation from TVA assets produced seven percent more energy during the three months ended December 31, 2016, as compared with the same period of the prior year. This higher energy production was primarily due to higher coal-fired and nuclear generation, while hydroelectric generation decreased significantly due to drought conditions in the first quarter of 2017. Operating and maintenance expense remained relatively flat for the three months ended December 31, 2016, as compared to the same period of the prior year, primarily due to a decrease in inventory and project write-offs and the timing of coal outages offset by an increase in the duration of nuclear outages and retirement-related benefit expenses. Because of a strong financial position in 2016, TVA was able to fund capital projects primarily from operating funds and anticipates continuing to do so in 2017 with fewer planned major projects.

On October 19, 2016, TVA’s Watts Bar Nuclear Plant ("Watts Bar") Unit 2 was declared commercially operational, becoming the first new U.S. nuclear generating unit to be brought online in the 21st century. Construction on TVA’s two natural gas-fired generation facilities continues to advance. The facility at the Paradise Fossil Plant ("Paradise") site is expected to be completed in the spring of 2017, and the facility at the Allen Fossil Plant ("Allen") site is expected to be completed in 2018. TVA also expanded its renewable energy supply when the River Bend Solar Energy Center located in northern Alabama was commissioned in November 2016.

Work on the Gallatin Fossil Plant ("Gallatin") selective catalytic reduction system (“SCR”) continues with the first two SCRs expected to be completed in the spring of 2017 and the second two SCRs expected to be completed in the fall of 2017. Work on the Shawnee Fossil Plant ("Shawnee") emissions reductions for Units 1 and 4 is underway, and its scrubbers and SCRs are expected to be operational in the fall of 2017.

With the completion of Watts Bar Unit 2, and the two natural gas-fired generation facilities currently under construction at the Paradise site and the Allen site, TVA does not foresee needing additional large, baseload generation units for the foreseeable future. TVA projects a minimal sales growth rate based in part on market changes impacting electric utilities, including stringent energy efficiency standards, technological advances, and evolving customer behaviors, as well as increased individual, government, and business use of distributed generation, the entrance of non-traditional competitors into the power delivery system markets, regulatory policies, and grid and storage technology advancements. TVA’s demand projections also factored into the decision to sell the Bellefonte Nuclear Plant ("Bellefonte") site, and on November 14, 2016, TVA entered into a contract to sell substantially all of its Bellefonte property.
    

40

Table of Contents                                                                                 

Results of Operations

Sales of Electricity

The following tables compare TVA’s energy sales for the three months ended December 31, 2016 and 2015 :    
 
Sales of Electricity
 
 
(millions of kWh)
 
SALESOFELECTRICITYA13.JPG
Note
(1) Includes approximately 536 million kWh of pre-commercial generation at Watts Bar Unit 2 and Paradise Combined Cycle plant. See Note 1 Pre-Commercial Plant Operations .
             
TVA uses degree days to measure the impact of weather on its power operations since weather affects both demand and market prices for electricity. Degree days measure the extent to which average temperatures in the five largest cities in TVA's service area vary from 65 degrees Fahrenheit.
TVE-10Q2ND_CHARTX14977A03.JPG
Notes
* Normal heating degree days for the three months ended December 31, 2016 and 2015 , were 1,302. This calculation is updated every five years in order to
incorporate data for the then-most-recent 30 years. It was last updated in 2011.
** Normal cooling degree days for the three months ended December 31, 2016 and 2015 , were 67. This calculation is updated every five years in order to
incorporate data for the then-most-recent 30 years. It was last updated in 2011.

41

Table of Contents                                                                                 


Sales of electricity increased approximately seven percent for the three months ended December 31, 2016 , as compared to same period in the prior year, primarily due to increased sales volume for LPCs driven primarily by a 29 percent increase in heating degree days. Additionally, sales to industries directly served increased moderately primarily as a result of economic conditions affecting certain customers. Partially offsetting these increases was a decrease in sales to federal agencies and other primarily as a result of a decrease in off-system sales, as TVA had less excess generation available for sale to the market as compared to the same period of the prior year.

Financial Results

The following table compares operating results for the three months ended December 31, 2016 and 2015 :
Summary Consolidated Statements of Operations  
 
Three Months Ended December 31
 
 
2016
 
2015
 
Percent Change
 
Operating revenues
$
2,546

 
$
2,280

 
11.7
%
 
Operating expenses
2,117

 
2,052

 
3.2
%
 
Operating income
429

 
228

 
88.2
%
 
Other income, net
12

 
12

 
%
 
Interest expense, net
339

 
277

 
22.4
%
 
Net income (loss)
$
102

 
$
(37
)
 
375.7
%
 

Operating Revenues.   Operating revenues for the three months ended December 31, 2016 and 2015 , consisted of the following:
OPERATINGREVENUEA03.JPG
Note
The 2016 amounts in the chart above exclude a contra-revenue amount of approximately $14 million representing revenue capitalized during pre-commercial operations at Watts Bar Unit 2 and Paradise Combined Cycle plant. See Note 1 Pre-Commercial Plant Operations .

TVA's rate structures provide price signals intended to reflect higher cost periods to serve LPCs and their end-use customers. Under these structures, weather can positively or negatively impact both volume and effective rates. This is because the wholesale structure includes two components: a demand charge and an energy charge. The demand charge is based on the customer's peak monthly usage and increases as the peak increases. The energy charge is based on the kWhs used by the customer. The rate structures also include a separate fuel rate that includes the costs of natural gas, fuel oil, purchased power, coal, emission allowances, nuclear fuel, and other fuel-related commodities; realized gains and losses on derivatives purchased to hedge the costs of such commodities; and tax equivalents associated with the fuel cost adjustments.

42

Table of Contents                                                                                 

The changes in components of operating revenues for the three months ended December 31, 2016 , compared to the three months ended December 31, 2015 , are as follows:
 
Three Months Ended December 31, 2016
 
Three Months Ended December 31, 2015
 
Variance
Base revenue
$
1,716

(1)  
$
1,561

 
$
155

Fuel cost recovery
791

 
681

 
110

Off-system sales
1

 
4

 
(3
)
Revenue from sales of electricity
2,508

 
2,246

 
262

Other revenue
38

 
34

 
4

Total operating revenues
$
2,546

 
$
2,280

 
$
266

Note
(1) Excludes approximately $14 million of revenue capitalized during pre-commercial operations at Watts Bar Unit 2 and Paradise Combined Cycle plant. See Note 1 Pre-Commercial Plant Operations .
    
Operating revenues increased $266 million for the three months ended December 31, 2016 , as compared to the same period of the prior year, primarily due to a $155 million increase in base revenue and a $110 million increase in fuel cost recovery revenues.  The $155 million increase in base revenue was predominantly driven by an increase of $123 million resulting from higher sales volume during the three months ended December 31, 2016, as compared to same period of the prior year. In addition, approximately $46 million of the increase in base revenue was attributable to higher effective rates during the three months ended December 31, 2016, as compared to the same period of the prior year, resulting from the base rate adjustment that became effective October 1, 2016. Partially offsetting this increase in base revenue was the capitalization of approximately $14 million of revenue, resulting from pre-commercial generation at Watts Bar Unit 2 and Paradise Combined Cycle plant. See Note 1 Pre-Commercial Plant Operations . The $110 million increase in fuel cost recovery revenues reflects a $50 million increase attributable to higher energy sales and a $60 million increase attributable to higher fuel rates.  The higher fuel rates experienced were primarily driven by higher market prices for natural gas and a change in the mix of generation resources.
    
Operating Expenses. Operating expenses for the three months ended December 31, 2016 and 2015 , consisted of the following:

TVE-10Q2ND_CHARTX20835A03.JPG TVE-10Q2ND_CHARTX22065A03.JPG

43

Table of Contents                                                                                 

The following chart summarizes TVA's net generation and purchased power in millions of kWh by generating source for the periods indicated:
Power Supply from TVA-Operated Generation Facilities and Purchased Power
(millions of kWh)
 
Three Months Ended December 31
 
 
2016
 
2015
 
Coal-fired
10,190

 
27
%
 
8,504

 
25
%
 
Nuclear (1)
15,254

 
41
%
 
12,359

 
35
%
 
Hydroelectric
1,692

 
5
%
 
4,531

 
13
%
 
Natural gas and/or oil-fired
5,328

 
14
%
 
4,911

 
14
%
 
Total TVA-operated generation facilities
32,464

 
87
%
 
30,305

 
87
%
 
Purchased power (non-renewable) (2)
3,147

 
9
%
 
1,729

 
5
%
 
Purchased power (renewable) (3)
1,505

 
4
%
 
2,789

 
8
%
 
Total purchased power
4,652

 
13
%
 
4,518

 
13
%
 
Total power supply
37,116

 
100
%
 
34,823

 
100
%
 
Notes
(1) The nuclear amount for the three months ended December 31, 2016, includes approximately 536 million kWh of pre-commercial generation at Watts Bar Unit 2 and Paradise Combined Cycle plant. See Note 1 Pre-Commercial Plant Operations .
(2) Purchased power (non-renewable) includes generation from Caledonia Combined Cycle Plant, which is currently a leased facility operated by TVA. Generation from Caledonia Combined Cycle Plant was 1,035 million kWh and 815 million kWh for the quarters ended December 31, 2016 and 2015 , respectively.
(3) Purchased power (renewable) includes power purchased from the following renewable sources: hydroelectric, solar, wind, and cogeneration.

Three Months Ended December 31, 2016 , Compared to Three Months Ended December 31, 2015
TVE-10Q1ST_CHARTX08577.JPG
Fuel
Fuel expense increased $88 million for the three months ended December 31, 2016, as compared to the same period of the prior year. The increase in fuel expense was due in part to changes in the mix of generation resources and higher market prices for natural gas, which collectively contributed approximately $40 million to the increase. As an indication of general market direction, the average Henry Hub natural gas spot price for the three months ended December 31, 2016, was approximately 43 percent higher than the same period of the prior year. Additionally, a seven percent increase in generation from TVA-owned resources contributed approximately $32 million to the increase in fuel expense.



TVE-10Q1ST_CHARTX09554.JPG
Purchased Power
Purchased power expense decreased $5 million for the three months ended December 31, 2016, as compared to the same period of the prior year. Decreases due to a lower amount of realized losses associated with closing positions under the suspended FTP and a change in the resource mix were partially offset by higher natural gas prices and a three percent increase in the volume of power purchased.


TVE-10Q1ST_CHARTX10399.JPG
Operating and Maintenance
Operating and maintenance expense remained relatively flat for the three months ended December 31, 2016, as compared to the same period of the prior year. This was due in part to a $19 million decrease in planned outage expense due primarily to the timing of planned coal outages. Additionally, there was a $12 million decrease in inventory and project write-offs. These decreases in operating and maintenance expense were offset by an increase in benefit retirement costs primarily attributable to a $6 million increase in pension contributions and an $11 million increase in 401(k) matching contributions as a result of benefit plan amendments that became effective October 1, 2016. Additionally, there was a $17 million increase in planned nuclear refueling outage expense primarily due to an increase in the number of planned nuclear refueling outage days for the three months ended December 31, 2016, as compared to the same period of the prior year.


44

Table of Contents                                                                                 

TVE-10Q1ST_CHARTX11142.JPG
Depreciation and Amortization
Depreciation and amortization expense decreased $24 million for the three months ended December 31, 2016, as compared to same period of the prior year. Implementation of a new depreciation study during the three months ended December 31, 2016, resulted in approximately $56 million less depreciation expense. The decrease in depreciation expense as a result of the new depreciation rates is primarily attributable to the use of TVA's current generation plans, which resulted in changes in retirement date assumptions for coal-fired plants, and changes in the estimated service lives for transmission assets. See Note 1 — Depreciation . In addition, the retirement of Colbert Fossil Plant ("Colbert") Units 1-4 in March 2016 contributed $13 million to the decrease. Partially offsetting these decreases was an increase of approximately $45 million primarily from net additions to Completed plant, including a $33 million increase as the result of placing Watts Bar Unit 2 into service in October 2016.




TVE-10Q1ST_CHARTX11800.JPG
Tax Equivalents
Tax equivalents expense increased $5 million for the three months ended December 31, 2016, as compared to the same period of the prior year. This change primarily reflects an increase in the accrued tax equivalent expense related to the fuel cost adjustment mechanism, which is equal to five percent of the fuel cost adjustment mechanism revenues and increased for the three months ended December 31, 2016, as compared to the same period of the prior year.

Interest Expense .   Interest expense and interest rates for the three months ended December 31, 2016 and 2015 , were as follows:
Interest Expense
 
 Three Months Ended December 31
 
 
2016
 
2015
 
Percent
 Change
 
Interest Expense (1)
 
 
 
 
 
 
Interest expense
$
339

 
$
335

 
1.2
 %
 
Allowance for funds used during construction

 
(58
)
 
(100.0
)%
 
Net interest expense
$
339

 
$
277

 
22.4
 %
 
 
 
 
 
 
 
 
Average blended interest rate
5.15
%
 
5.17
%
 
(0.4
)%
 
Note
(1) Interest expense includes amortization of debt discounts, issuance, and reacquisition costs, net.

Net interest expense increased $62 million for the three months ended December 31, 2016, as compared to the same period of the prior year. In the first quarter of the prior year, TVA capitalized $58 million in allowance for funds used during construction ("AFUDC") related to the Watts Bar Unit 2 construction project.  TVA ended this capitalization on September 30, 2016.
Liquidity and Capital Resources

Sources of Liquidity

To meet cash needs and contingencies, TVA depends on various sources of liquidity.  TVA’s primary sources of liquidity are cash from operations and proceeds from the issuance of short-term and long-term debt.  Current liabilities may exceed current assets from time to time in part because TVA uses short-term debt to fund short-term cash needs, as well as to pay scheduled maturities and other redemptions of long-term debt. The daily balance of cash and cash equivalents maintained is based on near-term expectations for cash expenditures and funding needs.

In addition to cash from operations and proceeds from the issuance of short-term and long-term debt, TVA's sources of liquidity include a $150 million credit facility with the United States Department of the Treasury ("U.S. Treasury") , four long-term revolving credit facilities totaling $ 2.7 billion , and proceeds from financings. See Note 10 Credit Facility Agreements. Other financing arrangements may include lease financings and sales of loans, receivables, and other assets.

The TVA Act authorizes TVA to issue bonds, notes, or other evidences of indebtedness ("Bonds") in an amount not to exceed $30.0 billion outstanding at any time. At December 31, 2016 , TVA had $24.3 billion of Bonds outstanding (not including noncash items of foreign currency exchange gain of $188 million, unamortized debt issue costs of $60 million, and net discount on sale of Bonds of $98 million).  The balance of Bonds outstanding directly affects TVA’s capacity to meet operational liquidity

45

Table of Contents                                                                                 

needs and to strategically use Bonds to fund certain capital investments as management and the TVA Board may deem desirable.  Other options for financing not subject to the limit on Bonds, including lease financings (see Lease Financings below and Note 7 ), could provide supplementary funding if needed. Currently, TVA believes that it has adequate capability to fund its ongoing operational liquidity needs and make planned capital investments over the next decade through a combination of Bonds, additional power revenues through power rate increases, cost reductions, or other ways. See Lease Financings below, Note 7 , and Note 10 Credit Facility Agreements for additional information.

Debt Securities .  TVA’s Bonds are not obligations of the United States, and the United States does not guarantee the payments of principal or interest on Bonds. TVA’s Bonds consist of power bonds and discount notes. Power bonds have maturities of between one and 50 years. Discount notes have maturities of less than one year. Power bonds and discount notes have a first priority and equal claim of payment out of net power proceeds. Net power proceeds are defined as the remainder of TVA's gross power revenues after deducting the costs of operating, maintaining, and administering its power properties and payments to states and counties in lieu of taxes, but before deducting depreciation accruals or other charges representing the amortization of capital expenditures, plus the net proceeds from the sale or other disposition of any power facility or interest therein. In addition to power bonds and discount notes, TVA had outstanding at December 31, 2016 , the long-term debt of three variable interest entities. See Lease Financings below, Note 7 , and Note 10 Credit Facility Agreements for additional information.

The following table provides additional information regarding TVA's short-term borrowings.
Short-Term Borrowing Table
 
At
December 31
2016
 
Three Months Ended December 31 2016
 
At
December 31 2015
 
Three Months Ended December 31 2015
 
Amount Outstanding (at End of Period) or Average Amount Outstanding (During Period)
 
 
 
 
 
 
 
 
Discount Notes
$
2,027

 
$
1,391

 
$
1,504

 
$
1,163

 
Weighted Average Interest Rate
 
 
 
 
 
 
 
 
Discount Notes
0.499
%
 
0.330
%
 
0.234
%
 
0.089
%
 
Maximum Month-End Amount Outstanding (During Period)
 
 
 
 
 
 
 
 
Discount Notes
N/A

 
$
2,027

 
N/A

 
$
1,604

 

Lease Financings . TVA has entered into certain leasing transactions with special purpose entities to obtain third-party financing for its facilities. These special purpose entities are sometimes identified as variable interest entities ("VIEs") of which TVA is determined to be the primary beneficiary. TVA is required to account for these VIEs on a consolidated basis. See Note 7 and Note 10 for additional information about TVA’s lease financing activities. In 2016, TVA acquired 100 percent of the equity interests in certain special purpose entities created for the purpose of facilitating lease financing. TVA may seek to enter into similar arrangements in the future.

Summary Cash Flows

A major source of TVA's liquidity is operating cash flows resulting from the generation and sales of electricity. There was no net change in cash and cash equivalents for the three months ended December 31, 2016 . The net increase in cash and cash equivalents for the three months ended December 31, 2015 , was $11 million. A summary of cash flow components for the three months ended December 31, 2016 , and December 31, 2015 , follows:

    Cash provided by (used in):                         TVE-10Q2ND_CHARTX14779A03.JPG TVE-10Q2ND_CHARTX16174A03.JPG TVE-10Q2ND_CHARTX17109A03.JPG

46

Table of Contents                                                                                 

Operating Activities

TVA’s cash flows from operations are primarily driven by sales of electricity, fuel costs, and operating and maintenance costs. The timing and level of cash flows from operations can be affected by the weather, changes in working capital, commodity price fluctuations, outages, and other project expenses.

Net cash flows provided by operating activities increased $101 million for the three months ended December 31, 2016, as compared to the same period of the prior year, primarily as a result of increases in revenue collections due to higher sales and base rate changes offset partially by the increase in cash used for fuel purchases and the timing of pension contributions.

Investing Activities

The majority of TVA’s investing cash flows are due to investments to acquire, upgrade, or maintain generating and transmission assets, including environmental projects and the purchase of nuclear fuel.

Net cash flows used in investing activities decreased by $261 million for the three months ended December 31, 2016, as compared to the same period of the prior year, due to a decrease in major project spend, including the completion of Watts Bar Unit 2 and progress made on the Paradise Combined Cycle construction project.
    
Financing Activities

Net cash flows provided by financing activities decreased by $373 million for the three months ended December 31, 2016, as compared to the same period of the prior year, primarily due to higher redemptions of long-term bonds for the quarter ended December 31, 2016. This was partially offset by higher net issuance of short-term debt, with less cash needed to fund investing and other activities.

Key Initiatives and Challenges

Distributed Energy Resources

Changes in the energy delivery market will impact the way TVA and LPCs do business in the future. Energy efficiency and demand response are a growing part of TVA’s energy portfolio, and TVA wants to be positioned to proactively manage these resources to optimize their value for consumers in the Tennessee Valley. These resources, together with other options that are typically connected to the distribution systems of the LPCs, represent a new component in the utility marketplace called distributed energy resources ("DER") .

As technologies for producing energy using distributed s olar, micro turbines, and other types of smaller scale distributed resources are evolving, they are becoming more cost-competitive. Previously, absorbing the impact of electricity from the small number of distributed generation sites was well within the capacity of a system the size of TVA’s. As the amount of distributed generation grows on the TVA system, the need for TVA’s traditional generation resources may be reduced, and the ability of the system to reliably and economically operate in conjunction with these distributed generation sources may become more challenging. To meet this challenge, TVA is working with LPCs and others on long-term pricing and product development that includes DER products and addresses the implementation and support of those products.

TVA is also developing and managing demand side energy resources in collaboration with the LPC community. While TVA owns and operates its high-voltage transmission grid, the distribution system is a network of grids belonging to LPCs, each with its own characteristics and operational strengths and challenges. The growth of renewable resources on the distribution grid (primarily rooftop photovoltaic solar) necessitates the involvement of entities in addition to TVA, especially the LPCs . TVA and LPCs will need to focus on the safety and reliability impact of these resources as they are interconnected to the grid, as well as ensuring the pricing of electricity remains as low as feasible. D ue to uncertainties related to the technology choices and market penetration rates for DER options, TVA cannot currently predict the potential financial impacts from the future growth in DER, but it is anticipated that future growth will be a part of TVA’s overall strategy to meet customer demand while continuing to supply clean, reliable power in an evolving marketplace.

Generation Resources

Nuclear Response Capability . Since the events that occurred in 2011 at the Fukushima Daiichi Nuclear Power Plant ("Fukushima Events") , the Nuclear Regulatory Commission ("NRC") has issued and adopted additional detailed guidance on the expected response capability to be developed by each nuclear plant site. TVA submitted integrated strategies to the NRC on February 28, 2013. TVA is currently implementing strategies and physical plant modifications to address the actions outlined in this guidance for all of its nuclear plants. As of December 31, 2016 , TVA had spent $259 million on modifications related to these actions at all of its nuclear plants, including Watts Bar Unit 2, and expects to spend an additional $25 million to complete the remaining modifications intended to address this guidance.


47

Table of Contents                                                                                 

Extreme Flooding Preparedness. Updates to the TVA analytical hydrology model completed in 2009 indicated that under “probable maximum flood” conditions, some of TVA’s dams might not have been capable of regulating the higher flood waters.  A “probable maximum flood” is an extremely unlikely event; however, TVA is obligated to provide protection for its nuclear plants against such events.  As a result, TVA installed a series of temporary barriers to raise the height of four TVA dams to manage the issue on an interim basis.  Subsequent modifications have replaced the temporary barriers at three of the four dams, and work on the fourth, Fort Loudoun Dam, will continue after the completion of a Tennessee Department of Transportation project. During the third quarter of 2016, TVA was informed that work being done by the State of Tennessee to support the Fort Loudoun Dam modifications, originally scheduled to be completed in June 2016, is now estimated to be completed in mid-2018. TVA is taking steps to ensure that it complies with the NRC license requirements for Watts Bar related to the completion of the project.

Since 2009, TVA has performed further hydrology modeling of portions of the TVA watershed using updated modeling tools. TVA also substantially completed a series of permanent modifications to several other dams identified through the more recent analytical work. The modifications addressed and rectified the potential for certain dams to be overtopped during a “probable maximum flood” event as well as the potential for certain other dams to become unstable under “probable maximum flood” conditions. TVA has also made various improvements to plant protection features at Watts Bar and Sequoyah.
The revised hydrology models were reviewed and approved by the NRC for Watts Bar Units 1 and 2. However, TVA identified an error in the modeling that will require TVA to resubmit models for Watts Bar Units 1 and 2. TVA plans to seek NRC approval for similar modeling for Sequoyah Units 1 and 2 and will subsequently address conditions at Browns Ferry as needed. The updated models for Watts Bar and Sequoyah are expected to be submitted to the NRC in early CY 2018 for review and approval. TVA has deferred some modifications until these updated models are completed.
The hydrology analyses discussed above relate to the current operation and current requirements of TVA’s existing nuclear fleet.  In addition, the NRC has required all utilities to reexamine flood hazards at nuclear plants in light of the lessons learned from the Fukushima Events.  In March 2015, TVA sent its flood hazard analyses to the NRC for all three of its nuclear sites after considering the NRC’s Fukushima-related requirements.  Minor modifications to some of TVA’s nuclear plants may result from these analyses, and further modifications to TVA’s dams based on this analysis are expected.  Temporary protection measures are in place in the interim while the NRC review is underway. As of December 31, 2016 , TVA had spent $148 million on the modifications and improvements related to extreme flooding preparedness and expects to spend up to an additional $30 million to complete the modifications.
 
NRC Seismic Assessments . On May 9, 2014, the NRC notified licensees of nuclear power reactors in the central and eastern United States of the results of seismic hazard screening and prioritization evaluations performed by unit owners and
reviewed by the NRC staff. Because the seismic hazards for Browns Ferry, Sequoyah, and Watts Bar had increases in seismic parameters beyond the technical information available when the plants were designed and licensed, TVA must conduct seismic risk evaluations for these plants. TVA must complete the evaluation for Watts Bar by June 30, 2017, and the evaluations for Browns Ferry and Sequoyah by December 31, 2019.

Mitigation of Beyond-Design-Basis Events .  Supplementary NRC rulemaking is under development to mitigate beyond-design-basis flooding and seismic events.  The NRC staff submitted the draft final rule — Mitigation of Beyond-Design-Basis Events — to the NRC on December 15, 2016, requesting approval to publish the final rule. The final rule is not expected to be issued until mid-2017, and could result in TVA having to make modifications to one or more of its nuclear plants. Cost estimates for any required modifications cannot be developed until after the rule is finalized, but costs for modifications could be substantial.  See Extreme Flooding Preparedness and NRC Seismic Assessments above. 

Baffle-Former Bolt Degradation . In July 2016, Westinghouse Electric Corporation ("Westinghouse") issued a Nuclear Safety Advisory Letter (“NSAL”) 16-01 that addresses recently identified degradation of baffle-former bolts in some U.S. pressurized water reactors (“PWRs”). Baffle-former bolts help hold together a structure inside certain reactor vessels. Sequoyah Units 1 and 2, both of which are powered by PWRs, are referenced in the NSAL. Visual inspections of baffle-former bolts in Sequoyah Unit 1 during the refueling outage in the first quarter of 2017 showed no degradation of baffle-former bolts. The refueling outage of Sequoyah Unit 2 is scheduled to take place later in 2017 at which time the baffle-former bolts in that unit will be visually inspected. TVA is planning to complete ultrasonic inspections during the subsequent refueling outages at both Unit 1 and Unit 2.

Potential Issues Involving Nuclear Components. On January 10, 2017, the NRC released a list of nuclear units that are potentially impacted by AREVA components forged by Le Creusot Forge in France. Sequoyah Unit 1 and Watts Bar Unit 1 are included in the list because they received steam generator components from Le Creusot Forge. Two separate issues relating to the AREVA components were identified. One issue involves the level of carbon in some forgings, which may compromise the components’ structural integrity over time. Neither the NRC nor AREVA has found any safety concerns with the steam generator components produced by Le Creusot Forge. Additionally, Westinghouse, which supplied the components to TVA, has notified TVA that there are no known issues with the components Westinghouse received from Le Creusot Forge, and TVA is not aware of any issues with the components. TVA will participate with industry working groups investigating the forging issue. The other issue involves apparent documentation discrepancies which do not appear to have affected TVA.


48

Table of Contents                                                                                 

Watts Bar Nuclear Plant. In March 2016, the NRC issued a Chilling Effect Letter (“CEL”) to TVA regarding work environment concerns identified at Watts Bar. The NRC will conduct follow up inspections to monitor TVA's implementation of actions to resolve the work environment concerns. The NRC conducted its first follow-up inspection in October/November 2016, in which it found that Watts Bar still faces challenges in maintaining a safety conscious work environment. TVA updated the NRC on the status of corrective actions related to the work environment at Watts Bar in a public meeting on November 3, 2016.

Watts Bar Unit 2 . Watts Bar Unit 2 commenced commercial operations on October 19, 2016.  Project costs were $4.7 billion and were within the limit approved by the TVA Board in January 2016.
    
Bellefonte Nuclear Plant . On November 14, 2016, following a public auction, TVA entered into a contract to sell substantially all of its Bellefonte site to Nuclear Development, LLC for $111 million.  Nuclear Development, LLC paid TVA $22 million on November 14, 2016, and the remaining $89 million is due at closing.  Nuclear Development, LLC has up to two years to close on the property, and TVA will maintain the site until then. See Note 6 Deferred Nuclear Generation Units .

Clean Air Projects . During 2011, the TVA Board approved the addition of emission control equipment at Gallatin. TVA completed the addition of scrubbers on the four Gallatin units during 2016 and is currently installing SCR systems on these units. As of December 31, 2016, it is anticipated that the first two SCRs will be operational in the spring of 2017 and the final two will be operational in the fall of 2017. In addition, at its December 30, 2014 meeting, the TVA Board authorized the installation of SCRs and scrubbers on Units 1 and 4 at Shawnee. It is anticipated that these systems will be operational in the fall of 2017.

Coal Combustion Residuals Facilities. TVA has committed to a programmatic approach to the elimination of wet storage of coal combustion residuals ("CCR") within the TVA service area. Under this program (the “CCR Conversion Program”), TVA has committed to (1) convert all operational coal-fired plants to dry CCR storage, (2) close all wet storage facilities, and (3) meet all applicable state and federal regulations. To carry out its CCR Conversion Program, TVA is undertaking the following actions:

Dry generation and dewatering projects . Conversion of coal plant CCR wet processes to dry generation or dewatering is complete at Bull Run, and construction is underway at Kingston and Shawnee. Planning and engineering phases are currently underway at Gallatin, Cumberland, and Paradise.

Landfills . Lined and permitted dry storage facilities have been constructed and are operational at the Bull Run, Kingston, and Gallatin Fossil Plants. Planning and engineering phases are currently underway at the Cumberland, Paradise, and Shawnee Fossil Plants.

Wet CCR impoundment closures . TVA is planning to close wet CCR impoundments in accordance with federal and state requirements when (1) coal-fired plants are converted to dry CCR processes and dry storage landfills become operational or (2) plant operations cease. Closure project schedules and costs are driven by the selected closure technology (such as cap and close in place or closure by removal). TVA issued an environmental impact statement ("EIS") that addresses the closure of CCR impoundments at TVA's coal-fired plants in June 2016. The EIS was finalized in July 2016. Although the EIS was designed to be programmatic in order to address the mode of impoundment closures, it specifically addressed closure methods at 10 impoundments. TVA subsequently decided to close those impoundments, although final closure plans are still subject to approval by appropriate state regulators. Additional National Environmental Policy Act ("NEPA") analyses will be conducted as other impoundments are designated for closure. As environmental studies are performed and closure methodologies are determined, detailed project schedules and estimates will be finalized.

Groundwater monitoring . Compliance with the EPA’s CCR rule will require additional engineering and analysis as well as implementation of a comprehensive groundwater monitoring program.

The CCR Conversion Program is scheduled to be completed by 2022 with two exceptions. First, a new landfill at Shawnee will be required to accommodate the addition of air pollution controls, and the landfill is scheduled to be operational by 2020. Once the new landfill is in service, the existing bottom ash impoundment and dry stack will be closed in accordance with federal and state requirements. Second, the impoundments at Gallatin are pending additional studies to determine the final closure methodology and schedule. While plans are currently being formulated for the CCR closure methodology for Gallatin, TVA is involved in two lawsuits relating to alleged releases of waste materials from the CCR facilities at Gallatin.  In both cases, the plaintiffs are seeking injunctive relief and civil penalties.  The injunctive relief could include an order requiring TVA to relocate the CCR facilities, and the cost of doing so would be substantial.  The civil penalties, if awarded, could also be substantial.  See Note 16 Legal Proceedings Cases Involving Gallatin Fossil Plant CCR Facilities .

Through December 31, 2016 , TVA had spent approximately $1.0 billion on its CCR Conversion Program. TVA expects to spend an additional $1.2 billion on the CCR Conversion Program through 2022. Once the CCR Conversion Program is completed, TVA will continue to undertake certain CCR projects, including building new landfill sections under existing permits and closing existing sections once they reach capacity.
    
Natural Gas-Fired Units . During 2014, the TVA Board approved the construction of two natural gas-fired generation facilities. One facility, with an expected generation capacity of approximately 1,000 MW, is under construction at the Paradise

49

Table of Contents                                                                                 

site at a cost not to exceed $1.1 billion. A second facility, with an expected generation capacity of approximately 1,000 MW, is under construction at the Allen site at a cost not to exceed $975 million. Upon completion of each facility, existing coal-fired units at the site will be retired with the exception of Paradise Unit 3, which will continue to be operated on the Paradise site.

In April 2016, the Environmental Protection Agency ("EPA") issued an Administrative Order ("AO") allowing Paradise Units 1 and 2 to operate for an additional year beyond the compliance date allowed by the Mercury and Air Toxics Standards ("MATS") rule.  The extended compliance date under the AO is April 16, 2017.  The AO allows TVA to continue to operate these units, which, in their current configuration, are not capable of meeting certain requirements of the MATS rule.  The AO allows TVA to continue to operate Paradise Units 1 and 2 to maintain electric reliability pending the availability of commercial power from the natural gas-fired units currently under construction at the Paradise site without incurring penalties under the Clean Air Act ("CAA").  These units are expected to come online in the spring of 2017.  

TVA initially intended to use wastewater for the Allen facility’s cooling system but has now determined such a method would be cost prohibitive from both a capital and long-term operations and maintenance perspective. Due to the industrial nature of the wastewater, it would have required significantly more water treatment than initially anticipated. TVA evaluated several wastewater treatment alternatives and concluded the current plan to build five wells to obtain cooling water from an aquifer is the preferred method. Three of the five wells were permitted in the summer of 2016 and were installed by September 2016. The remaining two wells were permitted in September 2016. The Sierra Club challenged the issuance of the final two well permits, arguing that the Shelby County Health Department had issued the permits in violation of applicable rules. Following a hearing on November 30, 2016, the Groundwater Quality Control Board of Shelby County denied the Sierra Club’s appeal, finding that the well permits met the requirements of the applicable rules and were appropriately granted by the Health Department. The deadline for the Sierra Club to appeal this ruling is early February 2017. TVA has commenced installation of the final two wells. The units are currently expected to come online in 2018.

Renewable Energy Resources. On November 10, 2016, the River Bend Solar Energy Center located in northern Alabama began commercial operation.  TVA has a 20-year power purchase agreement signed on February 23, 2015, with NextEra Energy Resources for power generated from the facility. The River Bend Solar Energy Center has more than 300,000 solar panels with trackers that are designed to follow the sun from east to west each day to maximize energy production with a generating capacity of 75 megawatts. The power purchase agreement supports TVA’s renewable energy portfolio and is helping TVA meet its commitment to provide low-cost, carbon-free electricity.

River Management . The summer of 2016 was the hottest and driest in the Tennessee Valley since 2010 — a trend that continued into the first quarter of 2017. In the first quarter of 2017, the Tennessee Valley region experienced rainfall deficits of 12 inches in some areas, along with above average temperatures and the fifth driest runoff in TVA history. Various aspects of TVA's three-fold mission are being impacted by these weather patterns. These include maintaining minimum river flows for navigation, generating electricity, and maintaining water quality, water supply, and recreation for the Tennessee Valley; having cool water available to meet thermal compliance and enabling normal operation of TVA's nuclear and fossil-fueled plants; reducing availability of low-cost, hydroelectric generation; and oxygenation of water to help fish species remain healthy. Rainfall of 5.8 inches during December 2016 helped ease drought conditions. In spite of this increased rainfall, runoff during the first quarter of 2017 was 52 percent below normal resulting in hydroelectric generation being 48 percent below normal and 60 percent lower during the first quarter of 2017 as compared to the same period of the prior year.

Small Modular Reactors . TVA submitted an Early Site Permit Application ("ESPA") for review by the NRC in May 2016. TVA supplemented its ESPA on December 15, 2016, as outlined in its letter to the NRC dated August 11, 2016. The NRC completed its acceptance review of the application on December 30, 2016, and will begin its full detailed technical review of the application in early CY 2017. The ESPA is based on a future application for two or more small modular reactor ("SMR") units at TVA’s Clinch River site in Oak Ridge, Tennessee. TVA is considering the four SMR designs under development in the United States and will evaluate the designs and vendors for the SMR technology as they are completed. Because a design has not been selected, the ESPA seeks approval of a Plant Parameter Envelope that encompasses all four SMR designs. TVA and DOE have entered into an interagency agreement to jointly fund licensing activities for the Clinch River site with DOE reimbursement of up to 50 percent of TVA's eligible costs through 2020.

TVA is developing the Clinch River site on a schedule that supports submittal of a combined construction and operating license ("COL") application in 2019, in conjunction with supporting the NRC’s review of the ESPA. Submittal of a COL is subject to sufficient progress being made by the SMR vendor(s) with their design certification(s), and a TVA decision to select a specific SMR technology and proceed with development of a COL application in 2017.


50

Table of Contents                                                                                 

Dam Safety and Remediation Initiatives

Assurance Initiatives. TVA has an established dam safety program, which includes procedures based on the Federal Guidelines for Dam Safety, with the objective of reducing the risk of a dam safety event. The program is comprised of various engineering activities for all of TVA’s dams including safety reassessments using modern industry criteria and the new probable maximum flood and site-specific seismic load cases.    

One aspect of the guidelines is that dam structures will be periodically reassessed to assure that TVA's dams meet current design criteria. These reassessments include material sampling of the dam and foundational structures and detailed engineering analysis. TVA is currently performing reassessments on its 49 dam projects. Thirty-eight reassessments have been completed through December 31, 2016 . The remaining 11 reassessments were initiated in 2016 and are scheduled to be completed by the end of 2017.  Results of the completed reassessments identified areas for further studies at several TVA dams, including Boone and Pickwick (as discussed in more detail below). TVA has spent $64 million on dam safety assurance initiatives since 2012 and expects to spend an additional $206 million through 2021.

Boone Dam Remediation . In October 2014, a sinkhole was discovered near the base of the earthen embankment at Boone Dam, and a small amount of water and sediment was found seeping from the river bank below the dam. TVA identified underground pathways contributing to the seepage and prepared a plan to repair the dam, which consists of the construction of a composite seepage barrier in the dam’s earthen embankment. An environmental assessment review through TVA's NEPA process was completed on January 7, 2016, and a finding of no significant impact was published. TVA completed the first part (low mobility grouting) of its test grouting program on the embankment in September 2016 and is currently evaluating the effectiveness of that grouting phase.  The second phase of the grouting program (high mobility grouting) is underway, and it is anticipated those efforts will be completed in late 2017.

TVA continues to perform investigative drilling, grouting, and other activities in support of the seepage barrier design.  Based on preliminary findings, the design plans are being modified. The cost and duration for the overall remediation of Boone Dam will be determined upon completion of design during the summer of 2017 with construction plans being finalized thereafter. It is anticipated that construction plans will be completed by December 2017. These plans will not include any future repairs or projects that may be required as a result of the change in water flow once the composite seepage barrier is complete. The cost and duration of additional work efforts will be determined as design and construction plans are finalized.  Benchmarking durations and costs of similar activities at other facilities to complete composite walls have ranged from $200 million to $300 million with a range of five to seven years to complete. TVA will continue working with the community to help mitigate local impacts of the extended drawdown.

Pickwick Landing Dam South Embankment Remediation. Reassessments of Pickwick found low safety factors for post-earthquake stability indicating that the dam is at significant risk for slope stability failure following a seismic event in portions of the south embankment. Slope stability failure could lead to a breach of the south embankment and loss of the reservoir, resulting in loss of life and damage to property downstream, disruption to navigation, and loss of generation and recreation.

                On September 30, 2016, TVA issued a final environmental assessment and finding of no significant impact for its proposed upgrades to the south embankment.  Upon completion of the preliminary engineering study, TVA determined that remediation of the south embankment should be performed by constructing berms on the upstream and downstream slopes. The design phase of the project began during the first quarter of 2017 with the construction phase scheduled to begin in the fall of 2017.  The project is currently estimated to be completed in two years. However, the project could take longer than two years depending on the sequencing and loading of the dam.  The total project cost is estimated to be approximately $100 million.

Major Capital Projects

The table below summarizes major projects of at least $1.0 billion, as approved by the TVA Board, which support TVA's strategic imperatives related to having a diversified, cleaner portfolio, providing electricity at the lowest feasible rate, responding to changing regulatory requirements including environmental regulations, and meeting operational challenges related to generation reliability. See Liquidity and Capital Resources and Key Initiatives and Challenge s.
Summary Table of Major Projects
Projects
 
Estimated Project Cost
(in billions)
 
Estimated
 In-Service Year
Capacity Expansion Projects
 
 
 
 
Paradise combined cycle plant
 
$
1.0

 
2017
Allen combined cycle plant
 
1.0

 
2018
Environmental
 
 
 
 
Gallatin clean air controls
 
1.0

 
2018


51

Table of Contents                                                                                 

Regulatory Compliance

Environmental Mitigation. Of the $290 million that TVA is required to spend on environmental mitigation projects under the Environmental Agreements, TVA has already spent approximately $248 million in implementing energy efficiency, electric vehicle, and renewable energy projects. These expenditures on environmental mitigation projects are in addition to the decisions TVA made under the Environmental Agreements to control, convert, or retire additional coal-fired units. See Part I, Business — Power Supply and Load Management Resources Coal-Fired of the Annual Report.

Transmission Issues. TVA anticipates expenditures related to transmission facilities to increase as a result of both new and evolving regulatory requirements. The North American Electric Reliability Corporation ("NERC") approved revisions to the Transmission Planning ("TPL") Reliability Standards in 2013. TVA has spent $23 million since the approval of the standard through December 31, 2016 , on existing transmission facilities and anticipates spending an additional $37 million through 2018 to ensure compliance with the 2013 revision of the TPL standards. Total costs of compliance with the standard, including those beyond 2018, are estimated to be approximately $650 million.

Steam-Electric Effluent Guidelines . On November 3, 2015, the EPA published a final rule revising the existing steam electric effluent limitation guidelines ("ELGs") .  The ELGs update the existing technology-based water discharge limitations for power plants.  Compliance with new requirements is required in the 2018-2023 timeframe and will necessitate major upgrades to wastewater treatment systems at all coal-fired plants. Dry fly ash handling is mandated by the rule. The rule also requires either dry bottom ash handling systems or “no discharge” recycle of bottom ash transport waters, and new technology-based limits on flue gas desulfurization (scrubber) wastewater require primary physical/chemical treatment and secondary biological treatment to meet extremely low limits for arsenic, mercury, and selenium.

TVA currently has four plants with wet scrubbers that will have to comply with the scrubber-related limits, the largest being Cumberland Fossil Plant ("Cumberland") . TVA is working with the State of Tennessee and the EPA in an effort to address compliance with the ELGs at Cumberland given its unique “once-through” scrubber design. Compliance with the rule at Cumberland without modification to address the unique design could cause TVA to incur disproportionately high costs at Cumberland or experience other operational outcomes which TVA cannot predict at this time. 

Ratemaking

At its August 25, 2016 meeting, the TVA Board approved a base rate adjustment which took effect on October 1, 2016. The base rate adjustment is expected to contribute approximately $200 million to fiscal year 2017 revenues.

Pension

During 2016, the Tennessee Valley Authority Retirement System (“TVARS”) Board of Directors and the TVA Board approved amendments to TVA’s pension plan and the 401(k) plan.  These amendments, which became effective on October 1, 2016, changed the future retirement benefits for employees and retirees and also changed the annual minimum contribution required by TVA to the pension plan.   The amendments adopted reduced the benefit obligation by $960 million and committed TVA to annual contributions of the greater of the minimum contribution calculated by TVARS's actuary according to the TVARS Rules and Regulations or $300 million for a period of 20 years or until the plan has reached a fully funded status if sooner than 20 years. See Note 15 .

Safeguarding Assets     

Physical Security Non-Nuclear Asset Protection.   TVA utilizes a variety of security technologies, security awareness activities, and security personnel to prevent sabotage, vandalism, and thefts.  Any of these activities could negatively impact the ability of TVA to generate, transport, and deliver power to its customers. TVA's Police and Emergency Management are active participants with numerous professional and peer physical security organizations in both the electric industry and law enforcement communities.

Physical attacks on transmission facilities across the country have heightened awareness of the need to physically protect facilities. TVA is working with the Department of Homeland Security ("DHS") , the Federal Energy Regulatory Commission ("FERC") , NERC, the SERC Reliability Corporation, the North American Transmission Forum, and other utilities to implement industry approved recommendations and standards.

Nuclear Security . Nuclear security is carried out in accordance with federal regulations as set forth by the NRC. These regulations are designed for the protection of TVA's nuclear power plants, the public, and employees from the threat of radiological sabotage and other nuclear-related terrorist threats. TVA has security forces to guard against such threats.

Cyber Security. TVA operates in a highly regulated environment. TVA's cyber security program aligns or complies with the Federal Information Security Management Act, the NERC Critical Infrastructure Protection requirements, and the NRC requirements for cyber security, as well as industry best practices. As part of the U.S. government, TVA coordinates with and works closely with the DHS and the United States Computer Emergency Readiness Team ("US-CERT") . US-CERT functions as

52

Table of Contents                                                                                 

a liaison between the DHS and the public and private sectors to coordinate responses to security threats from the Internet. TVA is also participating in studies funded through the DOE to identify, design, and test new solutions for protecting critical infrastructure from cyber attacks.

Although TVA has continued to experience increased cybersecurity threats, none of the attacks to date have impacted TVA's ability to operate as planned or compromised data which could involve TVA in legal proceedings. See Item 1A, Risk Factors — Operational Risks TVA's facilities and information infrastructure may not operate as planned due to physical and cyber threats to TVA's security of the Annual Report.

Transmission Assets . In addition to physical and cybersecurity attacks, TVA’s transmission assets are vulnerable to various types of electrically charged energy disruptions such as those from geomagnetic disturbances ("GMD") and electromagnetic pulses ("EMP"). Although the effects of GMD and EMP are dissimilar, they are often considered together. On September 22, 2016, FERC approved the Phase 2 NERC Standard TPL-007 to address GMD events. TVA has already met many of the requirements of the new standard with completion of a model of the 500 kV grid and evaluation of the effects of solar storms ranging from NERC’s reference case to possible extreme levels. Only a few items of equipment would exceed threshold levels even for the extreme cases and no damage would be expected. The most serious threats from EMP are those caused by high-altitude nuclear explosions. Like others in the industry, TVA is coordinating with federal and state authorities, NERC, and other grid owners and operators to address this emerging concern.

Environmental Matters

TVA’s activities, particularly its power generation activities, are subject to comprehensive regulation under environmental laws and regulations relating to air pollution, water pollution, and management and disposal of solid and hazardous wastes, among other issues.

Clean Air Act

National Ambient Air Quality Standards. On March 2, 2015, the United States District Court for the Northern District of California approved a consent decree between the EPA and certain environmental petitioners in Sierra Club v. McCarthy . The consent decree set a schedule for the EPA to complete nationwide area designations with respect to the 2010 1-Hour sulfur dioxide ("SO 2 ") NAAQS based on monitored air quality levels and SO 2 source emission rates and amounts. Air quality modeling was required in 2016 to determine designation of areas around five TVA coal-fired plants. No areas around any TVA generating units are expected to be designated non-attainment. Lower SO 2 permit limits well within the capability of existing control equipment are in place for Gallatin and are expected to be in place for Paradise.

Petition to Expand the Ozone Transport Region.  On December 9, 2013, eight of the twelve states that make up the Ozone Transport Region ("OTR") submitted a petition, pursuant to section 176A(a) of the Clean Air Act ("CAA") , requesting the EPA to add nine states, including Kentucky and Tennessee, to the OTR.  The EPA failed to act on the petition within the 180-day period provided under the CAA. On October 6, 2016, six of the eight states filing the petition sued the EPA in the U.S. District Court for the Southern District of New York, asking the court to require the EPA to act on the petition by a date certain.  In response to this lawsuit, the EPA signed, on January 12, 2017, a notice proposing to deny the petition on the basis that the CAA provides other options, such as the use of the “good neighbor provision” in Section 110, and Section 126, to address the impact of interstate air pollution.  The EPA also states that its September 2016 updated Cross State Air Pollution Rule is a significant step to control states’ emission reduction obligations under Section 110 to meet the 2008 ozone NAAQS.  The comment period on this proposal closes 30 days after publication of the notice in the Federal Register.  The EPA has also proposed to enter into a consent decree with the plaintiffs requiring the agency to finalize its action on the petition no later than October 27, 2017.

Cleanup of Solid and Hazardous Wastes

Coal Combustion Residuals. On December 16, 2016, President Obama signed into law the Water Infrastructure Improvements for the Nation Act ("WIIN Act"), which, among other elements, includes amendments to the Solid Waste Disposal Act to provide a path to CCR implementation through state or federal-based permitting as an alternative to the current practice of self-implementation and enforcement through citizen suits in federal courts.


53

Table of Contents                                                                                 

Estimated Required Environmental Expenditures

The following table contains information about TVA’s current estimates on projects related to environmental laws and regulations.
Air, Water, and Waste Quality Estimated Potential Environmental Expenditures (1)
At December 31, 2016
(in millions)

 
Estimated Timetable
 
Total Estimated Expenditures
 
 
 
 
Coal combustion residual conversion program (2)
2017-2022
 
$
1,200

Proposed clean air control projects (3)
2017-2021
 
$
335

Clean Water Act requirements (4)
2017-2023
 
$
400

Notes
(1) These estimates are subject to change as additional information becomes available and as regulations change.
(2)  Includes costs associated with pond closures, conversion of wet to dry handling, and landfill activities. In April 2015, the EPA finalized rules related to CCRs. TVA is continuing to evaluate the rules and their impact on its operations, including the cost and timing estimates of related projects. See Key Initiatives and Challenges Coal Combustion Residual Facilities .
(3)  Includes air quality projects that TVA is currently planning to undertake to comply with existing and proposed air quality regulations, but does not include any
projects that may be required to comply with potential GHG regulations or transmission upgrades.
(4)  Includes projects that TVA is currently planning to comply with revised rules under the Clean Water Act (i.e., Section 316(b) and effluent limitation guidelines for
steam electric power plants).

Legal Proceedings

From time to time, TVA is party to or otherwise involved in lawsuits, claims, proceedings, investigations, and other legal matters ("Legal Proceedings") that have arisen in the ordinary course of conducting its activities, as a result of catastrophic events or otherwise. TVA had accrued approximately $ 51 million with respect to Legal Proceedings as of December 31, 2016 . No assurance can be given that TVA will not be subject to significant additional claims and liabilities. If actual liabilities significantly exceed the estimates made, TVA's results of operations, liquidity, and financial condition could be materially adversely affected.

For a discussion of certain current material Legal Proceedings, see Note 16 Legal Proceedings , which discussion is incorporated into this Part I, Item 2, Management's Discussion and Analysis of Financial Condition and Results of Operations .

Off-Balance Sheet Arrangements
    
At December 31, 2016 , TVA had no off-balance sheet arrangements.

Critical Accounting Policies and Estimates

The preparation of financial statements requires TVA to estimate the effects of various matters that are inherently uncertain as of the date of the financial statements. Although the financial statements are prepared in conformity with accounting principles generally accepted in the U.S., TVA is required to make estimates and assumptions that affect the reported amounts of assets and liabilities, the disclosure of contingent assets and liabilities, and the amounts of revenues and expenses reported during the reporting period. Each of these estimates varies in regard to the level of judgment involved and its potential impact on TVA's financial results. Estimates are deemed critical either when a different estimate could have reasonably been used, or where changes in the estimate are reasonably likely to occur from period to period, and such use or change would materially impact TVA's financial condition, results of operations, or cash flows. TVA's critical accounting policies are discussed in Item 7, Management's Discussion and Analysis of Financial Condition and Results of Operations — Critical Accounting Policies and Estimates and Note 1 of the Notes to Consolidated Financial Statements in the Annual Report.

New Accounting Standards and Interpretations

For a discussion of new accounting standards and interpretations, see Note 2 , which discussion is incorporated into this Part I, Item 2, Management’s Discussion and Analysis of Financial Condition and Results of Operations.

Corporate Governance

The terms of Joe H. Ritch, C. Peter Mahurin, and Michael R. McWherter as members of the TVA Board ended on January 3, 2017.

On January 9, 2017, Michael Balduzzi, Senior Vice President, Nuclear Operations, was named as TVA’s Senior Vice President and Chief Nuclear Officer (“CNO”). Mr. Balduzzi’s appointment became effective January 23, 2017. Mr. Balduzzi reports to Joseph P. Grimes, Jr., TVA’s Executive President, Generation, who was serving as CNO prior to Mr. Balduzzi’s appointment.


54

Table of Contents                                                                                 

Effective January 13, 2017, V. Lynn Evans was selected as the Chair of the TVA Board through May 18, 2017.

Legislative and Regulatory Matters

The WIIN Act amended the TVA Act to prohibit the TVA Board from ordering the removal of existing floating homes located on waters within TVA’s jurisdiction if the homes meet certain criteria. The amendment does allow the TVA Board to bar future construction of floating homes.    

TVA continues to monitor how regulatory agencies are interpreting and implementing the provisions of the Dodd-Frank Wall Street Reform and Consumer Protection Act, which was enacted in July 2010.  As a result of this act and its implementing regulations, TVA has become subject to recordkeeping, reporting, and reconciliation requirements related to its derivative transactions. In addition, depending on how regulatory agencies interpret and implement the provisions of this act, TVA’s hedging costs may increase, and TVA may have to post additional collateral and margin in connection with its derivative transactions.

TVA does not engage, and does not control any entity that is engaged, in any activity listed under Section 13(r) of the Exchange Act, which requires certain issuers to disclose certain activities relating to Iran involving the issuer and its affiliates.  Based on information supplied by each such person, none of TVA's directors and executive officers are involved in any such activities.  While TVA is an agency and instrumentality of the United States of America, TVA does not believe its disclosure obligations, if any, under Section 13(r), extend to the activities of any other departments, divisions, or agencies of the United States.

ITEM 3.  QUANTITATIVE AND QUALITATIVE DISCLOSURES ABOUT MARKET RISK

There are no material changes related to market risks disclosed under Item 7, Management's Discussion and Analysis of Financial Condition and Results of Operations — Risk Management Activities in the Annual Report.  See Note 12 for additional information regarding TVA's derivative transactions and risk management activities.

55

Table of Contents                                                                                 


ITEM 4.  CONTROLS AND PROCEDURES

Disclosure Controls and Procedures

TVA’s management, including the President and Chief Executive Officer, the Executive Vice President and Chief Financial Officer, and members of the Disclosure Control Committee, including the Vice President and Controller (Principal Accounting Officer), evaluated the effectiveness of TVA’s disclosure controls and procedures (as defined in Rule 13a-15(e) under the Securities Exchange Act of 1934 (the "Exchange Act") ) as of December 31, 2016 .  Based on this evaluation, TVA’s management, including the President and Chief Executive Officer, the Executive Vice President and Chief Financial Officer, and members of the Disclosure Control Committee, including the Vice President and Controller (Principal Accounting Officer), concluded that TVA’s disclosure controls and procedures were effective as of December 31, 2016 , to ensure that information required to be disclosed by TVA in reports that it files or submits under the Exchange Act, is recorded, processed, summarized, and reported, within the time periods specified in the Securities and Exchange Commission’s rules and forms, and include controls and procedures designed to ensure that information required to be disclosed by TVA in such reports is accumulated and communicated to TVA’s management, including the President and Chief Executive Officer, the Executive Vice President and Chief Financial Officer, and members of the Disclosure Control Committee, including the Vice President and Controller (Principal Accounting Officer), as appropriate, to allow timely decisions regarding required disclosure.

Changes in Internal Control over Financial Reporting

During the quarter ended December 31, 2016 , there were no changes in TVA's internal control over financial reporting that materially affected, or are reasonably likely to materially affect, TVA's internal control over financial reporting.


56

Table of Contents                                                                                 

PART II - OTHER INFORMATION

ITEM 1.  LEGAL PROCEEDINGS

From time to time, TVA is party to or otherwise involved in lawsuits, claims, proceedings, investigations, and other legal matters ("Legal Proceedings") that have arisen in the ordinary course of conducting its activities, as a result of catastrophic events or otherwise.  While the outcome of the Legal Proceedings to which TVA is a party cannot be predicted with certainty, any adverse outcome to a Legal Proceeding involving TVA may have a material adverse effect on TVA’s financial condition, results of operations, and cash flows.

For a discussion of certain current material Legal Proceedings, see Note 16 Legal Proceedings , which discussion is incorporated by reference into this Part II, Item 1, Legal Proceedings.

ITEM 1A.  RISK FACTORS

There are no material changes related to risk factors from the risk factors disclosed in Item 1A, Risk Factors in the Annual Report.


57

Table of Contents                                                                                 

ITEM 6.  EXHIBITS

Exhibit  No. 
Description 
 
 
3.1
Tennessee Valley Authority Act of 1933, as amended, 16 U.S.C. §§ 831-831ee
 
 
10.1
December 2019 Maturity Community Bank Credit Agreement with SunTrust Bank as Administrative Agent and a Lender, Branch Banking and Trust Company as Letter of Credit Issuer and a Lender, First National Bank, First Tennessee Bank National Association, HomeTrust Bank, Pinnacle Bank, Regions Bank, Trustmark National Bank, and United Community Bank (Incorporated by reference to Exhibit 10.1 to TVA's Current Report on Form 8-K filed on December 15, 2016, File No. 000-52313)
 
 
31.1
Rule 13a-14(a)/15d-14(a) Certification Executed by the Chief Executive Officer
 
 
31.2
Rule 13a-14(a)/15d-14(a) Certification Executed by the Chief Financial Officer
 
 
32.1
Section 1350 Certification Executed by the Chief Executive Officer
 
 
32.2
Section 1350 Certification Executed by the Chief Financial Officer
 
 
101.INS
TVA XBRL Instance Document
 
 
101.SCH
TVA XBRL Taxonomy Extension Schema
 
 
101.CAL
TVA XBRL Taxonomy Extension Calculation Linkbase
 
 
101.DEF
TVA XBRL Taxonomy Extension Definition Linkbase
 
 
101.LAB
TVA XBRL Taxonomy Extension Label Linkbase
 
 
101.PRE
TVA XBRL Taxonomy Extension Presentation Linkbase
 


58

Table of Contents                                                                                 

SIGNATURES

Pursuant to the requirements of Section 13, 15(d), or 37 of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized.

Date:
January 30, 2017
 
TENNESSEE VALLEY AUTHORITY                           
 
 
 
(Registrant)
 
 
 
 
 
 
 
 
 
 
By:
_/s/ William D. Johnson __________
 
 
 
William D. Johnson
 
 
 
President and Chief Executive Officer
(Principal Executive Officer) 
 
 
 
By:
_ /s/ John M. Thomas, III__________
 
 
 
John M. Thomas, III
 
 
 
Executive Vice President and Chief Financial Officer
(Principal Financial Officer)


59

Table of Contents                                                                                 

EXHIBIT INDEX

Exhibit  No. 
Description 
 
 
3.1
Tennessee Valley Authority Act of 1933, as amended, 16 U.S.C. §§ 831-831ee
 
 
10.1
December 2019 Maturity Community Bank Credit Agreement with SunTrust Bank as Administrative Agent and a Lender, Branch Banking and Trust Company as Letter of Credit Issuer and a Lender, First National Bank, First Tennessee Bank National Association, HomeTrust Bank, Pinnacle Bank, Regions Bank, Trustmark National Bank, and United Community Bank (Incorporated by reference to Exhibit 10.1 to TVA's Current Report on Form 8-K filed on December 15, 2016, File No. 000-52313)
 
 
31.1
Rule 13a-14(a)/15d-14(a) Certification Executed by the Chief Executive Officer
 
 
31.2
Rule 13a-14(a)/15d-14(a) Certification Executed by the Chief Financial Officer
 
 
32.1
Section 1350 Certification Executed by the Chief Executive Officer
 
 
32.2
Section 1350 Certification Executed by the Chief Financial Officer
 
 
101.INS
TVA XBRL Instance Document
 
 
101.SCH
TVA XBRL Taxonomy Extension Schema
 
 
101.CAL
TVA XBRL Taxonomy Extension Calculation Linkbase
 
 
101.DEF
TVA XBRL Taxonomy Extension Definition Linkbase
 
 
101.LAB
TVA XBRL Taxonomy Extension Label Linkbase
 
 
101.PRE
TVA XBRL Taxonomy Extension Presentation Linkbase


60


EXHIBIT 3.1
                                        
TENNESSEE VALLEY AUTHORITY ACT

AN ACT

To improve the navigability and to provide for the flood control of the Tennessee River; to provide for reforestation and the proper use of marginal lands in the Tennessee Valley; to provide for the agricultural and industrial development of said valley; to provide for the national defense by the creation of a corporation for the operation of Government properties at and near Muscle Shoals in the State of Alabama, and for other purposes.

Be it enacted by the Senate and House of Representatives of the United States of America in Congress assembled, That for the purpose of maintaining and operating the properties now owned by the United States in the vicinity of Muscle Shoals, Alabama, in the interest of the national defense and for agricultural and industrial development, and to improve navigation in the Tennessee River and to control the destructive flood water in the Tennessee River and Mississippi River Basins, there is hereby created a body corporate by the name of the “Tennessee Valley Authority” (hereinafter referred to as the “Corporation”). The Board of Directors first appointed shall be deemed the incorporator, and the incorporation shall be held to have been effected from the date of the first meeting of the Board. This Act may be cited as the “Tennessee Valley Authority Act of 1933.”
Sec. 2. MEMBERSHIP, OPERATION, AND DUTIES OF THE BOARD OF
DIRECTORS.
(a) MEMBERSHIP.--
(1) APPOINTMENT.--The Board of Directors of the Corporation (referred to in this Act as the “Board”) shall be composed of 9 members appointed by the President by and with the advice and consent of the Senate, at least 7 of whom shall be a legal resident of the service area of the Corporation.
(2) CHAIRMAN.--The members of the Board shall select 1 of the members to act as chairman of the Board.
(b) QUALIFICATIONS.--To be eligible to be appointed as a member of the Board, an individual--
(1) shall be a citizen of the United States;
(2) shall have management expertise relative to a large for-profit or nonprofit corporate, government, or academic structure;
(3) shall not be an employee of the Corporation;
(4) shall make full disclosure to Congress of any investment or other financial interest that the individual holds in the energy industry; and
(5) shall affirm support for the objectives and missions, of the Corporation, including being a national leader in technological innovation, low-cost power, and environmental stewardship.
(c) RECOMMENDATIONS.--In appointing members of the Board, the President shall--
(1) consider recommendations from such public officials as--
(A) the Governors of States in the service area;
(B) individual citizens;

1




(C) business, industrial, labor, electric power distribution, environmental, civic, and service organizations; and
(D) the congressional delegations of the States in the service area; and
(2) seek qualified members from among persons who reflect the diversity, including the geographical diversity, and needs of the service area of the Corporation.
(d) TERMS.--
(1) IN GENERAL.--A member of the Board shall serve a term of 5 years. A member of the Board whose term has expired may continue to serve after the member’s term has expired until the date on which a successor takes office, except that the member shall not serve beyond the end of the session of Congress in which the term of the member expires.
(2) VACANCIES.--A member appointed to fill a vacancy on the Board occurring before the expiration of the term for which the predecessor of the member was appointed shall be appointed for the remainder of that term.
(e) QUORUM.--
(1) IN GENERAL.--Five of the members of the Board shall constitute a quorum for the transaction of business.
(2) VACANCIES.--A vacancy on the Board shall not impair the power of the Board to act.
(f) COMPENSATION.--
(1) IN GENERAL.--A member of the Board shall be entitled to receive--
(A) a stipend of--
(i) $45,000 per year; or
(ii)(I) in the case of the chairman of any committee of the Board created by the Board, $46,000 per year; or
(II) in the case of the chairman of the Board, $50,000 per year; and
(B) travel expenses, including per diem in lieu of subsistence, in the same manner as persons employed intermittently in Government service under section 5703 of title 5, United States Code.
(2) ADJUSTMENTS IN STIPENDS.--The amount of the stipends under paragraph (1)(A) shall be adjusted by the same percentage, at the same time and manner, and subject to the same limitations as are applicable to adjustments under section 5318 of title 5, United States Code.
(g) DUTIES.--
(1) IN GENERAL.--The Board shall--
(A) establish the broad goals, objectives, and policies of the Corporation that are appropriate to carry out this Act;
(B) develop long-range plans to guide the Corporation in achieving the goals, objectives, and policies of the Corporation and provide assistance to the chief executive officer to achieve those goals, objectives, and policies;
(C) ensure that those goals, objectives, and policies are achieved;
(D) approve an annual budget for the Corporation;
(E) adopt and submit to Congress a conflict-of-interest policy applicable to members of the Board and employees of the Corporation;
(F) establish a compensation plan for employees of the Corporation in accordance with subsection (i);

2




(G) approve all compensation (including salary or any other pay, bonuses, benefits, incentives, and any other form of remuneration) of all managers and technical personnel that report directly to the chief executive officer (including any adjustment to compensation);
(H) ensure that all activities of the Corporation are carried out in compliance with applicable law;
(I) create an audit committee, composed solely of Board members independent of the management of the Corporation, which shall--
(i) in consultation with the inspector general of the Corporation, recommend to the Board an external auditor;
(ii) receive and review reports from the external auditor of the Corporation and inspector general of the Corporation; and
(iii) make such recommendations to the Board as the audit committee considers necessary;
(J) create such other committees of Board members as the Board considers to be appropriate;
(K) conduct such public hearings as it deems appropriate on issues that could have a substantial effect on--
(i) the electric ratepayers in the service area; or
(ii) the economic, environmental, social, or physical well-being of the people of the service area;
(L) establish the electricity rates charged by the Corporation; and
(M) engage the services of an external auditor for the Corporation.
(2) MEETINGS.--The Board shall meet at least 4 times each year.
(h) CHIEF EXECUTIVE OFFICER.--
(1) APPOINTMENT.--The Board shall appoint a person to serve as chief executive officer of the Corporation.
(2) QUALIFICATIONS.--
(A) IN GENERAL.--To serve as chief executive officer of the Corporation, a person--
(i) shall have senior executive-level management experience in large, complex organizations;
(ii) shall not be a current member of the Board or have served as a member of the Board within 2 years before being appointed chief executive officer; and
(III) shall comply with the conflict-of-interest policy adopted by the Board.
(B) EXPERTISE.--In appointing a chief executive officer, the Board shall give particular consideration to appointing an individual with expertise in the electric industry and with strong financial skills.
(3) TENURE.--The chief executive officer shall serve at the pleasure of the Board.
(i) COMPENSATION PLAN.--
(1) IN GENERAL.--The Board shall approve a compensation plan that specifies all compensation (including salary or any other pay, bonuses, benefits, incentives, and any other form of remuneration) for the chief executive officer and employees of the Corporation.

3




(2) ANNUAL SURVEY.--The compensation plan shall be based on an annual survey of the prevailing compensation for similar positions in private industry, including engineering and electric utility companies, publicly owned electric utilities, and Federal, State, and local governments.
(3) CONSIDERATIONS.--The compensation plan shall provide that education, experience, level of responsibility, geographic differences, and retention and recruitment needs will be taken into account in determining compensation of employees.
(4) POSITIONS AT OR BELOW LEVEL IV.--The chief executive officer shall determine the salary and benefits of employees whose annual salary is not greater than the annual rate payable for positions at level IV of the Executive Schedule under section 5315 of title 5, United States Code.
(5) POSITIONS ABOVE LEVEL IV.--On the recommendation of the chief executive officer, the Board shall approve the salaries of employees whose annual salaries would be in excess of the annual rate payable for positions at level IV of the Executive Schedule under section 5315 of title 5, United States Code.
Sec. 3.
(a) APPOINTMENT BY THE CHIEF EXECUTIVE OFFICER.--The chief executive officer shall appoint, with the advice and consent of the Board, and without regard to the provisions of civil service laws applicable to officers and employees of the United States, such managers, assistant managers, officers, employees, attorneys, and agents, as are necessary for the transaction of the business of the Corporation.
(b) WAGE RATES.--All contracts to which the Corporation is a party and which require the employment of laborers and mechanics in the construction, alteration, maintenance, or repair of buildings, dams, locks or other projects shall contain a provision that not less than the prevailing rate of wages for work of a similar nature prevailing in the vicinity shall be paid to such laborers or mechanics.
In the event any dispute arises as to what are the prevailing rates of wages, the question shall be referred to the Secretary of Labor for determination, and his decision shall be final. In the determination of such prevailing rate or rates, due regard shall be given to those rates which have been secured through collective agreement by representatives of employers and employees.
Where such work as is described in the two preceding paragraphs is done directly by the Corporation the prevailing rate of wages shall be paid in the same manner as though such work had been let by contract.
Insofar as applicable, the benefits of the Act entitled “An Act to provide compensation for employees of the United States suffering injuries while in the performance of their duties, and for other purposes,” approved September 7, 1916 as amended, shall extend to persons given employment under the provisions of this Act.
Sec. 4. Except as otherwise specifically provided in this Act, the Corporation—
(a)     Shall have succession in its corporate name.
(b)     May sue and be sued in its corporate name.
(c)     May adopt and use a corporate seal, which shall be judicially noticed.
(d)     May make contracts, as herein authorized.
(e)     May adopt, amend, and repeal bylaws.
(f)     May purchase or lease and hold such real and personal property as it deems necessary or convenient in the transaction of its business, and may dispose of any such personal property held by it.

4



The Board shall select a treasurer and as many assistant treasurers as it deems proper: Provided , That any member of said Board may be removed from office at any time by a concurrent resolution of the Senate and the House of Representatives.
(g) Shall have such powers as may be necessary or appropriate for the exercise of the powers herein specifically conferred upon the Corporation.
(h) Shall have power in the name of the United States of America to exercise the right of eminent domain, and in the purchase of any real estate or the acquisition of real estate by condemnation proceedings, the title to such real estate shall be taken in the name of the United States of America, and thereupon all such real estate shall be entrusted to the Corporation as the agent of the United States to accomplish the purposes of this Act.
(i) Shall have power to acquire real estate for the construction of dams, reservoirs, transmission lines, power houses, and other structures, and navigation projects at any point along the Tennessee River, or any of its tributaries, and in the event that the owner or owners of such property shall fail and refuse to sell to the Corporation at a price deemed fair and reasonable by the Board, then the Corporation may proceed to exercise the right of eminent domain, and to condemn all property that it deems necessary for carrying out the purposes of this Act, and all such condemnation proceedings shall be had pursuant to the provisions and requirements hereinafter specified, with reference to any and all condemnation proceedings: Provided , That nothing contained herein or elsewhere in this Act shall be construed to deprive the Corporation of the rights conferred by the Act of February 26, 1931 (46 Stat. 1422, ch. 307, secs. 1 to 5, inclusive), as now compiled in section 258a to 258e, inclusive, of Title 40 of the United States Code.
(j) Shall have power to construct such dams, and reservoirs, in the Tennessee River and its tributaries, as in conjunction with Wilson Dam, and Norris, Wheeler, and Pickwick Landing Dams, now under construction, will provide a nine-foot channel in the said river and maintain a water supply for the same, from Knoxville to its mouth, and will best serve to promote navigation on the Tennessee River and its tributaries and control destructive flood waters in the Tennessee and Mississippi River drainage basins; and shall have power to acquire or construct power houses, power structures, transmission lines, navigation projects, and incidental works in the Tennessee River and its tributaries, and to unite the various power installations into one or more systems by transmission lines. The directors of the Authority are hereby directed to report to Congress their recommendations not later than April 1, 1936, for the unified development of the Tennessee River system.
(k) Shall have power in the name of the United States—
( a ) to convey by deed, lease, or otherwise, any real property in the possession of or under the control of the Corporation to any person or persons, for the purpose of recreation or use as a summer residence, or for the operation on such premises of pleasure resorts for boating, fishing, bathing, or any similar purpose;
( b ) to convey by deed, lease, or otherwise, the possession and control of any such real property to any corporation, partnership, person, or persons for the purpose of erecting thereon docks and buildings for shipping purposes or the manufacture or storage thereon of products for the purpose of trading or shipping in transportation: Provided , That no transfer authorized herein in (b) shall be made without the approval of Congress: And provided further , That said Corporation, without further action of Congress, shall have power to convey by deed, lease, or otherwise, to the Ingalls Shipbuilding Corporation, a tract or tracts of land at or near Decatur, Alabama; and to the Commercial Barge Lines, Inc., a tract or tracts of land at or near Guntersville, Alabama;

5




( c ) to transfer any part of the possession and control of the real estate now in possession of and under the control of said Corporation to any other department, agency, or instrumentality of the United States: Provided , however, That no land shall be conveyed, leased, or transferred, upon which there is located any permanent dam, hydroelectric power plant, or munitions plant heretofore or hereafter built by or for the United States or for the Authority, except that this prohibition shall not apply to the transfer of Nitrate Plant Numbered 1, at Muscle Shoals, Alabama, or to Waco Quarry: And provided further , That no transfer authorized herein in (a) or (c), except leases for terms of less than twenty years, shall be made without the approval of the President of the United States, if the property to be conveyed exceeds $500 in value; and
( d ) to convey by warranty deed, or otherwise, lands, easements, and rights-of-way to States, counties, municipalities, school districts, railroad companies, telephone, telegraph, water, and power companies, where any such conveyance is necessary in order to replace any such lands, easements, or rights-of-way to be flooded or destroyed as the result of the construction of any dam or reservoir now under construction by the Corporation, or subsequently authorized by Congress, and easements and rights-of-way upon which are located transmission or distribution lines. The Corporation shall have power to convey or lease Nitrate Plant Numbered 1, at Muscle Shoals, Alabama, and Waco Quarry, with the approval of the War Department 1 and the President.
(l) Shall have power to advise and cooperate in the readjustment of the population displaced by the construction of dams, the acquisition of reservoir areas, the protection of watersheds, the acquisition of rights-of-way, and other necessary acquisitions of land, in order to effectuate the purposes of the Act; and may cooperate with Federal, State, and local agencies to that end.
Sec. 4A. LAW ENFORCEMENT.
(a) DESIGNATION OF LAW ENFORCEMENT AGENTS.--The Board may designate employees of the Corporation to act as law enforcement agents in the area of jurisdiction described in subsection (c).
(b) DUTIES AND POWERS.--
(1) DUTIES.--A law enforcement agent designated under subsection (a) shall maintain law and order and protect persons and property in the area of jurisdiction described in subsection (c) and protect property and officials and employees of the Corporation outside that area.
(2) POWERS.--In the performance of duties described in paragraph (1), a law enforcement agent designated under subsection (a) may--
(A) make arrests without warrant for any offense against the United States committed in the agent's presence, or for any felony cognizable under the laws of the United States if the agent has probable cause to believe that the person to be arrested has committed or is committing such a felony;
(B) execute any warrant or other process issued by a court or officer of competent jurisdiction for the enforcement of any Federal law or regulation issued pursuant to law in connection









__________________________
1 The Department of War was designated the Department of the Army and the title of Secretary of Was was changed to Secretary of the Army by the Act of July 26, 1947, 61 Stat. 501.

6



with the investigation of an offense described in subparagraph (A);
(C) conduct an investigation of an offense described in subparagraph (A) in the absence of investigation of the offense by any Federal law enforcement agency having investigative jurisdiction over the offense or with the concurrence of that agency; and
(D) carry firearms in carrying out any activity described in subparagraph (A), (B), or (C).
(c) AREA OF JURISDICTION.--A law enforcement agent designated under subsection (a) shall be authorized to exercise the law enforcement duties and powers described in subsection (b)--
(1) on any lands or facilities owned or leased by the Corporation or within such adjoining areas in the vicinities of such lands or facilities as may be determined by the Board under subsection (e); and
(2) on other lands or facilities--
(A) when the person to be arrested is in the process of fleeing from such lands, facilities, or adjoining areas to avoid arrest;
(B) in conjunction with the protection of property or officials or employees of the Corporation on or within lands or facilities other than those owned or leased by the Corporation; or
(C) in cooperation with other Federal, State, or local law enforcement agencies.
(d) FEDERAL INVESTIGATIVE JURISDICTION AND STATE CIVIL AND CRIMINAL JURISDICTION NOT PREEMPTED.--Nothing in this section shall be construed to--
(1) limit or restrict the investigative jurisdiction of any Federal law enforcement agency; or
(2) affect any right of a State or a political subdivision thereof to exercise civil and criminal jurisdiction on or within lands or facilities owned or leased by the Corporation.
(e) DETERMINATION OF ADJOINING AREAS.--
(1) IN GENERAL.--The Board shall determine and may from time-to-time modify the adjoining areas for each facility or particular area of land, or for individual categories of such facilities or lands, for the purposes of subsection (c)(1).
(2) NOTICE.--A notice and description of each adjoining area determination or modification of a determination made under paragraph (1) shall be published in the Federal Register.
(f) QUALIFICATIONS AND TRAINING.--The Board, in consultation with the Attorney General, shall adopt qualification and training standards for law enforcement agents designated under subsection (a).
(g) RELATION TO OTHER LAW.--A law enforcement agent designated under subsection (a) shall not be considered to be a law enforcement officer of the United States for the purposes of any other law; and no law enforcement agent designated under subsection (a) or other employee of the Corporation shall receive an increase in compensation solely on account of this section.
(h) RELATIONSHIP WITH ATTORNEY GENERAL.--The duties and powers of law enforcement agents designated under subsection (a) that are described in subsection (b) shall be exercised in accordance with guidelines approved by the Attorney General.

    

7



Sec. 5. The Board is hereby authorized--
(a) To contract with commercial producers for the production of such fertilizers or fertilizer materials as may be needed in the Government's program of development and introduction in excess of that produced by Government plants. Such contracts may provide either for outright purchase of materials by the Board or only for the payment of carrying charges on special materials manufactured at the Board's request for its program.
(b) To arrange with farmers and farm organizations for large-scale practical use of the new forms of fertilizers under conditions permitting an accurate measure of the economic return they produce.
(c) To cooperate with National, State, district, or county experimental stations or demonstration farms, with farmers, landowners, and associations of farmers or landowners, for the use of new forms of fertilizer or fertilizer practices during the initial or experimental period of their introduction, and for promoting the prevention of soil erosion by the use of fertilizers and otherwise.
(d) The Board in order to improve and cheapen the production of fertilizer is authorized to manufacture and sell fixed nitrogen, fertilizer, and fertilizer ingredients at Muscle Shoals by the employment of existing facilities, by modernizing existing plants, or by any other process or processes that in its judgment shall appear wise and profitable for the fixation of atmospheric nitrogen or the cheapening of the production of fertilizer.
(e) Under the authority of this Act the Board may make donations or sales of the product of the plant or plants operated by it to be fairly and equitably distributed through the agency of county demonstration agents, agricultural colleges, or otherwise as the Board may direct, for experimentation, education, and introduction of the use of such products in cooperation with practical farmers so as to obtain information as to the value, effect, and best methods of their use.
(f) The Board is authorized to make alterations, modifications, or improvements in existing plants and facilities, and to construct new plants.
(g) In the event it is not used for the fixation of nitrogen for agricultural purposes or leased, then the Board shall maintain in standby condition nitrate plant numbered 2, or its equivalent, for the fixation of atmospheric nitrogen, for the production of explosives in the event of war or a national emergency, until the Congress shall by joint resolution release the Board from this obligation, and if any part thereof be used by the Board for the manufacture of phosphoric acid or potash, the balance of nitrate plant numbered 2 shall be kept in standby condition.
(h) To establish, maintain, and operate laboratories and experimental plants, and to undertake experiments for the purpose of enabling the Corporation to furnish nitrogen products for military purposes, and nitrogen and other fertilizer products for agricultural purposes in the most economical manner and at the highest standard of efficiency.
(i) To request the assistance and advice of any officer, agent, or employee of any executive department or of any independent office of the United States, to enable the Corporation the better to carry out its power successfully, and as far as practicable shall utilize the services of such officers, agents, and employees, and the President shall, if in his opinion, the public interest, service, or economy so require, direct that such assistance, advice, and service be rendered to the Corporation, and any individual that may be by the President directed to render such assistance, advice, and service shall be thereafter subject to the orders, rules, and regulations of the Board: Provided , That

8



any invention or discovery made by virtue of and incidental to such service by an employee of the Government of the United States serving under this section, or by any employee of the Corporation, together with any patents which may be granted thereon, shall be the sole and exclusive property of the Corporation, which is hereby authorized to grant such licenses thereunder as shall be authorized by the Board: Provided further , That the Board may pay to such inventor such sum from the income from sale of license as it may deem proper.
(j) Upon the requisition of the Secretary of War 2 or the Secretary of the Navy to manufacture for and sell at cost to the United States explosives or their nitrogenous content.
(k) Upon the requisition of the Secretary of War the Corporation shall allot and deliver without charge to the War Department so much power as shall be necessary in the judgment of said Department for use in operation of all locks, lifts, or other facilities in aid of navigation.
(l) To produce, distribute, and sell electric power, as herein particularly specified.
(m) Repealed.
(n) The President is authorized, within twelve months after the passage of this Act, to lease to any responsible farm organization or to any corporation organized by it nitrate plant numbered 2 and Waco Quarry, together with the railroad connecting said quarry with nitrate plant numbered 2, for a term not exceeding fifty years at a rental of not less than $1 per year, but such authority shall be subject to the express condition that the lessee shall use said property during the term of said lease exclusively for the manufacture of fertilizer and fertilizer ingredients to be used only in the manufacture of fertilizer by said lessee and sold for use as fertilizer. The said lessee shall covenant to keep said property in first-class condition, but the lessee shall be authorized to modernize said plant numbered 2 by the installation of such machinery as may be necessary, and is authorized to amortize the cost of said machinery and improvements over the term of said lease or any part thereof. Said lease shall also provide that the Board shall sell to the lessee power for the operation of said plant at the same schedule of prices that it charges all other customers for power of the same class and quantity. Said lease shall also provide that, if the said lessee does not desire to buy power of the publicly owned plant, it shall have the right to purchase its power for the operation of said plant of the Alabama Power Company or any other publicly or privately owned corporation engaged in the generation and sale of electric power, and in such case the lease shall provide further that the said lessee shall have a free right of way to build a transmission line over Government property to said plant paying the actual expenses and damages, if any, incurred by the Corporation on account of such line. Said lease shall also provide that the said lessee shall covenant that during the term of said lease the said lessee shall not enter into any illegal monopoly, combination, or trust with any privately owned corporation engaged in the manufacture, production, and sale of fertilizer with the object or effect of increasing the price of fertilizer to the farmer. 3  
Sec. 6. In the appointment of officials and the selection of employees for said Corporation, and in the promotion of any such employees or officials, no political test or qualification shall be permitted or given consideration, but all such appointments and promotions shall be given and made








__________________________
2 Title changed to Secretary of the Army by 61 Stat. 501.

3 Subsection (n) of Section 5 is omitted from the United States Code as having been executed.

9



on the basis of merit and efficiency. Any member of said Board who is found by the President of the United States to be guilty of a violation of this section shall be removed from office by the President of the United States, and any appointee of said Board who is found by the Board to be guilty of a violation of this section shall be removed from office by said Board.
Sec. 7. In order to enable the Corporation to exercise the powers and duties vested in it by this Act—
(a) The exclusive use, possession, and control of the United States nitrate plants numbered 1 and 2, including steam plants, located, respectively, at Sheffield, Alabama, and Muscle Shoals, Alabama, together with all real estate and buildings connected therewith, all tools and machinery, equipment, accessories, and materials belonging thereto, and all laboratories and plants used as auxiliaries thereto; the fixed-nitrogen research laboratory, the Waco limestone quarry, in Alabama, and Dam Numbered 2, located at Muscle Shoals, its power house, and all hydroelectric and operating appurtenances (except the locks), and all machinery, lands, and buildings in connection therewith, and all appurtenances thereof, and all other property to be acquired by the Corporation in its own name or in the name of the United States of America, are hereby entrusted to the Corporation for the purposes of this Act.
(b) The President of the United States is authorized to provide for the transfer to the Corporation of the use, possession, and control of such other real or personal property of the United States as he may from time to time deem necessary and proper for the purposes of the Corporation as herein stated.
Sec. 8. (a) The Corporation shall maintain its principal office in the immediate vicinity of Muscle Shoals, Alabama. The Corporation shall be held to be an inhabitant and resident of the northern judicial district of Alabama within the meaning of the laws of the United States relating to the venue of civil suits.
(b) The Corporation shall at all times maintain complete and accurate books of accounts.
(c) Each member of the Board, before entering upon the duties of his office, shall subscribe to an oath (or affirmation) to support the Constitution of the United States and to faithfully and impartially perform the duties imposed upon him by this Act.
Sec. 9.
(a) The Board shall file with the President and with the Congress, in March of each year, a financial statement and a complete report as to the business of the Corporation covering the preceding governmental fiscal year. This report shall include an itemized statement of the cost of power at each power station, the total number of employees and the names, salaries, and duties of those receiving compensation at the rate of more than $1,500 a year.
(b) All purchases and contracts for supplies or services, except for personal services, made by the Corporation, shall be made after advertising, in such manner and at such times sufficiently in advance of opening bids, as the Board shall determine to be adequate to insure notice and opportunity for competition: Provided , That advertisement shall not be required when, (1) an emergency requires immediate delivery of the supplies or performance of the services; or (2) repair parts, accessories, supplemental equipment, or services are required for supplies or services previously furnished or contracted for; or (3) the aggregate amount involved in any purchase of supplies or procurement of services does not exceed $25,000; in which cases such purchases of

10



supplies or procurement of services may be made in the open market in the manner common among businessmen: Provided further , That in comparing bids and in making awards the Board may consider such factors as relative quality and adaptability of supplies or services, the bidder's financial responsibility, skill, experience, record of integrity in dealing, ability to furnish repairs and maintenance services, the time of delivery or performance offered, and whether the bidder has complied with the specifications.
(c) AUDITS.--The Comptroller General of the United States shall audit the transactions of the Corporation at such times as he shall determine, but not less frequently than once each governmental fiscal year, with personnel of his selection. In such connection he and his representatives shall have free and open access to all papers, books, records, files, accounts, plants, warehouse, offices, and all other things, property, and places belonging to or under the control of or used or employed by the Corporation, and shall be afforded full facilities for counting all cash and verifying transactions with and balances in depositories. He shall make report of each such audit in quadruplicate, one copy for the President of the United States, one for the chairman of the Board, one for public inspection at the principal office of the Corporation, and the other to be retained by him for the uses of the Congress: Provided , That such report shall not be made until the Corporation shall have had reasonable opportunity to examine the exceptions and criticisms of the Comptroller General or the General Accounting Office, to point out errors therein, explain or answer the same, and to file a statement which shall be submitted by the Comptroller General with his report. The expenses for each such audit shall be paid from any appropriation or appropriations for the General Accounting Office, and such part of such expenses as may be allocated to the cost of generating, transmitting, and distributing electric energy shall be reimbursed promptly by the Corporation as billed by the Comptroller General. 4  
Nothing in this Act shall be construed to relieve the Treasurer or other accountable officers or employees of the Corporation from compliance with the provisions of existing law requiring the rendition of accounts for adjustment and settlement pursuant to section 236, Revised Statutes, as amended by section 305 of the Budget and Accounting Act, 1921 (42 Stat. 24), and accounts for all receipts and disbursements by or for the Corporation shall be rendered accordingly: Provided , That, subject only to the provisions of the Tennessee Valley Authority Act of 1933, as amended, the Corporation is authorized to make such expenditures and to enter into such contracts, agreements, and arrangements, upon such terms and conditions and in such manner as it may deem necessary, including the final settlement of all claims and litigation by or against the Corporation; and, notwithstanding the provisions of any other law governing the expenditure of public funds, the General Accounting Office, in the settlement of the accounts of the Treasurer or other accountable officer or employee of the Corporation, shall not disallow credit for, nor withhold funds because of, any expenditure which the Board shall determine to have been necessary to carry out the provisions of said Act.
(d) ADMINISTRATIVE ACCOUNTS AND BUSINESS DOCUMENTS.--The Corporation shall determine its own system of administrative accounts and the forms and contents of its contracts








__________________________
4 While not expressly repealed, the provisions of the second paragraph of section 9(b) were superseded by 59 Stat. 599 (31 U.S.C. secs. 9105-9106).

11



and other business documents except as otherwise provided in the Tennessee Valley Authority Act of 1933, as amended.
Sec. 9a. The Board is hereby directed in the operation of any dam or reservoir in its possession and control to regulate the stream flow primarily for the purposes of promoting navigation and controlling floods. So far as may be consistent with such purposes, the Board is authorized to provide and operate facilities for the generation of electric energy at any such dam for the use of the Corporation and for the use of the United States or any agency thereof, and the Board is further authorized, whenever an opportunity is afforded, to provide and operate facilities for the generation of electric energy in order to avoid the waste of water power, to transmit and market such power as in this Act provided, and thereby, so far as may be practicable, to assist in liquidating the cost or aid in the maintenance of the projects of the Authority.
Sec. 9b. RECREATIONAL ACCESS .
(a) DEFINITION OF FLOATING CABIN.--In this section, the term “floating cabin” means a watercraft or other floating structure--
(1) primarily designed and used for human habitation or occupation; and
(2) not primarily designed or used for navigation or transportation on water.
(b) RECREATIONAL ACCESS.--The Board may allow the use of a floating cabin if--
(1) the floating cabin is maintained by the owner to reasonable health, safety, and environmental standards, as required by the Board;
(2) the Corporation has authorized the use of recreational vessels on the waters; and
(3) the floating cabin was located on waters under the jurisdiction of the Corporation as of the date of enactment of this section.
(c) FEES.--The Board may levy fees on the owner of a floating cabin on waters under the jurisdiction of the Corporation for the purpose of ensuring compliance with subsection (b) if the fees are necessary and reasonable for such purpose.
(d) CONTINUED RECREATIONAL USE.--
(1) IN GENERAL.--With respect to a floating cabin located on waters under the jurisdiction of the Corporation on the date of enactment of this section, the Board--
(A) may not require the removal of the floating cabin--
(i) in the case of a floating cabin that was granted a permit by the Corporation before the date of enactment of this section, for a period of 15 years beginning on such date of enactment; and
(ii) in the case of a floating cabin not granted a permit by the Corporation before the date of enactment of this section, for a period of 5 years beginning on such date of enactment; and
(B) shall approve and allow the use of the floating cabin on waters under the jurisdiction of the Corporation at such time and for such duration as--
(i) the floating cabin meets the requirements of subsection (b); and
(ii) the owner of the floating cabin has paid any fee assessed pursuant to subsection (c).
(2) SAVINGS PROVISIONS.--
(A) Nothing in this subsection restricts the ability of the Corporation to enforce reasonable health, safety, or environmental standards.
(B) This section applies only to floating cabins located on waters under the jurisdiction of the Corporation.

12



(e) NEW CONSTRUCTION.--The Corporation may establish regulations to prevent the construction of new floating cabins.
Sec. 10. The Board is hereby empowered and authorized to sell the surplus power not used in its operations, and for operation of locks and other works generated by it, to States, counties, municipalities, corporations, partnerships, or individuals, according to the policies hereinafter set forth; and to carry out said authority, the Board is authorized to enter into contracts for such sale for a term not exceeding twenty years, and in the sale of such current by the Board it shall give preference to States, counties, municipalities, and cooperative organizations of citizens or farmers, not organized or doing business for profit, but primarily for the purpose of supplying electricity to its own citizens or members; Provided , That all contracts made with private companies or individuals for the sale of power, which power is to be resold for a profit, shall contain a provision authorizing the Board to cancel said contract upon five years’ notice in writing, if the Board needs said power to supply the demands of States, counties, or municipalities. In order to promote and encourage the fullest possible use of electric light and power on farms within reasonable distance of any of its transmission lines the Board in its discretion shall have power to construct transmission lines to farms and small villages that are not otherwise supplied with electricity at reasonable rates, and to make such rules and regulations governing such sale and distribution of such electric power as in its judgment may be just and equitable: Provided further , That the Board is hereby authorized and directed to make studies, experiments, and determinations to promote the wider and better use of electric power for agricultural and domestic use, or for small or local industries, and it may cooperate with State governments, or their subdivisions or agencies, with educational or research institutions, and with cooperatives or other organizations, in the application of electric power to the fuller and better balanced development of the resources of the region: Provided further , That the Board is authorized to include in any contract for the sale of power such terms and conditions, including resale rate schedules, and to provide for such rules and regulations as in its judgment may be necessary or desirable for carrying out the purposes of this Act, and in case the purchaser shall fail to comply with any such terms and conditions, or violate any such rules and regulations, said contract may provide that it shall be voidable at the election of the Board: Provided further , That in order to supply farms and small villages with electric power directly as contemplated by this section, the Board in its discretion shall have power to acquire existing electric facilities used in serving such farms and small villages: And provided further , That the terms “States,” “counties,” and “municipalities” as used in this Act shall be construed to include the public agencies of any of them unless the context requires a different construction.
Sec. 11. It is hereby declared to be the policy of the Government so far as practical to distribute and sell the surplus power generated at Muscle Shoals equitably among the States, counties, and municipalities within transmission distance. This policy is further declared to be that the projects herein provided for shall be considered primarily as for the benefit of the people of the section as a whole and particularly the domestic and rural consumers to whom the power can economically be made available, and accordingly that sale to and use by industry shall be a secondary purpose, to be utilized principally to secure a sufficiently high load factor and revenue returns which will permit domestic and rural use at the lowest possible rates and in such manner as to encourage increased domestic and rural use of electricity. It is further hereby declared to be the policy of the

13



Government to utilize the Muscle Shoals properties so far as may be necessary to improve, increase, and cheapen the production of fertilizer ingredients by carrying out the provisions of this Act.
Sec. 12. In order to place the Board upon a fair basis for making such contracts and for receiving bids for the sale of such power, it is hereby expressly authorized, either from appropriations made by Congress or from funds secured from the sale of such power, or from funds secured by the sale of bonds hereafter provided for, to construct, lease, purchase, or authorize the construction of transmission lines within transmission distance from the place where generated, and to interconnect with other systems. The Board is also authorized to lease to any person, persons, or corporation the use of any transmission line owned by the Government and operated by the Board, but no such lease shall be made that in any way interferes with the use of such transmission lines by the Board: Provided , That if any State, county, municipality, or other public or cooperative organization of citizens or farmers, not organized or doing business for profit but primarily for the purpose of supplying electricity to its own citizens or members, or any two or more of such municipalities or organizations, shall construct or agree to construct and maintain a properly designed and built transmission line to the Government reservation upon which is located a Government generating plant, or to a main transmission line owned by the Government or leased by the Board and under the control of the Board, the Board is hereby authorized and directed to contract with such State, county, municipality, or other organization, or two or more of them, for the sale of electricity for a term not exceeding thirty years; and in any such case the Board shall give to such State, county, municipality, or other organization ample time to fully comply with any local law now in existence or hereafter enacted providing for the necessary legal authority for such State, county, municipality, or other organization to contract with the Board for such power. Provided further , That all contracts entered into between the Corporation and any municipality or other political subdivision or cooperative organization shall provide that the electric power shall be sold and distributed to the ultimate consumer without discrimination as between consumers of the same class, and such contract shall be voidable at the election of the Board if a discriminatory rate, rebate, or other special concession is made or given to any consumer or user by the municipality or other political subdivision or cooperative organization: And provided further , That as to any surplus power not so sold as above provided to States, counties, municipalities, or other said organizations, before the Board shall sell the same to any person or corporation engaged in the distribution and resale of electricity for profit, it shall require said person or corporation to agree that any resale of such electric power by said person or corporation shall be made to the ultimate consumer of such electric power at prices that shall not exceed a schedule fixed by the Board from time to time as reasonable, just, and fair; and in case of any such sale, if an amount is charged the ultimate consumer which is in excess of the price so deemed to be just, reasonable, and fair by the Board, the contract for such sale between the Board and such distributor of electricity shall be voidable at the election of the Board: And provided further, That the Board is hereby authorized to enter into contracts with other power systems for the mutual exchange of unused excess power upon suitable terms, for the conservation of stored water, and as an emergency or breakdown relief.
Sec. 12a. In order (1) to facilitate the disposition of the surplus power of the Corporation according to the policies set forth in this Act; (2) to give effect to the priority herein accorded to

14



States, counties, municipalities, and nonprofit organizations in the purchase of such power by enabling them to acquire facilities for the distribution of such power; and (3) at the same time to preserve existing distribution facilities as going concerns and avoid duplication of such facilities, the Board is authorized to advise and cooperate with and assist, by extending credit for a period of not exceeding five years to States, counties, municipalities and non-profit organizations situated within transmission distance from any dam where such power is generated by the Corporation in acquiring, improving, and operating (a) existing distribution facilities and incidental works, including generating plants; and (b) interconnecting transmission lines; or in acquiring any interest in such facilities, incidental works, and lines.
Sec. 13. In order to render financial assistance to those States and local governments in which the power operations of the Corporation are carried on and in which the Corporation has acquired properties previously subject to State and local taxation, the Board is authorized and directed to pay to said States, and the counties therein, for each fiscal year, beginning July 1, 1940, the following percentages of the gross proceeds derived from the sale of power by the Corporation for the preceding fiscal year as hereinafter provided, together with such additional amounts as may be payable pursuant to the provisions hereinafter set forth, said payments to constitute a charge against the power operations of the Corporation: For the fiscal year (beginning July 1, 1940, 10 per centum; 1941, 9 per centum; 1942, 8 per centum; 1943, 7-1/2 per centum; 1944, 7 per centum; 1945, 6-1/2 per centum; 1946, 6 per centum; 1947, 5-1/2 per centum; 1948 and each fiscal year thereafter, 5 per centum. 5 “Gross proceeds,” as used in this section, is defined as the total gross proceeds derived by the Corporation from the sale of power for the preceding fiscal year, excluding power used by the Corporation or sold or delivered to any other department or agency of the Government of the United States for any purpose other than the resale thereof. The payments herein authorized are in lieu of taxation, and the Corporation, its property, franchises and income, are hereby expressly exempted from taxation in any manner or form by any State, county, municipality, or any subdivision or district thereof.
The payment for each fiscal year shall be apportioned among said States in the following manner: One-half of said payment shall be apportioned by paying to each State the percentage thereof which the gross proceeds of the power sales by the Corporation within said State during the preceding fiscal year bears to the total gross proceeds from all power sales by the Corporation during the preceding fiscal year; the remaining one-half of said payment shall be apportioned by paying to each State the percentage thereof which the book value of the power property held by the Corporation within said State at the end of the preceding fiscal year bears to the total book value of all such property held by the Corporation on the same date. The book value of power property shall include that portion of the investment allocated or estimated to be allocable to power: Provided , That the minimum annual payment to each State (including payments to counties therein) shall not be less than an amount equal to the two-year average of the State and local ad valorem property taxes levied against power property purchased and operated by the Corporation in said State and against that portion of reservoir lands related to dams constructed by or an behalf of the United







__________________________
5 Section 114(a) of P.L. No. 94-274 directed TVA to make payments in lieu of taxes for the fiscal year transition period from July 1, 1976, through September 30, 1976, in a manner that was consistent with the payments made for the immediately preceding fiscal year.

15



States Government and held or operated by the Corporation and allocated or estimated to be allocable to power. The said two-year average shall be calculated for the last two years during which said property was privately owned and operated or said land was privately owned: Provided further , That the minimum annual payment to each State in which the Corporation owns and operates power property (including payments to counties therein) shall not be less than $10,000 in any case: Provided further , That the corporation shall pay directly to the respective counties the two-year average of county ad valorem property taxes (including taxes levied by taxing districts within the respective counties) upon power property and reservoir lands allocable to power, determined as above provided, and all payments to any such county within a State shall be deducted from the payment otherwise due to such State under the provisions of this section. The determination of the Board of the amounts due hereunder to the respective States and counties shall be final.
The payments above provided shall in each case be made to the State or county in equal monthly installments beginning not later than July 31, 1940.
Nothing herein shall be construed to limit the authority of the Corporation in its contracts for the sale of power to municipalities, to permit or provide for the resale of power at rates which may include an amount to cover tax-equivalent payments to the municipality in lieu of State, county, and municipal taxes upon any distribution system or property owned by the municipality, or any agency thereof, conditioned upon a proper distribution by the municipality of any amounts collected by it in lieu of State or county taxes upon any such distribution system or property; it being the intention of Congress that either the municipality or the State in which the municipality is situated shall provide for the proper distribution to the State and county of any portion of tax equivalent so collected by the municipality in lieu of State or county taxes upon any such distribution system or property.
The Corporation shall, not later than January 1, 1945, submit to the Congress a report on the operation of the provisions of this section, including a statement of the distribution to the various States and counties hereunder; the effect of the operation of the provisions of this section on State and local finances; an appraisal of the benefits of the program of the Corporation to the States and counties receiving payments hereunder, and the effect of such benefits in increasing taxable values within such States and counties; and such other date, information, and recommendations as may be pertinent to future legislation.
Sec. 14. The Board shall make a thorough investigation as to the present value of Dam Numbered 2, and the steam plants at nitrate plant numbered 1, and nitrate plant numbered 2, and as to the cost of Cove Creek Dam, for the purpose of ascertaining how much of the value or the cost of said properties shall be allocated and charged up to (1) flood control, (2) navigation, (3) fertilizer, (4) national defense, and (5) the development of power. The findings thus made by the Board, when approved by the President of the United States, shall be final, and such findings shall thereafter be used in all allocation of value for the purpose of keeping the book value of said properties. In like manner, the cost and book value of any dams, steam plants, or other similar improvements hereafter constructed and turned over to said Board for the purpose of control and management shall be ascertained and allocated.
The Board shall on or before January 1, 1937, file with Congress a statement of its allocation of the value of all such properties turned over to said Board, and which have been completed prior

16



to the end of the preceding fiscal year, and shall thereafter in its annual report to Congress file a statement of its allocation of the value of such properties as have been complete during the preceding fiscal year.
For the purpose of accumulating data useful to the Congress in the formulation of legislative policy in matters relating to the generation, transmission, and distribution of electric energy and the production of chemicals necessary to national defense and useful in agriculture, and to the Federal Power Commission and other Federal and State agencies, and to the public, the Board shall keep complete accounts of its costs of generation, transmission, and distribution of electric energy and shall keep a complete account of the total cost of generating and transmission facilities constructed or otherwise acquired by the Corporation, and of producing such chemicals, and a description of the major components of such costs according to such uniform system of accounting for public utilities as the Federal Power Commission has, and if it has none, then it is hereby empowered and directed to prescribe such uniform system of accounting, together with records of such other physical data and operating statistics of the Authority as may be helpful in determining the actual cost and value of services, and the practices, methods, facilities, equipment, appliances, and standards and sizes, types, location, and geographical and economic integration of plants and systems best suited to promote the public interest, efficiency, and the wider and more economical use of electric energy. Such data shall be reported to the Congress by the Board from time to time with appropriate analyses and recommendations, and, so far as practicable, shall be made available to the Federal Power Commission and other Federal and State agencies which may be concerned with the administration of legislation relating to the generation, transmission, or distribution of electric energy and chemicals useful to agriculture. It is hereby declared to be the policy of this Act that, in order, as soon as practicable, to make the power projects self-supporting and self-liquidating, the surplus power shall be sold at rates which, in the opinion of the Board, when applied to the normal capacity of the Authority's power facilities, will produce gross revenues in excess of the cost of production of said power and in addition to the statement of the cost of power at each power station as required by section 9(a) of the “Tennessee Valley Act of 1933,” the Board shall file with each annual report, a statement of the total cost of all power generated by it at all power stations during each year, the average cost of such power per kilowatt hour, the rates at which sold, and to whom sold, and copies of all contracts for the sale of power.
Sec. 15. In the construction of any future dam, steam plant, or other facility, to be used in whole or in part for the generation or transmission of electric power the Board is hereby authorized and empowered to issue on the credit of the United States and to sell serial bonds not exceeding $50,000,000 in amount, having a maturity not more than fifty years from the date of issue thereof, and bearing interest not exceeding 3-1/2 per centum per annum. Said bonds shall be issued and sold in amounts and prices approved by the Secretary of the Treasury, but all such bonds as may be so issued and sold shall have equal rank. None of said bonds shall be sold below par, and no fee, commission, or compensation whatever shall be paid to any person, firm, or corporation for handling, negotiating the sale, or selling the said bonds. All of such bonds so issued and sold shall have all the rights and privileges accorded by law to Panama Canal bonds, authorized by section 8 of the Act of June 28, 1902, chapter 1302, as amended by the Act of December 21, 1905 (ch. 3, sec.

17



1, 34 Stat. 5), as now compiled in section 743 of title 31 of the United States Code. All funds derived from the sale of such bonds shall be paid over to the Corporation.
Sec. 15a. With the approval of the Secretary of the Treasury, the Corporation is authorized to issue bonds not to exceed in the aggregate $50,000,000 outstanding at any one time, which bonds may be sold by the Corporation to obtain funds to carry out the provisions of section 12a of this Act. Such bonds shall be in such forms and denominations, shall mature within such periods not more than fifty years from the date of their issue, may be redeemable at the option of the Corporation before maturity in such manner as may be stipulated therein, shall bear such rates of interest not exceeding 3-1/2 per centum per annum, shall be subject to such terms and conditions, shall be issued in such manner and amount, and sold at such prices, as may be prescribed by the Corporation, with the approval of the Secretary of the Treasury: Provided , That such bonds shall not be sold at such prices or on such terms as to afford an investment yield to the holders in excess of 3-1/2 per centum per annum. Such bonds shall be fully and unconditionally guaranteed both as to interest and principal by the United States, and such guaranty shall be expressed on the face thereof, and such bonds shall be lawful investments, and may be accepted as security for all fiduciary, trust, and public funds, the investment or deposit of which shall be under the authority or control of the United States or any officer or officers thereof. In the event that the Corporation should not pay upon demand, when due, the principal of, or interest on, such bonds, the Secretary of the Treasury shall pay to the holder the amount thereof, which is hereby authorized to be appropriated out of any moneys in the Treasury not otherwise appropriated, and thereupon to the extent of the amount so paid the Secretary of the Treasury shall succeed to all the rights of the holders of such bonds. The Secretary of the Treasury, in his discretion, is authorized to purchase any bonds issued hereunder, and for such purpose the Secretary of the Treasury is authorized to use as a public-debt transaction the proceeds from the sale of any securities hereafter issued under the Second Liberty Bond Act, as amended, and the purposes for which securities may be issued under such Act, as amended, are extended to include any purchases of the Corporation’s bonds hereunder. The Secretary of the Treasury may, at any time, sell any of the bonds of the Corporation acquired by him under this section. All redemptions, purchases, and sales by the Secretary of the Treasury of the bonds of the Corporation shall be treated as public-debt transactions of the United States. With the approval of the Secretary of the Treasury, the Corporation shall have power to purchase such bonds in the open market at any time and at any price. No bonds shall be issued hereunder to provide funds or bonds necessary for the performance of any proposed contract negotiated by the Corporation under the authority of section 12a of this Act until the proposed contract shall have been submitted to and approved by the Federal Power Commission. When any such proposed contract shall have been submitted to the said Commission, the matter shall be given precedence and shall be in every way expedited and the Commission’s determination of the matter shall be final. The authority of the Corporation to issue bonds hereunder shall expire at the end of five years from the date when this section as amended herein becomes law, except that such bonds may be issued at any time after the expiration of said period to provide bonds or funds necessary for the performance of any contract entered into by the Corporation, prior to the expiration of said period, under the authority of section 12a of this Act.

18



Sec. 15b. No bonds shall be issued by the Corporation after the date of enactment of this section under section 15 or section 15a.
Sec. 15c. With the approval of the Secretary of the Treasury the Corporation is authorized, after the date of enactment of this section, to issue bonds not to exceed in the aggregate $61,500,000. Such bonds may be sold by the Corporation to obtain funds which may be used for the following purposes only:
(1) Not to exceed $46,000,000 may be used for the purchase of electric utility properties of the Tennessee Electric Power Company and Southern Tennessee Power Company as contemplated in the contract between the Corporation and the Commonwealth and Southern Corporation and others, dated as of May 12, 1939.
(2) Not to exceed $6,500,000 may be used for the purchase and rehabilitation of electric utility properties of the Alabama Power Company and Mississippi Power Company in the following named counties in northern Alabama and northern Mississippi: The counties of Jackson, Madison, Limestone, Lauderdale, Colbert, Lawrence, Morgan, Marshall, DeKalb, Cherokee, Cullman, Winston, Franklin, Marion, and Lamar in northern Alabama, and the counties of Calhoun, Chickasaw, Monroe, Clay, Lowndes, Oktibbeha, Choctaw, Webster, Noxubee, Winston, Neshoba, and Kemper in northern Mississippi.
(3) Not to exceed $3,500,000 may be used for rebuilding, replacing, and repairing electric utility properties purchased by the Corporation in accordance with the foregoing provisions of this section.
(4) Not to exceed $3,500,000 may be used for constructing electric transmission lines, substations, and other electrical facilities necessary to connect the electric utility properties purchased by the Corporation in accordance with the foregoing provisions of this section with the electric power system of the Corporation.
(5) Not to exceed $2,000,000 may be used for making loans under section 12a to States, counties, municipalities, and nonprofit organizations to enable them to purchase any electric utility properties referred to in the contract between the Corporation and the Commonwealth and Southern Corporation and others, dated as of May 12, 1939, or any electric utility properties of the Alabama Power Company or Mississippi Power Company in any of the counties in northern Alabama or northern Mississippi named in paragraph (2).
The Corporation shall file with the President and with the Congress in December of each year a financial statement and complete report as to the expenditure of funds derived from the sale of bonds under this section covering the period not covered by an such previous statement or report. Such bonds shall be in such forms and denominations, shall mature within such periods not more than fifty years from the date of their issue, may be redeemable at the option of the Corporation before maturity in such manner as may be stipulated therein, shall bear such rates of interest not exceeding 3-1/2 per centum per annum, shall be subject to such terms and conditions, shall be issued in such manner and amount, and sold at such prices, as may be prescribed by the Corporation with the approval of the Secretary of the Treasury: Provided , That such bonds shall not be sold at such prices or on such terms as to afford an investment yield to the holders in excess of 3-1/2 per centum per annum. Such bonds shall be fully and unconditionally guaranteed both as to interest and principal by the United States, and such guaranty shall be expressed on the face thereof, and such bonds shall

19



be lawful investments, and may be accepted as security for fiduciary, trust, and public funds, the investment or deposit of which shall be under the authority or control of the United States or any officer or officers thereof. In the event that the Corporation should not pay upon demand when due, the principal of, or interest on, such bonds, the Secretary of the Treasury shall pay to the holder the amount thereof, which is hereby authorized to be appropriated out of any moneys in the Treasury not otherwise appropriated, and thereupon to the extent of the amount so paid the Secretary of the Treasury shall succeed to all the rights of the holders of such bonds. The Secretary of the Treasury, in his discretion, is authorized to purchase any bonds issued hereunder, and for such purpose the Secretary of the Treasury is authorized to use as a public-debt transaction the proceeds from the sale of any securities hereafter issued under the Second Liberty Bond Act, as amended, and the purposes for which securities may be issued under such Act, as amended, are extended to include any purchases of the Corporation’s bonds hereunder. The Secretary of the Treasury may, at any time, sell any of the bonds of the Corporation acquired by him under this section. All redemptions, purchases, and sales by the Secretary of the Treasury of the bonds of the Corporation shall be treated as public-debt transactions of the United States. With the approval of the Secretary of the Treasury, the Corporation shall have power to purchase such bonds in the open market at any time and at any price. None of the proceeds of the bonds shall be used for the performance of any proposed contract negotiated by the Corporation under the authority of section 12a of this Act until the proposed contract shall have been submitted to and approved by the Federal Power Commission. When any such proposed contract shall have been submitted to the said Commission, the matter shall be given precedence and shall be in every way expedited and the Commission’s determination of the matter shall be final. The authority of the Corporation to issue bonds under this section shall expire January 1, 1941, except that if at the time such authority expires the amount of bonds issued by the Corporation under this section is less than $61,500,000, the Corporation may, subject to the foregoing provisions of this section, issue, after the expiration of such period, bonds in an amount not in excess of the amount by which the bonds so issued prior to the expiration of such period is less than $61,500,000 for refunding purposes, or, subject to the provisions of paragraph (5) of this section (limiting the purposes for which loans under section 12a of funds derived from bond proceeds may be made) to provide funds found necessary in the performance of any contract entered into by the Corporation prior to the expiration of such period, under the authority of section 12a.
Sec. 15d. (a) The Corporation is authorized to issue and sell bonds, notes and other evidences of indebtedness (hereinafter collectively referred to as “bonds”) in an amount not exceeding $30,000,000,000 outstanding at any one time to assist in financing its power program and to refund such bonds. The Corporation may, in performing functions authorized by this Act, use the proceeds of such bonds for the construction, acquisition, enlargement, improvement, or replacement of any plant or other facility used or to be used for the generation or transmission of electric power (including the portion of any multiple-purpose structure used or to be used for power generation); as may be required in connection with the lease, lease-purchase, or any contract for the power output of any such plant or other facility; and for other purposes incidental thereto. Unless otherwise specifically authorized by Act of Congress the Corporation shall make no contracts for the sale or delivery of power which would have the effect of making the Corporation or its distributors, directly or

20



indirectly, a source of power supply outside the area for which the Corporation or its distributors were the primary source of power supply on July 1, 1957, and such additional area extending not more than five miles around the periphery of such area as may be necessary to care for the growth of the Corporation and its distributors within said area: Provided, however, That such additional area shall not in any event increase by more than 2-1/2 per centum (or two thousand square miles, whichever is the lesser) the area for which the Corporation and its distributors were the primary source of power supply on July 1, 1957; And provided further , That no part of such additional area may be in a State not now served by the Corporation or its distributors or in a municipality receiving electric service from another source on or after July 1, 1957, and no more than five hundred square miles of such additional area may be in any one State now served by the Corporation or its distributors.
Nothing in this subsection shall prevent the Corporation or its distributors from supplying electric power to any customer within any area in which the Corporation or its distributors had generally established electric service on July 1, 1957, and to which electric service was not being supplied from any other source on the effective date of this Act.
Nothing in this subsection shall prevent the Corporation, when economically feasible, from making exchange power arrangements with other power-generating organizations with which the Corporation had such arrangements on July 1, 1957, nor prevent the Corporation from continuing to supply power to Dyersburg, Tennessee, and Covington, Tennessee, or from entering into contracts to supply or from supplying power to the cities of Paducah, Kentucky; Princeton, Kentucky; Glasgow, Kentucky; Fulton, Kentucky; Monticello, Kentucky; Hickman, Kentucky; Chickamauga, Georgia; Ringgold, Georgia; Oak Ridge, Tennessee; and South Fulton, Tennessee; or agencies thereof; or from entering into contracts to supply or from supplying power for the Naval Auxiliary Air Station in Lauderdale and Kemper Counties, Mississippi, through the facilities of the East Mississippi Electric Power Association: Provided further, That nothing herein contained shall prevent the transmission of TVA power to the Atomic Energy Commission or the Department of Defense or any agency thereof, on certification by the President of the United States that an emergency defense need for such power exists. Nothing in this Act shall affect the present rights of the parties in any existing lawsuits involving efforts of towns in the same general area where TVA power is supplied to obtain TVA power.
The principal of and interest on said bonds shall be payable solely from the Corporation’s net power proceeds as hereinafter defined. Net power proceeds are defined for purposes of this section as the remainder of the Corporation’s gross power revenues after deducting the costs of operating, maintaining, and administering its power properties (including costs applicable to that portion of its multiple-purpose properties allocated to power) and payments to States and counties in lieu of taxes but before deducting depreciation accruals or other charges representing the amortization of capital expenditures, plus the net proceeds of the sale or other disposition of any power facility or interest therein, and shall include reserve or other funds created from such sources. Notwithstanding the provisions of section 26 of this Act or any other provision of law, the Corporation may pledge and use its net power proceeds for payment of the principal of and interest on said bonds, for purchase or redemption thereof, and for other purposes incidental thereto, including creation of reserve funds and other funds which may be similarly pledged and used, to such extent and in such manner as it

21



may deem necessary or desirable. The Corporation is authorized to enter into binding covenants with the holders of said bonds--and with the trustee, if any--under any indenture, resolution, or other agreement entered into in connection with the issuance thereof (any such agreement being hereinafter referred to as a “bond contract”) with respect to the establishment of reserve funds and other funds, adequacy of charges for supply of power, application and use of net power proceeds, stipulations concerning the subsequent issuance of bonds or the execution of leases or lease-purchase agreements relating to power properties, and such other matters, not inconsistent with this Act, as the Corporation may deem necessary or desirable to enhance the marketability of said bonds. The issuance and sale of bonds by the Corporation and the expenditure of bond proceeds for the purposes specified herein, including the addition of generating units to existing power-producing projects and the construction of additional power-producing projects, shall not be subject to the requirements or limitations of any other law.
(b) Bonds issued by the Corporation hereunder shall not be obligations of, nor shall payment of the principal thereof or interest thereon be guaranteed by, the United States. Proceeds realized by the Corporation from issuance of such bonds and from power operations and the expenditure of such proceeds shall not be subject to apportionment under the provisions of Revised Statutes 3679, as amended (31 U.S.C. 665). 6  
(c) Bonds issued by the Corporation under this section shall be negotiable instruments unless otherwise specified therein, shall be in such forms and denominations, shall be sold at such times and in such amounts, shall mature at such time or times not more than fifty years from their respective dates, shall be sold at such prices, shall bear such rates of interest, may be redeemable before maturity at the option of the Corporation in such manner and at such times and redemption premiums, may be entitled to such relative priorities of claim on the Corporation’s net power proceeds with respect to principal and interest payments, and shall be subject to such other terms and conditions, as the Corporation may determine: Provided, That at least fifteen days before selling each issue of bonds hereunder (exclusive of any commitment shorter than one year) the Corporation shall advise the Secretary of the Treasury as to the amount, proposed date of sale, maturities, terms and conditions and expected rates of interest of the proposed issue in the fullest detail possible and, if the Secretary shall so request, shall consult with him or his designee thereon, but the sale and issuance of bonds shall not be subject to approval by the Secretary of the Treasury except as to the time of issuance, and the maximum rates of interest to be borne by the bonds: Provided further , That if the Secretary of the Treasury does not approve a proposed issue of bonds hereunder within seven working days following the date on which he is advised of the proposed sale, the Corporation may issue to the Secretary interim obligations in the amount of the proposed issue, which the Secretary is directed to purchase. In case the Corporation determines that a proposed issue of bonds hereunder cannot be sold on reasonable terms, it may issue to the Secretary interim obligations which the Secretary is authorized to purchase. Notwithstanding the foregoing provisions of this subsection, obligations issued by the Corporation to the Secretary shall not exceed $150,000,000 outstanding at any one time, shall mature on or before one year from date of issue, and shall bear interest equal to the










__________________________
6 With the codification of title 31, U.S.C., by 96 Stat. 990, these provisions of Revised Statutes 3679 were included in 31 U.S.C. secs. 1511-1519.

22



average rate (rounded to the nearest one-eighth of a percent) on outstanding marketable obligations of the United States with maturities from dates of issue of one year or less as of the close of the month preceding the issuance of the obligations of the Corporation. If agreement is not reached within eight months concerning the issuance of any bonds which the Secretary has failed to approve, the Corporation may nevertheless proceed to sell such bonds on any date thereafter without approval by the Secretary in amount sufficient to retire the interim obligations issued to the Treasury and such interim obligations shall be retired from the proceeds of such bonds. For the purpose of any purchase of the Corporation’s obligations the Secretary of the Treasury is authorized to use as a public debt transaction the proceeds from the sale of any securities issued under the Second Liberty Bond Act, as amended, and the purposes for which securities may be issued under the Second Liberty Bond Act, as amended, are extended to include any purchases of the Corporation’s obligations hereunder. The Corporation may sell its bonds by negotiation or on the basis of competitive bids, subject to the right, if reserved, to reject all bids; may designate trustees, registrars, and paying agents in connection with said bonds and the issuance thereof; may arrange for audits of its accounts and for reports concerning its financial condition and operations by certified public accounting firms (which audits and reports shall be in addition to those required by sections 105 and 106 of the Act of December 6, 1945 (59 Stat. 599; 31 U.S.C. 850-851), 7 may, subject to any covenants contained in any bond contract, invest the proceeds of any bonds and other funds under its control which derive from or pertain to its power program in any securities approved for investment of national bank funds and deposit said proceeds and other funds, subject to withdrawal by check or otherwise, in any Federal Reserve Bank or bank having membership in the Federal Reserve System; and may perform such other acts not prohibited by law as it deems necessary or desirable to accomplish the purposes of this section. Bonds issued by the Corporation hereunder shall contain a recital that they are issued pursuant to this section, and such recital shall be conclusive evidence of the regularity of the issuance and sale of such bonds and of their validity. The annual report of the Board filed pursuant to section 9 of this Act shall contain a detailed statement of the operation of the provisions of this section during the year.
(d) Bonds issued by the Corporation hereunder shall be lawful investments and may be accepted as security for all fiduciary, trust, and public funds, the investment or deposit of which shall be under the authority or control of any officer or agency of the United States. The Secretary of the Treasury or any other officer or agency having authority over or control of any such fiduciary, trust, or public funds, may at any time sell any of the bonds of the Corporation acquired by them under this section. Bonds issued by the Corporation hereunder shall be exempt both as to principal and interest from all taxation now or hereafter imposed by any State or local taxing authority except estate, inheritance, and gift taxes.
(e) From net power proceeds in excess of those required to meet the Corporation’s obligations under the provisions of any bond or bond contract, the Corporation shall, beginning with fiscal year 1961, make payments into the Treasury as miscellaneous receipts on or before September 30, of each fiscal year as a return on the appropriation investment in the Corporation’s power facilities,







__________________________
7 With the codification of title 31, U.S.C., by 96 Stat. 990, the provisions of sections 105 and 106 of the Act of December 6, 1945, were included in 31 U.S.C. secs. 9106-9106.

23



plus a repayment sum of not less than $10,000,000 for each of the first five fiscal years, $15,000,000 for each of the next five fiscal years, and $20,000,000 for each fiscal year thereafter, which repayment sum shall be applied to reduction of said appropriation investment until a total of $1,000,000,000 of said appropriation investment shall have been repaid. 8 The said appropriation investment shall consist, in any fiscal year, of that part of the Corporation’s total investment assigned to power as of the beginning of the fiscal year (including both completed plant and construction in progress) which has been provided from appropriations or by transfers of property from other Government agencies without reimbursement by the Corporation, less repayments of such appropriation investment made under title II of the Government Corporations Appropriation Act, 1948, this Act, or other applicable legislation. The payment as a return on the appropriation investment in each fiscal year shall be equal to the computed average interest rate payable by the Treasury upon its total marketable public obligations as of the beginning of said fiscal year applied to said appropriation investment. Payments due hereunder may be deferred for not more than two years when, in the judgment of the Board of Directors of the Corporation, such payments cannot feasibly be made because of inadequacy of funds occasioned by drought, poor business conditions, emergency replacements, or other factors beyond the control of the Corporation.
(f) The Corporation shall charge rates for power which will produce gross revenues sufficient to provide funds for operation, maintenance, and administration of its power system; payments to States and counties in lieu of taxes; debt service on outstanding bonds, including provision and maintenance of reserve funds and other funds established in connection therewith; payments to the Treasury as a return on the appropriation investment pursuant to subsection (e) hereof; payment to the Treasury of the repayment sums specified in subsection (e) hereof; and such additional margin as the Board may consider desirable for investment in power system assets, retirement of outstanding bonds in advance of maturity, additional reduction of appropriation investment, and other purposes connected with the Corporation’s power business having due regard for the primary objectives of the Act, including the objective that power shall be sold at rates as low as are feasible. In order to protect the investment of holders of the Corporation’s securities and the appropriation investment as defined in subsection (e) hereof, the Corporation, during each successive five-year period beginning with the five-year period which commences on July 1 of the first full fiscal year after the effective date of this section, shall apply net power proceeds either in reduction (directly or through payments into reserve or sinking funds) of its capital obligations, including bonds and the appropriation investment, or to reinvestment in power assets, at least to the extent of the combined amount of the aggregate of the depreciation accruals and other charges representing the amortization of capital expenditures applicable to its power properties plus the net proceeds realized from any











__________________________
8 Section 114(b) of P.L. No. 94-274 directed TVA to make a payment of $5,000,000 on September 30, 1976, as repayment of the appropriation investment plus a payment as a return on the appropriation investment for the fiscal year transition period from July 1, 1976, through September 30, 1976, computed at the average interest rate payable by the Treasury upon its total marketable public obligations as of July 1, 1976, applied to the balance of appropriations as of July 1, 1976.

24



disposition of power facilities in said period. As of October 1, 1975, the five-year periods described herein shall be computed as beginning on October 1 of that year and of each fifth year thereafter.
(g) Power generating and related facilities operated by the Corporation under lease and lease-purchase agreements shall constitute power property held by the Corporation within the meaning of section 13 of this Act, but that portion of the payment due for any fiscal year under said section 13 to a State where such facilities are located which is determined or estimated by the Board to result from holding such facilities or selling electric energy generated thereby shall be reduced by the amount of any taxes or tax equivalents applicable to such fiscal year paid by the owners or others on account of said facilities to said State and to local taxing jurisdictions therein. In connection with the construction of a generating plant or other facilities under an agreement providing for lease or purchase of said facilities or any interest therein by or on behalf of the Corporation, or for the purchase of the output thereof, the Corporation may convey, in the name of the United States by deed, lease, or otherwise, any real property in its possession or control, may perform necessary engineering and construction work and other services, and may enter into any necessary contractual arrangements.
(h) It is hereby declared to be the intent of this section to aid the Corporation in discharging its responsibility for the advancement of the national defense and the physical, social and economic development of the area in which it conducts its operations by providing it with adequate authority and administrative flexibility to obtain the necessary funds with which to assure an ample supply of electric power for such purposes by issuance of bonds and as otherwise provided herein, and this section shall be construed to effectuate such intent.
Sec. 16. The Board, whenever the President deems it advisable, is hereby empowered and directed to complete Dam Numbered 2 at Muscle Shoals, Alabama, and the steam plant at nitrate plant numbered 2, in the vicinity of Muscle Shoals, by installing in Dam Numbered 2 the additional power units according to the plans and specifications of said dam, and the additional power unit in the steam plant at nitrate plant numbered 2.
Sec. 17. The Secretary of War, or the Secretary of the Interior, is hereby authorized to construct, either directly or by contract to the lowest responsible bidder, after due advertisement, a dam in and across Clinch River in the State of Tennessee, which has by long custom become known and designated as the Cove Creek Dam, together with a transmission line from Muscle Shoals, according to the latest and most approved designs, including power house and hydroelectric installations and equipment for the generation of power, in order that the waters of the said Clinch River may be impounded and stored above said dam for the purpose of increasing and regulating the flow of the Clinch River and the Tennessee River below, so that the maximum amount of primary power may be developed at Dam Numbered 2 and at any and all other dams below the said Cove Creek Dam: Provided , however , That the President is hereby authorized by appropriate order to direct the employment by the Secretary of War, or by the Secretary of the Interior, of such engineer or engineers as he may designate, to perform such duties and obligations as he may deem proper, either in the drawing of plans and specifications for said dam, or to perform any other work in the building or construction of the same. The President may, by such order, place the control of the construction of said dam in the hands of such engineer or engineers taken from private life as he may desire: And provided further , That the President is hereby expressly authorized, without regard to the restriction or limitation of any other statute, to select attorneys and assistants for the purpose of





25



making any investigation he may deem proper to ascertain whether, in the control and management of Dam Numbered 2, or any other dam or property owned by the Government in the Tennessee River Basin, or in the authorization of any improvement therein, there has been any undue or unfair advantage given to private persons, partnerships, or corporations, by any officials or employees of the Government, or whether in any such matters the Government has been injured or unjustly deprived of any of its rights. 9
Sec. 18. In order to enable and empower the Secretary of War, the Secretary of the Interior, or the Board to carry out the authority hereby conferred, in the most economical and efficient manner, he or it is hereby authorized and empowered in the exercise of the powers of national defense in aid of navigation, and in the control of the flood waters of the Tennessee and Mississippi Rivers, constituting channels of interstate commerce, to exercise the right of eminent domain for all purposes of this Act, and to condemn all lands, easements, rights of way, and other area necessary in order to obtain a site for said Cove Creek Dam, and the flowage rights for the reservoir of water above said dam, and to negotiate and conclude contracts with States, counties, municipalities, and all State agencies and with railroads, railroad corporations, common carriers, and all public utility commissions and any other person, firm, or corporation, for the relocation of railroad tracks, highways, highway bridges, mills, ferries, electric-light plants, and any and all other properties, enterprises, and projects whose removal may be necessary in order to carry out the provisions of this Act. When said Cove Creek Dam, transmission line, and power house shall have been completed, the possession, use, and control thereof shall be entrusted to the Corporation for use and operation in connection with the general Tennessee Valley project, and to promote flood control and navigation in the Tennessee River.
Sec. 19. The Corporation, as an instrumentality and agency of the Government of the United States for the purpose of executing its constitutional powers, shall have access to the United States Patent and Trademark Office for the purpose of studying, ascertaining, and copying all methods, formula, and scientific information (not including access to pending applications for patents) necessary to enable the Corporation to use and employ the most efficacious and economical process for the production of fixed nitrogen, or any essential ingredient of fertilizer, or any method of improving and cheapening the production of hydroelectric power, and any owner of a patent whose patent rights may have been thus in any way copied, used, infringed, or employed by the exercise of this authority by the Corporation shall have as the exclusive remedy a cause of action against the Corporation to be instituted and prosecuted on the equity side of the appropriate district court of the United States, for the recovery of reasonable compensation for such infringement. The Under Secretary of Commerce for Intellectual Property and Director of the United States Patent and Trademark Office shall furnish to the Corporation, at its request and without payment of fees, copies of documents on file in his office: Provided , That the benefits of this section shall not apply to any art, machine, method of manufacture, or composition of matter, discovered or invented by such employee during the time of his employment or service with the Corporation or with the Government of the United States.








__________________________
9 Text of section 17 is omitted from the United States Code as having been executed.

26



Sec. 20. The Government of the United States hereby reserves the right, in case of war or national emergency declared by Congress, to take possession of all or any part of the property described or referred to in this Act for the purpose of manufacturing explosives or for other war purposes; but, if this right is exercised by the Government, it shall pay the reasonable and fair damages that may be suffered by any party whose contract for the purchase of electric power or fixed nitrogen or fertilizer ingredients is hereby violated, after the amount of the damages has been fixed by the United States Claims Court in proceedings instituted and conducted for that purpose under rules prescribed by the court.
Sec. 21. (a) All general penal statutes relating to the larceny, embezzlement, conversion, or to the improper handling, retention, use, or disposal of public moneys or property of the United States, shall apply to the moneys and property of the Corporation and to moneys and properties of the United States entrusted to the Corporation.
(b) Any person who, with intent to defraud the Corporation, or to deceive any director, officer, or employee of the Corporation or any officer or employee of the United States (1) makes any false entry in any book of the Corporation, or (2) makes any false report or statement for the Corporation, shall, upon conviction thereof, be fined not more than $10,000 or imprisoned not more than five years, or both.
(c) Any person who shall receive any compensation, rebate, or reward, or shall enter into any conspiracy, collusion, or agreement, express or implied, with intent to defraud the Corporation or wrongfully and unlawfully to defeat its purposes, shall, on conviction thereof, be fined not more than $5,000 or imprisoned not more than five years, or both.
Sec. 22. To aid further the proper use, conservation, and development of the natural resources of the Tennessee River drainage basin and of such adjoining territory as may be related to or materially affected by the development consequent to this Act, and to provide for the general welfare of the citizens of said areas, the President is hereby authorized, by such means or methods as he may deem proper within the limits of appropriations made therefor by Congress, to make such surveys of and general plans for said Tennessee basin and adjoining territory as may be useful to the Congress and to the several States in guiding and controlling the extent, sequence, and nature of development that may be equitably and economically advanced through the expenditure of public funds, or through the guidance or control of public authority, all for the general purpose of fostering an orderly and proper physical, economic, and social development of said areas; and the President is further authorized in making said surveys and plans to cooperate with the States affected thereby, or subdivisions or agencies of such States, or with cooperative or other organizations, and to make such studies, experiments, or demonstrations as may be necessary and suitable to that end.
Sec. 23. The President shall, from time to time, as the work provided for in the preceding section progresses, recommend to Congress such legislation as he deems proper to carry out the general purposes stated in said section, and for the especial purpose of bringing about in said Tennessee drainage basin and adjoining territory in conformity with said general purposes (1) the maximum amount of flood control; (2) the maximum development of said Tennessee River for navigation purposes; (3) the maximum generation of electric power consistent with flood control and navigation; (4) the proper use of marginal lands; (5) the proper method of reforestation of all lands in said drainage basin suitable for reforestation; and (6) the economic and social well-being of the people living in said river basin.
    

27



Sec. 24. For the purpose of securing any rights of flowage, or obtaining title to or possession of any property, real or personal, that may be necessary or may become necessary, in the carrying out of any of the provisions of this Act, the President of the United States for a period of three years from the date of the enactment of this Act, is hereby authorized to acquire title in the name of the United States to such rights or such property, and to provide for the payment for same by directing the Board to contract to deliver power generated at any of the plants now owned or hereafter owned or constructed by the Government or by said Corporation, such future delivery of power to continue for a period not exceeding thirty years. Likewise, for one year after the enactment of this Act, the President is further authorized to sell or lease any parcel or part of any vacant real estate now owned by the Government in said Tennessee River Basin, to persons, firms, or corporations who shall contract to erect thereon factories or manufacturing establishments, and who shall contract to purchase of said Corporation electric power for the operation of any such factory or manufacturing establishment. No contract shall be made by the President for the sale of any of such real estate as may be necessary for present or future use on the part of the Government for any of the purposes of this Act. Any such contract made by the President of the United States shall be carried out by the Board: Provided , That no such contract shall be made that will in any way abridge or take away the preference right to purchase power given in this Act to States, counties, municipalities, or farm organizations: Provided further , That no lease shall be for a term to exceed fifty years: Provided further , That any sale shall be on condition that said land shall be used for industrial purposes only.
Sec. 25. The Corporation may cause proceedings to be instituted for the acquisition by condemnation of any lands, easements, or rights of way, which, in the opinion of the Corporation, are necessary to carry out the provisions of this Act. The proceedings shall be instituted in the United States district court for the district in which the land, easement, right of way, or other interest, or any part thereof, is located, and such court shall have full jurisdiction to divest the complete title to the property sought to be acquired out of all persons or claimants and vest the same in the United States in fee simple, and to enter a decree quieting the title hereto in the United States of America.
Sec. 26. Commencing July 1, 1936, the proceeds for each fiscal year derived by the Board from the sale of power or any other products manufactured by the Corporation, and from any other activities of the Corporation including the disposition of any real or personal property, shall be paid into the Treasury of the United States on March 31 of each year, save and except such part of such proceeds as in the opinion of the Board shall be necessary for the Corporation in the operation of dams and reservoirs, in conducting its business in generating, transmitting, and distributing electric energy and in manufacturing, selling, and distributing fertilizer and fertilizer ingredients. 10 A continuing fund of $1,000,000 is also excepted from the requirements of this section and may be withheld by the Board to defray emergency expenses and to insure continuous operation: Provided , That nothing in this section shall be construed to prevent the use by the Board, after June 30, 1936, of proceeds accruing prior to July 1, 1936, for the payment of obligations lawfully incurred prior to such latter date.
    








__________________________
10 Section 205(5) of P.L. No. 94-274 provided that for the purposes of section 26 of the TVA Act the fiscal year transition period from July 1, 1976, through September 30, 1976, shall be treated as part of the fiscal year beginning October 1, 1976.

28



Sec. 26a. The unified development and regulation of the Tennessee River system requires that no dam, appurtenant works, or other obstruction, affecting navigation, flood control, or public lands or reservations shall be constructed, and thereafter operated or maintained across, along, or in the said river or any of its tributaries until plans for such construction, operation, and maintenance shall have been submitted to and approved by the Board; and the construction, commencement of construction, operation, or maintenance of such structures without such approval is hereby prohibited. When such plans shall have been approved, deviation therefrom either before or after completion of such structures is prohibited unless the modification of such plans has previously been submitted to and approved by the Board.
In the event the Board shall, within sixty days after their formal submission to the Board, fail to approve any plans or modifications, as the case may be, for construction, operation, or maintenance of any such structures on the Little Tennessee River, the above requirements shall be deemed satisfied, if upon application to the Secretary of War, with due notice to the Corporation, and hearing thereon, such plans or modifications are approved by the said Secretary of War as reasonably adequate and effective for the unified development and regulation of the Tennessee River system.
Such construction, commencement of construction, operation, or maintenance of any structure or parts thereof in violation of the provisions of this section may be prevented, and the removal or discontinuation thereof required by the injunction or order of any district court exercising jurisdiction in any district in which such structures or parts thereof may be situated, and the Corporation is hereby authorized to bring appropriate proceedings to this end.
The requirements of this section shall not be construed to be a substitute for the requirements of any other law of the United States or of any State, now in effect or hereafter enacted, but shall be in addition thereto, so that any approval, license, permit or other sanction now or hereafter required by the provisions of any such law for the construction, operation, or maintenance of any structures whatever, except such as may be constructed, operated or maintained by the Corporation shall be required, notwithstanding the provisions of this section.
Sec. 27. All appropriations necessary to carry out the provisions of this Act are hereby authorized.
Sec. 28. That all Acts or parts of Acts in conflict herewith are hereby repealed, so far as they affect the operations contemplated by this Act.
Sec. 29. The right to alter, amend, or repeal this Act is hereby expressly declared and reserved, but no such amendment or repeal shall operate to impair the obligation of any contract made by said Corporation under any power conferred by this Act.
Sec. 30. The sections of this Act are hereby declared to be separable, and in the event any one or more sections of this Act be held to be unconstitutional, the same shall not affect the validity of other sections of this Act. 11  
Sec. 31. This Act shall be liberally construed to carry out the purposes of Congress to provide for the disposition of and make needful rules and regulations respecting Government properties entrusted to the Authority, provide for the national defense, improve navigation, control destructive







__________________________
11 Section 15 of the 1935 amendments to the TVA Act (49 Stat. 1081) contained similar language applicable to the provisions enacted by those amendments.

29



floods, and promote interstate commerce and the general welfare, but no real estate shall be held except what is necessary in the opinion of the Board to carry out plans and projects actually decided upon requiring the use of such land: Provided , That any land purchased by the Authority and not necessary to carry out plans and projects actually decided upon shall be sold by the Authority as agent of the United States, after due advertisement, at public auction to the highest bidder, or at private sale as provided in section 4(k) of this Act.




30



THE FOLLOWING PROVISIONS OF LAW, ENACTED AS SECTION 604 OF THE ENERGY AND WATER DEVELOPMENT APPROPRIATIONS ACT, 2005 (DIVISION C OF PUBLIC LAW 108-447), WERE NOT AMENDMENTS TO THE TVA ACT AND ARE ONLY “TRANSITIONAL” PROVISIONS OF LAW WHICH HAVE BEEN CODIFIED AS A NOTE UNDER 16 USC 831a.


SEC. 604. APPOINTMENTS; EFFECTIVE DATE; TRANSITION .

(a) APPOINTMENTS.--
(1) IN GENERAL.--As soon as practicable after the date of enactment of this Act, the President shall submit to the Senate nominations of six persons to serve as members of the Board of Directors of the Tennessee Valley Authority in addition to the members serving on the date of enactment of this Act.
(2) INITIAL TERMS.--Notwithstanding section 2(d) of the Tennessee Valley Authority Act of 1933 (as amended by this title), in making the appointments under paragraph (1), the President shall appoint--
(A) two members for a term to expire on May 18, 2007;
(B) two members for a term to expire on May 18, 2009; and
(C) two members for a term to expire on May 18, 2011.
(b) EFFECTIVE DATE.--The amendments made by this title take effect on the later of--
(1) the date on which at least three persons nominated under subsection (a) take office; or
(2) May 18, 2005.
(c) SELECTION OF CHAIRMAN.--The Board of Directors of the Tennessee Valley Authority shall select one of the members to act as chairman of the Board not later than 30 days after the effective date specified in subsection (b).
(d) CONFLICT-OF-INTEREST POLICY.--The Board of Directors of the Tennessee Valley Authority shall adopt and submit to Congress a conflict-of-interest policy, as required by section 2(g)(1)(E) of the Tennessee Valley Authority Act of 1933 (as amended by this title), as soon as practicable after the effective date specified in subsection (b).
(e) TRANSITION.--A person who is serving as a member of the board of directors of the Tennessee Valley Authority on the date of enactment of this Act--
(1) shall continue to serve until the end of the current term of the member; but
(2) after the effective date specified in subsection (b), shall serve under the terms of the Tennessee Valley Authority Act of 1933 (as amended by this title).






31


 

EXHIBIT 31.1


RULE 13a-14(a)/15d-14(a) CERTIFICATION

I, William D. Johnson, certify that:
1.
I have reviewed this Quarterly Report on Form 10-Q of the Tennessee Valley Authority;
2.
Based on my knowledge, this report does not contain any untrue statement of a material fact or omit to state a material fact necessary to make the statements made, in light of the circumstances under which such statements were made, not misleading with respect to the period covered by this report;
3.
Based on my knowledge, the financial statements, and other financial information included in this report, fairly present in all material respects the financial condition, results of operations and cash flows of the registrant as of, and for, the periods presented in this report;
4.
The registrant's other certifying officer and I are responsible for establishing and maintaining disclosure controls and procedures (as defined in Exchange Act Rules 13a-15(e) and 15d-15(e)) and internal control over financial reporting (as defined in Exchange Act Rules 13a-15(f) and 15d-15(f)) for the registrant and we have:
a)
Designed such disclosure controls and procedures, or caused such disclosure controls and procedures to be designed under our supervision, to ensure that material information relating to the registrant, including its consolidated subsidiaries, is made known to us by others within those entities, particularly during the period in which this report is being prepared;
b)
Designed such internal control over financial reporting, or caused such internal control over financial reporting to be designed under our supervision, to provide reasonable assurance regarding the reliability of financial reporting and the preparation of financial statements for external purposes in accordance with generally accepted accounting principles;
c)
Evaluated the effectiveness of the registrant's disclosure controls and procedures and presented in this report our conclusions about the effectiveness of the disclosure controls and procedures, as of the end of the period covered by this report based on such evaluation; and
d)
Disclosed in this report any change in the registrant's internal control over financial reporting that occurred during the registrant's most recent fiscal quarter (the registrant's fourth fiscal quarter in the case of an annual report) that has materially affected, or is reasonably likely to materially affect, the registrant's internal control over financial reporting; and
5.
The registrant's other certifying officer and I have disclosed, based on our most recent evaluation of internal control over financial reporting, to the registrant's auditors and the audit committee of the registrant's board of directors (or persons performing the equivalent functions):
a)
All significant deficiencies and material weaknesses in the design or operation of internal control over financial reporting which are reasonably likely to adversely affect the registrant's ability to record, process, summarize and report financial information; and
b)
Any fraud, whether or not material, that involves management or other employees who have a significant role in the registrant's internal control over financial reporting.
 
Date:
January 30, 2017
/s/ William D. Johnson
 
William D. Johnson
 
President and Chief Executive Officer
 
 
(Principal Executive Officer)


 





 

EXHIBIT 31.2

RULE 13a-14(a)/15d-14(a) CERTIFICATION

I, John M. Thomas, III, certify that:
1.
I have reviewed this Quarterly Report on Form 10-Q of the Tennessee Valley Authority;
2.
Based on my knowledge, this report does not contain any untrue statement of a material fact or omit to state a material fact necessary to make the statements made, in light of the circumstances under which such statements were made, not misleading with respect to the period covered by this report;
3.
Based on my knowledge, the financial statements, and other financial information included in this report, fairly present in all material respects the financial condition, results of operations and cash flows of the registrant as of, and for, the periods presented in this report;
4.
The registrant's other certifying officer and I are responsible for establishing and maintaining disclosure controls and procedures (as defined in Exchange Act Rules 13a-15(e) and 15d-15(e)) and internal control over financial reporting (as defined in Exchange Act Rules 13a-15(f) and 15d-15(f)) for the registrant and we have:
a)
Designed such disclosure controls and procedures, or caused such disclosure controls and procedures to be designed under our supervision, to ensure that material information relating to the registrant, including its consolidated subsidiaries, is made known to us by others within those entities, particularly during the period in which this report is being prepared;
b)
Designed such internal control over financial reporting, or caused such internal control over financial reporting to be designed under our supervision, to provide reasonable assurance regarding the reliability of financial reporting and the preparation of financial statements for external purposes in accordance with generally accepted accounting principles;
c)
Evaluated the effectiveness of the registrant's disclosure controls and procedures and presented in this report our conclusions about the effectiveness of the disclosure controls and procedures, as of the end of the period covered by this report based on such evaluation; and
d)
Disclosed in this report any change in the registrant's internal control over financial reporting that occurred during the registrant's most recent fiscal quarter (the registrant's fourth fiscal quarter in the case of an annual report) that has materially affected, or is reasonably likely to materially affect, the registrant's internal control over financial reporting; and
5.
The registrant's other certifying officer and I have disclosed, based on our most recent evaluation of internal control over financial reporting, to the registrant's auditors and the audit committee of the registrant's board of directors (or persons performing the equivalent functions):
a)
All significant deficiencies and material weaknesses in the design or operation of internal control over financial reporting which are reasonably likely to adversely affect the registrant's ability to record, process, summarize and report financial information; and
b)
Any fraud, whether or not material, that involves management or other employees who have a significant role in the registrant's internal control over financial reporting.
 
Date:
January 30, 2017
/s/ John M. Thomas, III
 
John M. Thomas, III

 
Executive Vice President and Chief Financial Officer
 
(Principal Financial Officer)

 





 

EXHIBIT 32.1
 

CERTIFICATION FURNISHED PURSUANT TO
SECURITIES EXCHANGE ACT RULE 13a-14(b)
 OR RULE 15d-14(b) AND 18 U.S.C. SECTION 1350,
AS ADOPTED PURSUANT TO
SECTION 906 OF THE SARBANES-OXLEY ACT OF 2002
 
In connection with the Quarterly Report on Form 10-Q of the Tennessee Valley Authority (the “Company”) for the quarter ended  December 31, 2016 , as filed with the Securities and Exchange Commission on the date hereof (the “Report”), I, William D. Johnson, President and Chief Executive Officer of the Company, certify, for the purposes of complying with Rule 13a-14(b) or Rule 15d-14(b) of the Securities Exchange Act of 1934, as amended, and Section 1350 of Chapter 63 of Title 18 of the United States Code, as adopted pursuant to Section 906 of the Sarbanes-Oxley Act of 2002, that:
 
(1) the Report fully complies with the requirements of section 13(a) or 15(d), as applicable, of the Securities Exchange Act of 1934, as amended; and
 
(2) the information contained in the Report fairly presents, in all material respects, the financial condition and results of operations of the Company.

/s/ William D. Johnson____________
William D. Johnson
President and Chief Executive Officer
(Principal Executive Officer)
January 30, 2017

 





 

EXHIBIT 32.2
 

CERTIFICATION FURNISHED PURSUANT TO
SECURITIES EXCHANGE ACT RULE 13a-14(b)
 OR RULE 15d-14(b) AND 18 U.S.C. SECTION 1350,
AS ADOPTED PURSUANT TO
SECTION 906 OF THE SARBANES-OXLEY ACT OF 2002
 
In connection with the Quarterly Report on Form 10-Q of the Tennessee Valley Authority (the “Company”) for the quarter ended  December 31, 2016 , as filed with the Securities and Exchange Commission on the date hereof (the “Report”), I, John M. Thomas, III, Executive Vice President and Chief Financial Officer of the Company, certify, for the purposes of complying with Rule 13a-14(b) or Rule 15d-14(b) of the Securities Exchange Act of 1934, as amended, and Section 1350 of Chapter 63 of Title 18 of the United States Code, as adopted pursuant to Section 906 of the Sarbanes-Oxley Act of 2002, that:
 
(1) the Report fully complies with the requirements of section 13(a) or 15(d), as applicable, of the Securities Exchange Act of 1934, as amended; and
 
(2) the information contained in the Report fairly presents, in all material respects, the financial condition and results of operations of the Company.

/s/ John M. Thomas, III
John M. Thomas, III
Executive Vice President and Chief Financial Officer
(Principal Financial Officer)
January 30, 2017