UNITED STATES

SECURITIES AND EXCHANGE COMMISSION
Washington, D.C. 20549

 

Form 8-K

 

Current Report Pursuant to Section 13 or 15(d) of

the Securities Act of 1934

 

Date of Report (Date of earliest event reported): June 24, 2019

 

Ocean Power Technologies, Inc.

(Exact name of registrant as specified in its charter)

 

Delaware   001-33417   22-2535818

(State or other jurisdiction

of incorporation)

 

(Commission

File Number)

 

(I.R.S. Employer

Identification No.)

 

28 Engelhard Drive, Suite B

Monroe Township, New Jersey

  08831
(Address of principal executive offices)   ( Zip Code)

 

(609) 730-0400

(Registrant’s telephone number, including area code)

 

Check the appropriate box below if the Form 8-K filing is intended to simultaneously satisfy the filing obligation of the registrant under any of the following provisions (see General Instruction A.2. below):

 

  [  ] Written communications pursuant to Rule 425 under the Securities Act (17 CFR 230.425)
     
  [  ] Soliciting material pursuant to Rule 14a-12 under the Exchange Act (17 CFR 240.14a-12)
     
  [  ] Pre-commencement communications pursuant to Rule 14d-2(b) under the Exchange Act (17 CFR 240.14-2(b))
     
  [  ] Pre-commencement communications pursuant to Rule 13e-4(c) under the Exchange Act (17 CRF 240.133-4(c))

 

Indicate by check mark whether the registrant is an emerging growth company as defined in Rule 405 of the Securities Act of 1933 (§230.405 of this chapter) or Rule 12b-2 of the Securities Exchange Act of 1934 (§240.12b-2 of this chapter).

 

Emerging growth company [  ]

 

If an emerging growth company, indicate by check mark if the registrant has elected not to use the extended transition period for complying with any new or revised financial accounting standards provided pursuant to Section 13(a) of the Exchange Act. [  ]

 

 

 

 
 

 

Item 1.01 Entry into a Material Definitive Agreement.

 

On June 24, 2019, Ocean Power Technologies, Inc. (the “Company”) entered into a contract amendment (the “Amendment”) with Premier Oil UK Limited (“PMO”) to amend the terms of the agreement by modifying the contract milestones such that delivery of the PB3 PowerBuoy for the initial trial phase shall occur no later than July 19, 2019 and the term of the agreement would be completed by approximately May 15, 2020.

 

The foregoing description of the Amendment is qualified in its entirety by reference to the full text of the Amendment, a copy of which is filed herewith as Exhibit 10.1.

 

Item 9.01 Financial Statements and Exhibits.

 

  Exhibits
     
  10.1 Amendment to Contract between Premier Oil UK Limited and the Company dated June 24, 2019.

 

 
 

 

SIGNATURE

 

Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned thereunto duly authorized.

 

    Ocean Power Technologies, Inc.
     
Dated: June 25, 2019   /s/ George H. Kirby
    George H. Kirby
    President and Chief Executive Officer

 

 
 

 

Exhibit Index

 

10.1 Amendment to Contract between Premier Oil UK Limited and the Company dated June 24, 2019.

 

 
 

 

CONTRACT NO: POUK/C2394

 

AMENDMENT NO: 02

 

between

 

PREMIER OIL UK LIMITED

 

and

 

OCEAN POWER TECHNOLOGIES INC.

 

FOR THE PROVISION OF INTELLIGENT MONITORING BUOY

 

     
 

 

Premier Oil UK Limited

 

This Amendment, dated 3 rd June, 2019 is made between

 

Premier Oil UK Limited, a company incorporated in Scotland (registered number SC048705) with its registered office at 4th Floor, Saltire Court, 20 Castle Terrace, Edinburgh, EH1 2EN and its principal place of business at Upper Denburn House, Prime Four Business Park, Kingswells Causeway, Kingswells, Aberdeen, AB15 8PU (the “COMPANY” as hereinafter defined)

 

AND

 

Ocean Power Technologies Inc., a company incorporated in the State of Delaware, United States of America (Company Registration Number is US Federal ID: 22-2535818 with its registered office at 28 Engelhard Drive, Monroe Township, New Jersey USA 08534 hereinafter called the CONTRACTOR

 

WHEREAS

 

The COMPANY and the CONTRACTOR entered into Contract No. POUK/C2394 (hereinafter referred to as the “CONTRACT”) whereby the CONTRACTOR agreed to provide the COMPANY with the provision of Intelligent Monitoring Buoy and Support Services.

 

The COMPANY and the CONTRACTOR now desire to enter into this Amendment No. 02 for the purpose of revising Exhibit 2 “CONTRACT Milestones” to incorporate the agreed milestones and dates for completion of those Milestones.

 

NOW THEREFORE IT IS AGREED AS FOLLOWS:

 

  1: Notwithstanding the date hereof this Amendment No. 02 is effective 3 rd June 2019
  2. The Milestones and dates in Exhibit 2 of the CONTRACT are deleted and replaced as per attached.

 

Save as specifically provided for herein, all other provisions of the CONTRACT shall remain unchanged by this Amendment.

 

POUK/C2394 Page 2 of 5 Date 03/06/2019
     
Approved for COMPANY   Approved for CONTRACTOR
 

 

Premier Oil UK Limited

 

IN WITNESS WHEREOF, each party hereto has caused this Amendment No. 02 to be executed by their duly authorised representatives as of the dates shown below:

 

For COMPANY:   For CONTRACTOR:
         
PREMIER OIL UK LIMITED   OCEAN POWER TECHNOLOGIES INC.
         
Signature: /s/ Calum Knowles   Signature: /s/ George Kirby
Name: Calum Knowles   Name: George Kirby
Title: Senior Contracts Engineer   Title: President & CEO
Date: June 3, 2019   Date: June 24, 2019

 

POUK/C2394 Page 3 of 5 Date 03/06/2019
     
Approved for COMPANY   Approved for CONTRACTOR
 

 

Premier Oil UK Limited

 

ATTACHMENT 1

TO

AMENDMENT NO. 02

 

 

 

 

 

POUK/C2394 Page 4 of 5 Date 03/06/2019
     
Approved for COMPANY   Approved for CONTRACTOR
 

 

Premier Oil UK Limited

 

EXHIBIT 2

 

Exhibit 2

 


Contract Milestones

 

Milestone   Date       Description
Ml   No later than 19 July 2019   Delivery Date   PB3 Delivered to Premier Oil Aberdeen nominated facility
             
M2   Ml+ 14 Days   Deemed “Fit for Purpose”   Completion of quayside payload re- assembly and Pre-Deployment Checklist. PB3 ready for load-out onto deployment vessel.
             
M3     Initial Trial Commencement   Completion of Offshore Commissioning of PB3
             
M4   M3 + 90 Days   Initial Trial Completion   Completion of the first three-month rental period
             
M5   M4+ 180 Days   Six Month Option Completion   Completion of the remaining six- month rental of the cumulative nine-month Rental Period
             
M6*   MS+ 14 Days   Redelivery Date   PB3 redelivered to Premier Oil Aberdeen nominated facility by Premier Oil at the conclusion of the Rental Period, subject to the term of the Rental Period. This date is intended to represent the end of the nine (9) month rental period.

 

Note: Milestone M6 subject to adjustment pending extension of Rental Period

 

POUK/C2394 Page 5 of 5 Date 03/06/2019
     
Approved for COMPANY   Approved for CONTRACTOR